BRIDGE AND APPROACHES COUNTY ROAD (EW-19): OVER TRIBUTARY TO HORSE CREEK , 0.6 MILES WEST OF THE US -69 JUNCTION NEAR AFTON . PROJECT LENGTH = 0.166 MILE

Let date
Thursday, May 16, 2019
Contract
180248
J/P numbers
30554(04)
District
Division 8
County
Ottawa
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-19): OVER TRIBUTARY TO HORSE CREEK , 0.6 MILES WEST OF THE US -69 JUNCTION NEAR AFTON . PROJECT LENGTH = 0.166 MILE
Project number
STP-258D(050)CI

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$576,696
1 B & B BRIDGE COMPANY, LLC Low bidder $656,410 +13.8%
2 RRY SERVICES LLC $694,293 +20.4% +5.8%

Bid tab: unit prices 28 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 B & B BRIDGE CO…#2 RRY SERVICES LLC
1201(A) 0102 CLEARING AND GRUBBING1LSUM $3,000.00 $7,500.00 $12,000.00
2202(A) 0183 UNCLASSIFIED EXCAVATION2,088CY $8.50 $6.50 $8.00
3202(D) 0184 UNCLASSIFIED BORROW1,108CY $12.00 $10.00 $15.00
4205(A) 4229 TYPE A-SALVAGED TOPSOIL1LSUM $5,000.00 $4,500.00 $3,500.00
5221(C) 2801 TEMPORARY SILT FENCE1,747LF $1.20 $4.99 $4.99
6221(F) 0100 TEMPORARY SILT DIKE140LF $10.00 $39.00 $39.00
7230(A) 2806 SOLID SLAB SODDING1,348SY $8.00 $8.95 $8.95
8232(B) 2814 SEEDING METHOD B1.36AC $1,200.00 $5,950.00 $1,000.00
9233(A) 2817 VEGETATIVE MULCHING1.36AC $800.00 $5,950.00 $1,000.00
10402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E1,560TON $25.00 $19.00 $25.00
11509(D) 0325 CLASS C CONCRETE10CY $305.00 $300.00 $275.00
12613(EE) 5610 (SP) 18" CORRUGATED POLYPROPYLENE PIPE60LF $75.00 $40.00 $60.00
13613(M) 7186 TYPE A4 CULVERT END TREATMENT2EA $1,200.00 $1,600.00 $1,750.00
14619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $2,000.00 $1,000.00 $3,000.00
15508 6359 PRECAST ARCH CULVERT30LF $3,800.00 $7,000.00 $8,200.00
16509(A) 1326 CLASS AA CONCRETE12.1CY $1,000.00 $400.00 $850.00
17510(A) 6334 RETAINING WALL153.7SY $800.00 $750.00 $700.00
18511(A) 1332 REINFORCING STEEL1,680LB $1.40 $2.00 $1.10
19542 4605 (PL)INSTALLATION OF BRIDGE ITEMS28EA $1,500.00 $235.00 $250.00
20601(B) 1353 TYPE I-A PLAIN RIPRAP1,963TON $40.00 $45.00 $39.00
21601(C) 1355 TYPE I-A FILTER BLANKET222TON $35.00 $38.00 $33.00
22619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $10,000.00 $7,500.00 $12,500.00
23623(A) 0932 BEAM GUARDRAIL W-BEAM SINGLE237.5LF $20.00 $23.90 $23.90
24623(G) 8590 GUARDRAIL END TREATMENT (31")4EA $2,250.00 $4,540.00 $4,540.00
25880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $2,480.00 $2,480.00
26642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $5,000.00 $5,100.00 $6,960.00
27220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $1,250.00 $2,000.00 $1,275.00
28641 1399 MOBILIZATION1LSUM $55,000.00 $60,350.00 $61,000.00