SL 275 - Braker Ln to Morrow St
0015-11-075 · let Feb 4, 2026 · Travis, Austin · Overlay
$2,185,903Low bid: ALLEN KELLER COMPANY+1.2% vs estimate $2,158,947
$67,743Left on the table3.1% gap to the second bid
5BiddersSpread 58% low to high
63Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ALLEN KELLER COMPANY | $2,185,903 | 1.2% | $67,743 | 1+$12,489 | 1-$316,850 | |
| 2 | LONE STAR PAVING COMPANY | $2,253,646 | +3.1% | 4.4% | $250,361 | 0 | 2-$536,220 |
| 3 | HUNTER INDUSTRIES, LTD. | $2,504,006 | +14.6% | 16.0% | $349,770 | 0 | 1-$339,167 |
| 4 | TEXAS MATERIALS GROUP, INC. | $2,853,777 | +30.6% | 32.2% | $610,300 | 2+$134,630 | 1-$475,850 |
| 5 | BOBCAT SERVICES, INC. | $3,464,076 | +58.5% | 60.5% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ALLEN KELLER COMPANY vs LONE STAR PAVING COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $207,000.00 | $9,060.00 | $523,850.32 | -$197,940 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 109,634 SY | $0.8700 | $2.30 | $1.62 | $156,777 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 8,774 SY | $24.02 | $32.00 | $35.01 | $70,017 |
| 341-7056 D-GR HMA TY-D PG76-22 | 6,029 TON | $111.82 | $117.00 | $123.11 | $31,230 |
| 347-7002 TOM-C PG76-22 SAC-B | 6,195 TON | $116.79 | $119.50 | $130.62 | $16,788 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 7,380 EA | $2.72 | $0.5000 | $1.03 | -$16,384 |
| 662-7113 WK ZN PAV MRK SHT TERM (TAB)TY Y | 4,808 EA | $3.02 | $0.5000 | $1.11 | -$12,116 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $6,515.73 | $870.00 | $11,585.04 | -$11,291 |
| 505-7001 TMA (STATIONARY) | 30 DAY | $212.44 | $27.00 | $217.57 | -$5,563 |
| 505-7003 TMA (MOBILE OPERATION) | 30 DAY | $199.78 | $15.00 | $229.60 | -$5,543 |
| 662-7017 WK ZN PAV MRK NON-REMOV (W)24"(SLD) | 2,912 LF | $3.44 | $5.00 | $3.95 | $4,543 |
| 666-7184 RE PM TY II (W) 24" (SLD) | 2,912 LF | $3.44 | $5.00 | $3.83 | $4,543 |
| 666-7186 RE PM TY II (W) (ARROW) | 92 EA | $55.94 | $100.00 | $86.49 | $4,054 |
| 666-7042 REFL PAV MRK TY I (W)(ARROW)(100MIL) | 92 EA | $106.29 | $150.00 | $156.95 | $4,021 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 27,515 LF | $0.5600 | $0.7000 | $0.4986 | $3,852 |
| 662-7018 WK ZN PAV MRK NON-REMOV (W)(ARROW) | 92 EA | $61.53 | $100.00 | $82.55 | $3,539 |
| 666-7213 RE PM TY II (Y) 6" (SLD) | 27,515 LF | $0.2000 | $0.3000 | $0.1749 | $2,752 |
| 3007-7001 BONDING COURSE | 19,735 GAL | $2.88 | $3.00 | $3.32 | $2,368 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 7,273 LF | $1.28 | $1.00 | $0.9489 | -$2,036 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 2,912 LF | $6.15 | $6.75 | $7.19 | $1,747 |
Positive: the low bidder was cheaper on that item. These 20 items account for $55,356 of the $67,743 gap.
ALLEN KELLER COMPANY: unbalanced items
Placed 1LONE STAR PAVING COMPANY: unbalanced items
Placed 2HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $184,683.13 | $523,850.32 | 0.35x | -$339,167 |