15Let jobs
$161,394,385Total low bids
$146,824,585Total estimates
+9.9%Low bids vs estimates
Jul 2025 results
Bid tabs (Excel) ExcelCSV| Let date | Contract | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Jul 17, 2025 | 250182NHPPI-4000-(223)PM | Custer Division 5 |
Grade · Grade | $59,732,772 | $76,423,144 | DUIT CONSTRUCTION COMPANY, INC. | +27.9% | 2 |
| Jul 17, 2025 | 250185STP-243C(055)CI | Love Division 7 |
Grade · Grade | $11,829,713 | $10,724,347 | SCHIRALLI CONSTRUCTION CORP. | -9.3% | 5 |
| Jul 17, 2025 | 250186STP-257B(094)PM | Osage Division 8 |
Bridge And ApproachesSH-18 · Bridge And Approaches | $8,575,263 | $7,350,060 | Frontier Bridge, Inc. | -14.3% | 6 |
| Jul 17, 2025 | 250155SSP-255F(636)IT | Canadian, Oklahoma, Tulsa, Wagoner Division 4 |
Its Construction · Its Construction | $2,182,390 | $1,969,217 | Midstate Traffic Control, Inc. | -9.8% | 2 |
| Jul 17, 2025 | 250110STP-253D(068)CI | Nowata Division 8 |
Bridge And ApproachesCOUNTY ROAD (NS 413 RD) · Bridge And Approaches | $1,490,048 | $1,421,720 | K & R BUILDERS, INC. | -4.6% | 9 |
| Jul 17, 2025 | 250183STP-239D(060)CI | Latimer Division 2 |
Bridge And ApproachesCOUNTY ROAD (EW 1430 RD, E CENTER POINT RD) · Bridge And Approaches | $696,895 | $554,524 | L & N BRIDGE, LLC | -20.4% | 8 |
| Jul 10, 2025 | 210239SSP-263B(069)PM | Pottawatomie Division 3 |
Grade · Grade | $20,248,870 | $22,686,173 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) | +12.0% | 5 |
| Jul 10, 2025 | 250176SSP-3500(197)PM | Love Division 7 |
Grade · Grade | $15,570,058 | $15,964,407 | C3 Construction, Inc. | +2.5% | 3 |
| Jul 10, 2025 | 250112STP-258C(100)CI | Ottawa Division 8 |
Grade · Grade | $7,351,898 | $6,583,881 | C3 Construction, Inc. | -10.4% | 3 |
| Jul 10, 2025 | 250180STP-159B(032)PM | Pawnee Division 8 |
Grade · Grade | $6,477,501 | $6,387,000 | BECCO CONTRACTORS, INC. | -1.4% | 2 |
| Jul 10, 2025 | 250181STP-269C(113)PM | Stephens Division 7 |
Bridge And ApproachesSH-53 · Bridge And Approaches | $5,838,334 | $4,931,993 | SEWELL BROS., INC. | -15.5% | 9 |
| Jul 10, 2025 | 250178STP-246C(069)PM | Mcintosh Division 1 |
Pavement RehabilitationUS-69B · Pavement Rehabilitation | $2,332,891 | $2,243,044 | C3 Construction, Inc. | -3.9% | 3 |
| Jul 10, 2025 | 250179STP-258D(117)CI | Ottawa Division 8 |
Bridge And ApproachesCOUNTY ROAD (S 690 RD) · Bridge And Approaches | $1,993,134 | $1,699,663 | K & R BUILDERS, INC. | -14.7% | 7 |
| Jul 10, 2025 | 250177STP-245C(093)CI | Mccurtain Division 2 |
Bridge And ApproachesCOUNTY ROAD (EW-213.5, GOODWATER ROAD) · Bridge And Approaches | $1,168,808 | $1,184,206 | C3 Construction, Inc. | +1.3% | 7 |
| Jul 8, 2025 | 250187SNL-26-FS | Pottawatomie Division 3 |
Construct Taxilane For T-Hangar And Rehabilitate Existing Taxilane And Apron At Shawnee Regional Airport (Snl). · Construct Taxilane For T-Hangar And Rehabilitate Existing Taxilane And Apron At Shawnee Regional Airport (Snl). | $1,336,010 | $1,271,005 | J Lee Enterprises | -4.9% | 4 |
1–15 of 15
Source: ODOT bid tabulations for each letting on Contracts and Proposals, read from ODOT's published bid tab reports, including the engineer's estimate. Bid Potato loads new lettings as ODOT posts them and backfills the last two years. Confirm against ODOT's official tabulations.