Bid tab 160130

Let Mar 17, 2016 · Division 7 · Carter Sign up free

‹ Mar 2016 results

BRIDGE AND APPROACHES COUNTY ROAD (POOLVILLE ROAD /N3143): OVER TRIBUTARY TO BEAR CREEK, 5.3 MILES SOUTH OF SH-7 NEAR RATLIFF CITY . PROJECT LENGTH = 0.208 MILE

Let date
Thursday, March 17, 2016
Contract
160130
J/P numbers
28379(04)
District
Division 7
County
Carter
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (POOLVILLE ROAD /N3143): OVER TRIBUTARY TO BEAR CREEK, 5.3 MILES SOUTH OF SH-7 NEAR RATLIFF CITY . PROJECT LENGTH = 0.208 MILE
Project number
STP-110C(240)CI

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$495,533
1 FRONTIER BRIDGE, INC. / BRIDGECO CONTRACTORS, INC. Low bidder $479,504 -3.2%
2 Silver Star Construction Company, Inc. $562,730 +13.6% +17.4%
3 BREWER CONSTRUCTION OKLAHOMA, LLC $581,432 +17.3% +21.3%
4 KLAVER CONSTRUCTION COMPANY, INC. $584,650 +18.0% +21.9%
5 EARTH BUILDERS, L.P. $685,054 +38.2% +42.9%

Bid tab: unit prices 29 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 FRONTIER BRIDGE…#2 Silver Star Con…#3 BREWER CONSTRUC…#4 KLAVER CONSTRUC…#5 EARTH BUILDERS,…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $10,000.00 $17,325.00 $65,000.00 $16,500.00 $9,660.00 $25,000.00
2202(H) 0185 EARTHWORK1LSUM $40,000.00 $47,250.00 $94,879.54 $55,000.00 $59,150.00 $40,000.00
3221(C) 2801 TEMPORARY SILT FENCE1,500LF $2.50 $1.95 $1.30 $2.20 $1.22 $1.80
4221(F) 0100 TEMPORARY SILT DIKE350LF $6.00 $8.93 $7.75 $10.20 $7.29 $10.00
5230(A) 2806 SOLID SLAB SODDING9,162SY $3.00 $1.52 $1.50 $1.74 $1.38 $1.80
6233(A) 2817 VEGETATIVE MULCHING3.8AC $600.00 $225.75 $405.00 $220.00 $100.00 $130.00
7303(A) 2100 AGGREGATE BASE TYPE A679CY $50.00 $44.60 $64.40 $58.12 $54.15 $85.00
8307(K) 4300 STABILIZED SUBGRADE3,880SY $8.00 $6.83 $6.65 $9.00 $12.30 $15.00
9402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E352TON $35.00 $21.77 $22.75 $25.46 $33.90 $50.00
10411(B) 5945 SUPERPAVE, TYPE S3(PG 64-22 OK)738TON $85.00 $75.97 $72.50 $125.00 $98.20 $130.00
11411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)353TON $110.00 $102.94 $97.70 $125.00 $119.40 $150.00
12509(D) 0325 CLASS C CONCRETE10CY $400.00 $347.04 $636.00 $300.00 $400.00 $450.00
13613(A) 4496 28" X 18" R.C.PIPE ARCH CLASS A-III44LF $65.00 $104.99 $254.00 $136.10 $95.00 $120.00
14613(B) 4527 21" X 15" CORR. GALV. STEEL PIPE ARCH54LF $30.00 $25.86 $32.00 $65.59 $60.00 $65.00
15613(L) 4504 21" X 15" PREFAB. CULVERT END SECTION, ARCH2EA $250.00 $350.91 $265.00 $1,406.04 $275.00 $1,800.00
16613(L) 4515 28" X 18" PREFAB. CULVERT END SECTION, ARCH2EA $275.00 $1,453.31 $2,650.00 $2,862.50 $1,075.00 $2,000.00
17619(A) 0920 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $2,500.00 $2,100.00 $2,195.00 $12,000.00 $4,830.00 $15,000.00
18629(E) 5048 REMOVE AND RESET MAILBOX2EA $100.00 $210.00 $265.00 $250.00 $250.00 $350.00
19202(A) 1301 UNCLASSIFIED EXCAVATION345CY $12.00 $5.65 $15.90 $15.00 $8.00 $20.00
20501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON95CY $12.00 $16.95 $15.90 $15.00 $10.00 $20.00
21509(A) 1326 CLASS AA CONCRETE167.06CY $600.00 $500.75 $371.00 $546.02 $609.85 $700.00
22511(A) 1332 REINFORCING STEEL23,671LB $1.00 $1.52 $1.00 $1.68 $0.9000 $1.00
23601(B) 1353 TYPE I-A PLAIN RIPRAP542TON $40.00 $42.64 $42.50 $60.60 $32.00 $55.00
24601(C) 1355 TYPE I-A FILTER BLANKET170TON $35.00 $32.98 $42.50 $35.00 $24.00 $45.00
25619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $5,000.00 $8,475.00 $5,300.00 $9,360.00 $7,141.50 $25,000.00
26880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $2,248.70 $10,000.00 $3,000.00 $1,990.00 $4,500.00
27642(B) 0096 CONSTRUCTION STAKING LEVEL II1LSUM $7,000.00 $8,715.00 $15,850.00 $9,753.75 $8,300.00 $8,000.00
28220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $5,000.00 $2,625.00 $7,500.00 $6,502.50 $2,500.00 $3,500.00
29641 1399 MOBILIZATION1LSUM $40,000.00 $47,653.62 $28,000.00 $28,000.00 $99,690.02 $50,000.00