$9.32Avg low bid / LF
$9.51Avg of all bids
$25.00Avg engineer's estimate
27Jobs · 40,473 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 3 | 395 | $22.41 | $33.77 |
| 2023 | 5 | 1,622 | $22.08 | $27.86 |
| 2022 | 2 | 398 | $28.73 | $32.26 |
| 2021 | 2 | 350 | $31.71 | $26.42 |
| 2020 | 4 | 34,774 | $7.48 | $8.13 |
| 2019 | 6 | 660 | $29.79 | $33.55 |
| 2018 | 5 | 2,274 | $13.44 | $13.58 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 16, 2024 | 6439-54-001 | MedinaSan Antonio | 155 LF | $20.00 | BECK-REIT & SONS, LTD. |
| Mar 6, 2024 | 0252-03-054 | BlancoAustin | 50 LF | $20.00 | TEXAS MATERIALS GROUP, INC. |
| Mar 5, 2024 | 0941-04-019 | VictoriaYoakum | 190 LF | $25.00 | HUNTER INDUSTRIES, LTD. |
| Nov 1, 2023 | 0264-04-054 | CokeSan Angelo | 67 LF | $78.13 | REECE ALBERT, INC. |
| Oct 5, 2023 | 0257-04-031 | EastlandBrownwood | 209 LF | $28.75 | JAY MILLS CONTRACTING, INCORPORATED |
| Sep 6, 2023 | 0914-33-088 | HaysAustin | 625 LF | $10.00 | D&S CONCRETE CONTRACTORS LLC |
| May 5, 2023 | 0251-06-036 | LampasasBrownwood | 709 LF | $25.00 | JAY MILLS CONTRACTING, INCORPORATED |
| May 5, 2023 | 0918-11-100 | KaufmanDallas | 12 LF | $50.00 | HODGES AND SON CONSTRUCTION COMPANY, INC. |
| Jun 30, 2022 | 0215-01-044 | ComalSan Antonio | 300 LF | $25.05 | WEBBER, LLC |
| Jan 7, 2022 | 0910-16-147 | SmithTyler | 98 LF | $40.00 | THK CONSTRUCTION LLC |
| Dec 2, 2021 | 0923-09-066 | EastlandBrownwood | 50 LF | $60.00 | HODGES AND SON CONSTRUCTION COMPANY, INC. |
| Aug 5, 2021 | 2502-01-021 | BellWaco | 300 LF | $27.00 | JAMES CONSTRUCTION GROUP, LLC |
| Oct 1, 2020 | 0902-90-141 | TarrantFort Worth | 33,594 LF | $7.00 | ZACHRY CONSTRUCTION CORPORATION |
| Jun 5, 2020 | 0923-06-058 | BrownBrownwood | 70 LF | $14.00 | PIERCE R & B LLC |
| May 7, 2020 | 0923-17-087 | ComancheBrownwood | 1,070 LF | $20.00 | ENCINO LANDSCAPE, INC. |
| Feb 7, 2020 | 0120-05-026 | HamiltonWaco | 40 LF | $60.00 | BIG CREEK CONSTRUCTION, LTD. |
| Dec 3, 2019 | 0483-01-056 | La SalleLaredo | 25 LF | $46.55 | HUNTER INDUSTRIES, LTD. |
| Oct 3, 2019 | 0681-01-023 | WichitaWichita Falls | 130 LF | $15.00 | PIERCE R & B LLC |
| Aug 6, 2019 | 0596-01-021 | HillWaco | 100 LF | $14.00 | BEAR CREEK CONTRACTING, LLC |
| May 8, 2019 | 0867-07-013 | San SabaBrownwood | 190 LF | $30.00 | BIG CREEK CONSTRUCTION, LTD. |
| May 7, 2019 | 0256-02-031 | StephensBrownwood | 25 LF | $150.00 | PEACHTREE CONSTRUCTION, LTD. |
| Feb 6, 2019 | 0867-07-013 | San SabaBrownwood | 190 LF | $30.00 | BIG CREEK CONSTRUCTION, LTD. |
| Nov 6, 2018 | 0906-00-185 | EctorOdessa | 220 LF | $10.00 | VIZCAINO, L.P. |
| Aug 8, 2018 | 0902-20-099 | WiseFort Worth | 324 LF | $25.00 | HODGES AND SON CONSTRUCTION COMPANY, INC. |
| Jul 11, 2018 | 0902-20-111 | WiseFort Worth | 1,156 LF | $12.00 | PIERCE R & B LLC |
| Apr 4, 2018 | 0902-40-027 | JackFort Worth | 444 LF | $10.00 | PIERCE R & B LLC |
| Feb 2, 2018 | 0774-03-014 | HamiltonWaco | 130 LF | $15.00 | OLDCASTLE MATERIALS TEXAS, INC. |