FM 2001 - Satterwhite Rd to SH 21
1776-02-021 · let Mar 4, 2026 · Hays, Austin · Overlay
$1,788,338Low bid: LONE STAR PAVING COMPANY-22.6% vs estimate $2,310,564
$67,610Left on the table3.8% gap to the second bid
7BiddersSpread 36% low to high
44Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONE STAR PAVING COMPANY | $1,788,338 | -22.6% | $67,610 | 0 | 4-$585,886 | |
| 2 | HUNTER INDUSTRIES, LTD. | $1,855,948 | +3.8% | -19.7% | $41,552 | 0 | 2-$433,685 |
| 3 | BOBCAT SERVICES, INC. | $1,897,500 | +6.1% | -17.9% | $84,496 | 1+$27,073 | 2-$466,683 |
| 4 | ALLEN KELLER COMPANY | $1,981,997 | +10.8% | -14.2% | $317,188 | 1+$10,090 | 3-$412,147 |
| 5 | DEAN WORD COMPANY, LTD. | $2,299,184 | +28.6% | -0.5% | $17,787 | 2+$36,827 | 1-$388,850 |
| 6 | TEXAS MATERIALS GROUP, INC. | $2,316,972 | +29.6% | 0.3% | $116,463 | ||
| 7 | CLARK CONSTRUCTION OF TEXAS, INC. | $2,433,435 | +36.1% | 5.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
LONE STAR PAVING COMPANY vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $9,800.00 | $124,338.57 | $523,850.32 | $114,539 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 12,074 SY | $39.75 | $34.67 | $49.06 | -$61,336 |
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 2,993 TON | $96.00 | $84.60 | $115.04 | -$34,120 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $10.00 | $170.46 | $217.57 | $16,046 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 120 DAY | $10.00 | $142.05 | $87.82 | $15,846 |
| 347-7002 TOM-C PG76-22 SAC-B | 6,825 TON | $108.00 | $105.97 | $130.62 | -$13,855 |
| 505-7002 TMA (MOBILE OPERATION) | 88 HR | $10.00 | $113.64 | $64.00 | $9,120 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1,150.00 | $3,041.73 | $11,585.04 | $7,567 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 3,698 EA | $0.5000 | $1.38 | $0.5715 | $3,254 |
| 3007-7001 BONDING COURSE | 14,128 GAL | $3.00 | $2.79 | $3.32 | -$2,967 |
| 354-7050 PLANE ASPH CONC PAV(1") | 15,500 SY | $0.8900 | $1.07 | $1.11 | $2,790 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 69,114 LF | $0.7600 | $0.8000 | $0.6515 | $2,765 |
| 354-7049 PLANE ASPH CONC PAV (0"- 1" EDGE MILL) | 3,639 SY | $0.9300 | $1.61 | $1.18 | $2,475 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 58,382 LF | $0.7600 | $0.8000 | $0.6629 | $2,335 |
| 662-7008 WK ZN PAV MRK NON-REMOV (W)6"(SLD) | 82,936 LF | $0.1900 | $0.2000 | $0.2750 | $829 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 70,058 LF | $0.1900 | $0.2000 | $0.2770 | $701 |
| 438-7014 CLEAN AND SEAL EXIST JTS (STRIP SEAL) | 43 LF | $210.00 | $220.45 | $57.79 | $449 |
| 134-7001 BACKFILL (TY A) | 295 STA | $131.50 | $130.20 | $224.26 | -$384 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,209 EA | $3.50 | $3.67 | $3.97 | $206 |
| 666-7421 REFL PAV MRK TY I (Y)6"(SLD)(060MIL) | 6,783 LF | $0.6100 | $0.6400 | $0.3278 | $203 |
Positive: the low bidder was cheaper on that item. These 20 items account for $66,463 of the $67,610 gap.
LONE STAR PAVING COMPANY: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $9,800.00 | $523,850.32 | 0.02x | -$514,050 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1,150.00 | $11,585.04 | 0.10x | -$41,740 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $10.00 | $217.57 | 0.05x | -$20,757 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 120 DAY | $10.00 | $87.82 | 0.11x | -$9,338 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2BOBCAT SERVICES, INC.: unbalanced items
Placed 3ALLEN KELLER COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 3,698 EA | $3.30 | $0.5715 | 5.77x | $10,090 |
| 500-7001 MOBILIZATION | 1 LS | $188,310.00 | $523,850.32 | 0.36x | -$335,540 |
| 134-7001 BACKFILL (TY A) | 295 STA | $66.14 | $224.26 | 0.29x | -$46,647 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $4,095.07 | $11,585.04 | 0.35x | -$29,960 |