Bid tab 160123

Let Feb 18, 2016 · Division 1 · Wagoner Sign up free

‹ Feb 2016 results

RESURFACE (ASPHALT ) SH-51B: FROM THE SH -72 JUNCTION, EXTEND EAST NEAR COWETA . PROJECT LENGTH = 6.248 MILES

Let date
Thursday, February 18, 2016
Contract
160123
J/P numbers
29754(04)
District
Division 1
County
Wagoner
Highway
Limits
RESURFACE (ASPHALT ) SH-51B: FROM THE SH -72 JUNCTION, EXTEND EAST NEAR COWETA . PROJECT LENGTH = 6.248 MILES
Project number
STP-273C(014)3P

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,354,839
1 GLOVER & ASSOCIATES, INC. Low bidder $1,083,186 -20.1%
2 Paragon Contractors, LLC $1,131,131 -16.5% +4.4%
3 BECCO CONTRACTORS, INC. $1,389,000 +2.5% +28.2%
4 APAC-CENTRAL, INC. $1,407,778 +3.9% +30.0%

Bid tab: unit prices 20 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 GLOVER & ASSOCI…#2 Paragon Contrac…#3 BECCO CONTRACTO…#4 APAC-CENTRAL, I…
1202(H) 0185 EARTHWORK1LSUM $30,000.00 $65,000.00 $29,120.00 $213,500.00 $107,875.61
2221(C) 2801 TEMPORARY SILT FENCE3,000LF $1.50 $1.00 $1.25 $1.30 $1.35
3230(A) 2806 SOLID SLAB SODDING1,667SY $3.00 $1.49 $1.35 $1.50 $1.40
4402(E) 0225 TRAFFIC BOUND SURFACE COURSE TYPE E2,295TON $18.00 $23.32 $23.85 $35.00 $26.29
5407(B) 0250 TACK COAT6,158GAL $2.75 $2.00 $3.55 $3.00 $2.71
6411(C) 5960 SUPERPAVE, TYPE S4(PG 64-22 OK)13,750TON $70.00 $58.00 $58.70 $60.00 $70.50
7412 5267 COLD MILLING PAVEMENT800SY $2.00 $3.33 $6.65 $2.50 $9.47
8509(C) 0322 CLASS A CONCRETE, SMALL STRUCTURES89.49CY $750.00 $566.69 $900.00 $600.00 $882.81
9509(D) 0325 CLASS C CONCRETE10CY $350.00 $296.78 $424.00 $600.00 $494.82
10511(A) 0332 REINFORCING STEEL7,416LB $1.00 $1.05 $2.05 $2.25 $0.5600
11611(G) 5706 INLET CDI RCP DES. 31EA $5,000.00 $4,000.00 $4,770.00 $7,000.00 $6,252.80
12611(H) 5330 ADD'L DEPTH IN INLET CI DES. 30.5VF $500.00 $2,341.96 $530.00 $300.00 $1,549.08
13613(A) 0492 24" R.C.PIPE CLASS III26LF $150.00 $89.69 $130.00 $90.00 $156.42
14613(A) 0493 30" R.C.PIPE CLASS III6LF $200.00 $132.95 $159.00 $100.00 $333.65
15613(A) 4496 28" X 18" R.C.PIPE ARCH CLASS A-III52LF $175.00 $70.81 $185.00 $110.00 $159.25
16613(M) 7187 TYPE B4 CULVERT END TREATMENT4EA $1,000.00 $1,661.94 $1,275.00 $2,000.00 $2,756.14
17619(B) 0291 REMOVAL OF HEADWALL15EA $1,000.00 $1,000.00 $2,300.00 $1,800.00 $1,124.96
18856(A) 8530 TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE)113,630LF $1.00 $0.3800 $0.3500 $0.3500 $0.3700
19856(A) 8555 TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE)240LF $12.00 $5.94 $5.30 $10.00 $5.60
20880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $60,000.00 $7,000.00 $7,353.60 $73,940.00 $58,776.92