BRIDGE AND APPROACHES COUNTY ROAD (NS-265): OVER THE TRIBUTARY OF EAST CACHE CREEK, 1.5 MILES NORTH OF SH -5. PROJECT LENGTH = 0.066 MILE
- Let date
- Thursday, January 22, 2015
- Contract
- 150008
- J/P numbers
- 29338(04)
- District
- County
- Cotton
- Highway
- Limits
- BRIDGE AND APPROACHES COUNTY ROAD (NS-265): OVER THE TRIBUTARY OF EAST CACHE CREEK, 1.5 MILES NORTH OF SH -5. PROJECT LENGTH = 0.066 MILE
- Project number
- STP-217D(012)CI
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $271,751 | ||
| 1 | Munoz Construction, Inc. Low bidder | $235,828 | -13.2% | |
| 2 | Frontier Bridge, Inc. | $259,161 | -4.6% | +9.9% |
| 3 | KLAVER CONSTRUCTION COMPANY, INC. | $271,311 | -0.2% | +15.0% |
| 4 | K & R BUILDERS, INC. | $299,557 | +10.2% | +27.0% |
| 5 | CP3 ENTERPRISES, INC. | $379,585 | +39.7% | +61.0% |
| 6 | EARTH BUILDERS, L.P. | $447,650 | +64.7% | +89.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Munoz Construct… | #2 Frontier Bridge… | #3 KLAVER CONSTRUC… | #4 K & R BUILDERS,… | #5 CP3 ENTERPRISES… | #6 EARTH BUILDERS,… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 201(A) 0102 | CLEARING AND GRUBBING | 1 | LSUM | $5,000.00 | $1,000.00 | $5,500.00 | $7,505.00 | $4,875.00 | $12,180.00 | $20,000.00 |
| 2 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $7,000.00 | $30,000.00 | $12,650.00 | $25,000.00 | $17,380.00 | $38,123.40 | $25,000.00 |
| 3 | 221(C) 2801 | TEMPORARY SILT FENCE | 650 | LF | $2.50 | $1.75 | $1.45 | $1.31 | $2.00 | $7.55 | $4.00 |
| 4 | 221(F) 0100 | TEMPORARY SILT DIKE | 32 | LF | $10.00 | $10.00 | $13.06 | $11.88 | $15.00 | $30.21 | $20.00 |
| 5 | 221(G) 0150 | TEMPORARY ROCK FILTER DAM TYPE 1 | 20 | CY | $100.00 | $50.00 | $110.00 | $100.00 | $120.00 | $66.87 | $65.00 |
| 6 | 230(A) 2806 | SOLID SLAB SODDING | 1,928 | SY | $2.00 | $4.25 | $2.06 | $1.88 | $2.44 | $3.65 | $5.00 |
| 7 | 233(A) 2817 | VEGETATIVE MULCHING | 0.72 | AC | $600.00 | $700.00 | $900.00 | $818.00 | $200.00 | $1,827.00 | $3,500.00 |
| 8 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 310 | TON | $50.00 | $40.00 | $35.00 | $35.00 | $35.52 | $53.59 | $50.00 |
| 9 | 408 5774 | PRIME COAT | 381 | GAL | $6.00 | $7.00 | $16.50 | $15.00 | $18.00 | $14.01 | $22.00 |
| 10 | 509(D) 0325 | CLASS C CONCRETE | 10 | CY | $275.00 | $220.00 | $388.00 | $450.00 | $312.50 | $499.38 | $500.00 |
| 11 | 202(A) 1301 | UNCLASSIFIED EXCAVATION | 245 | CY | $20.00 | $10.00 | $16.50 | $15.00 | $12.00 | $29.33 | $25.00 |
| 12 | 501(A) 1306 | STRUCTURAL EXCAVATION UNCLASSIFIED | 125 | CY | $15.00 | $10.00 | $27.50 | $5.00 | $22.00 | $36.54 | $25.00 |
| 13 | 509(A) 1326 | CLASS AA CONCRETE | 212.44 | CY | $550.00 | $300.00 | $405.00 | $451.26 | $572.50 | $595.30 | $800.00 |
| 14 | 511(A) 1332 | REINFORCING STEEL | 34,588 | LB | $1.00 | $1.00 | $1.23 | $0.9000 | $1.00 | $1.22 | $2.00 |
| 15 | 601(B) 1353 | TYPE I-A PLAIN RIPRAP | 464 | TON | $38.00 | $35.00 | $49.00 | $60.00 | $44.48 | $70.64 | $60.00 |
| 16 | 601(C) 1355 | TYPE I-A FILTER BLANKET | 147 | TON | $35.00 | $35.00 | $41.00 | $45.00 | $36.50 | $55.05 | $50.00 |
| 17 | 619(D) 1397 | REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM | $8,000.00 | $20,000.00 | $8,250.00 | $15,000.00 | $13,500.00 | $16,493.00 | $28,000.00 |
| 18 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $5,000.00 | $3,500.00 | $2,640.00 | $3,285.00 | $3,000.00 | $2,923.20 | $5,000.00 |
| 19 | 642(B) 0096 | CONSTRUCTION STAKING LEVEL II | 1 | LSUM | $5,000.00 | $7,500.00 | $8,250.00 | $7,500.00 | $9,000.00 | $6,942.60 | $5,000.00 |
| 20 | 220 2800 | SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM | $5,000.00 | $4,000.00 | $3,850.00 | $3,500.00 | $3,000.00 | $2,831.85 | $3,500.00 |
| 21 | 641 1399 | MOBILIZATION | 1 | LSUM | $27,000.00 | $18,000.00 | $24,000.00 | $15,260.67 | $30,875.00 | $36,296.40 | $32,000.00 |