Bid Day Forecast: 0914-00-513

Travis · Dec 2, 2026 Sign up free
Set your company to personalize scores

CCSJ 0914-00-513 · lets Dec 2, 2026 · Travis, Austin · Various

$1,909,738Engineer's estimate Items at market: $1,709,909 (-10.5%)
$1,583,186Most likely low bid$1,469,781 to $1,681,357 (middle half)
4.9Expected bidders5 plan holders, 5 regular bidders
42/100Weak fitMarket only. Set your company for a personal score

Where the low bid should land

$1,296,145 (1 in 10 go lower)$1,749,769 (1 in 10 go higher)

From 16 comparable let jobs (district + work type, estimates of $763,895 to $4,774,344, last 3 years). 94% of them went under the estimate; the typical low bid was -17.1% vs estimate.

Bid / no-bid score

  • Competition17 / 25Jobs like this draw about 4.9 bidders.
  • Margin2 / 20Low bids land at 83% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Nov 2026 0016-03-125Hays · 6 bidders $2,797,454-12.2%
Sep 2026 0337-03-020Williamson · 4 bidders $2,174,856-14.3%
Apr 2026 0337-02-054Williamson · 4 bidders $2,388,456-6.9%
Mar 2026 3545-02-013Hays · 7 bidders $1,570,963-37.4%
Mar 2026 1776-02-021Hays · 7 bidders $1,788,338-22.6%
Feb 2026 0150-05-051Burnet · 6 bidders $2,897,632-9.8%
Feb 2026 0015-11-075Travis · 5 bidders $2,185,903+1.2%
Dec 2025 0322-01-052Bastrop · 6 bidders $2,047,396-24.3%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn AustinAvg bid vs est.Avg win vs est.Their typical bid here
BOBCAT SERVICES, INC. SharpestBidders 921 of 4 -5.4%-18.1% $1,806,916
LONE STAR PAVING COMPANYBidders 1604427 of 52 -1.0%-15.1% $1,889,712
HUNTER INDUSTRIES, LTD.Bidders 2406612 of 69 -1.0%-9.3% $1,891,444
TEXAS MATERIALS GROUP, INC.Bidders 71018112 of 74 3.6%-3.6% $1,979,263
Rucoba & Maya Construction, LLCBidders 931 of 2 14.3%-2.6% $2,183,001

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

50 of 53 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x 1 LS$523,850.32$0.0010 – $42,200,000.00 $523,85030.6%
351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")94 low bids · prices swing 22x 13,000 SY$35.01$15.00 – $325.00 $455,19426.6%
351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")124 low bids · prices swing 125x 6,000 SY$49.06$6.00 – $748.00 $294,38917.2%
351-7031 FLEXIBLE PAVEMENT STRUCTURE REPAIR 2.5"3 low bids 9,000 SY$26.93$18.66 – $45.25 $242,37314.2%
505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x 150 DAY$217.57$0.0010 – $16,487.00 $32,6361.9%
351-7001 FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")32 low bids · prices swing 52x 1,000 SY$30.34$21.01 – $1,100.00 $30,3441.8%
351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")36 low bids · prices swing 12x 500 SY$36.28$20.10 – $250.00 $18,1421.1%
790-7004 LANE CLOSURE(SETUP & REM)(TYP 4)5 low bids · prices swing 22x 15 EA$1,080.69$89.00 – $2,000.00 $16,2100.9%
790-7003 LANE CLOSURE(SETUP & REM)(TYP 3)7 low bids · prices swing 23x 25 EA$480.16$88.00 – $2,000.00 $12,0040.7%
666-7042 REFL PAV MRK TY I (W)(ARROW)(100MIL)328 low bids · prices swing 1,000x 60 EA$156.95$1.00 – $1,000.00 $9,4170.6%
666-7066 REFL PAV MRK TY I (W)(WORD)(100MIL)324 low bids · prices swing 1,000x 50 EA$184.78$1.00 – $1,000.00 $9,2390.5%
790-7006 LANE CLOSURE(SETUP & REM)(TYP 6)17 low bids · prices swing 33x 15 EA$473.42$45.00 – $1,500.00 $7,1010.4%
790-7009 LANE CLOSURE(SETUP & REM)(TYP 9)13 low bids · prices swing 17x 10 EA$570.58$75.00 – $1,250.00 $5,7060.3%
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN975 low bids · prices swing 7,870,000x 50 DAY$87.82$0.0010 – $7,870.00 $4,3910.3%
790-7002 LANE CLOSURE(SETUP & REM)(TYP 2)35 low bids · prices swing 1,250x 10 EA$414.16$1.00 – $1,250.00 $4,1420.2%