RESURFACE (ASPHALT ) SH-76: FROM 6.74 MILES NORTH OF THE GARVIN COUNTY LINE , EXTEND NORTH NEAR DIBBLE . PROJECT LENGTH = 7.050 MILES
- Let date
- Thursday, March 17, 2016
- Contract
- 160099
- J/P numbers
- 30565(04)
- District
- Division 3
- County
- Mcclain
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-76: FROM 6.74 MILES NORTH OF THE GARVIN COUNTY LINE , EXTEND NORTH NEAR DIBBLE . PROJECT LENGTH = 7.050 MILES
- Project number
- ACSTP-244C(047)3P
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $2,168,751 | ||
| 1 | MARKWELL PAVING COMPANY, INC. Low bidder | $1,761,985 | -18.8% | |
| 2 | T.J. CAMPBELL CONSTRUCTION COMPANY | $1,999,991 | -7.8% | +13.5% |
| 3 | Silver Star Construction Company, Inc. | $2,074,000 | -4.4% | +17.7% |
| 4 | HASKELL LEMON CONSTRUCTION CO. | $2,183,299 | +0.7% | +23.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 MARKWELL PAVING… | #2 T.J. CAMPBELL C… | #3 Silver Star Con… | #4 HASKELL LEMON C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 202(A) 0183 | UNCLASSIFIED EXCAVATION | 8,272 | CY | $15.00 | $7.50 | $7.00 | $8.90 | $20.00 |
| 2 | 209 0120 | MACHINE GRADING | 74,400 | LF | $1.80 | $1.00 | $0.5000 | $0.7000 | $2.00 |
| 3 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 15,105 | TON | $30.00 | $27.00 | $28.00 | $35.30 | $30.00 |
| 4 | 407(B) 0250 | TACK COAT | 16,130 | GAL | $3.05 | $1.50 | $3.00 | $2.85 | $3.50 |
| 5 | 411(D) 5970 | SUPERPAVE, TYPE S5(PG 70-28 OK) | 15,808 | TON | $85.00 | $72.95 | $85.00 | $77.95 | $85.15 |
| 6 | 412 5267 | COLD MILLING PAVEMENT | 375 | SY | $20.00 | $2.00 | $24.00 | $10.00 | $10.00 |
| 7 | 855(A) 8840 | TRAFFIC STRIPE(PLASTIC)(THIN LINE)(4" WIDE) | 93,060 | LF | $0.4000 | $0.3500 | $0.4500 | $0.4000 | $0.0500 |
| 8 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $20,000.00 | $7,000.00 | $39,000.00 | $95,914.60 | $5,000.00 |