17-00119-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Peter Baker & Son Co. Low bidder | $1,240,026 | ||
| 2 | Lorig Construction Company | $1,428,672 | +15.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Peter Baker & S… | #2 Lorig Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $4,500.00 | $20,000.00 | |
| 2 | X0320586 | FLEX DELINEATORS | 16 | EACH | $52.50 | $150.00 | |
| 3 | X2130010 | EXPLOR TRENCH SPL | 250 | FOOT | $1.00 | $50.00 | |
| 4 | X4400196 | HMA SURF REM SPL | 27,096 | SQ YD | $3.88 | $3.25 | |
| 5 | X6026624 | VALVE BOX ADJ SPL | 2 | EACH | $500.00 | $400.00 | |
| 6 | X6030310 | FR & LIDS ADJUST SPL | 11 | EACH | $700.00 | $750.00 | |
| 7 | X7015005 | CHANGEABLE MESSAGE SN | 100 | CAL DA | $25.00 | $25.00 | |
| 8 | X7800200 | PAINT PVT MARK CURB | 333 | FOOT | $1.00 | $1.00 | |
| 9 | Z0004510 | HMA DRIVEWAY PAVT 3 | 59 | SQ YD | $66.00 | $32.00 | |
| 10 | Z0004562 | COMB C C&G REM & REPL | 2,602 | FOOT | $38.00 | $47.50 | |
| 11 | Z0004910 | HMA F PATCH (H M) | 30 | TON | $100.00 | $175.00 | |
| 12 | Z0017400 | DRAIN UTIL STR ADJ | 7 | EACH | $375.00 | $700.00 | |
| 13 | Z0017700 | DRAIN UTIL STR RECON | 1 | EACH | $1,000.00 | $1,300.00 | |
| 14 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $15.00 | $15.00 | |
| 15 | 20101000 | TEMPORARY FENCE | 2,080 | FOOT | $0.5000 | $3.00 | |
| 16 | 20101200 | TREE ROOT PRUNING | 22 | EACH | $65.00 | $250.00 | |
| 17 | 20101300 | TREE PRUN 1-10 | 7 | EACH | $40.00 | $125.00 | |
| 18 | 20101350 | TREE PRUN OVER 10 | 34 | EACH | $70.00 | $150.00 | |
| 19 | 20200100 | EARTH EXCAVATION | 456 | CU YD | $15.00 | $45.00 | |
| 20 | 20201200 | REM & DISP UNS MATL | 456 | CU YD | $15.00 | $45.00 | |
| 21 | 21101615 | TOPSOIL F & P 4 | 1,408 | SQ YD | $6.50 | $6.50 | |
| 22 | 25000400 | NITROGEN FERT NUTR | 18 | POUND | $3.00 | $3.00 | |
| 23 | 25000600 | POTASSIUM FERT NUTR | 18 | POUND | $3.00 | $3.00 | |
| 24 | 25200110 | SODDING SALT TOLERANT | 1,408 | SQ YD | $8.00 | $8.00 | |
| 25 | 25200200 | SUPPLE WATERING | 13 | UNIT | $0.0100 | $0.1000 | |
| 26 | 28000510 | INLET FILTERS | 51 | EACH | $30.00 | $170.00 | |
| 27 | 35101500 | AGG BASE CSE B | 734 | CU YD | $20.00 | $65.00 | |
| 28 | 40201000 | AGGREGATE-TEMP ACCESS | 50 | TON | $13.00 | $50.00 | |
| 29 | 40600290 | BIT MATLS TACK CT | 18,290 | POUND | $1.35 | $0.0100 | |
| 30 | 40600400 | MIX CR JTS FLANGEWYS | 60 | TON | $400.00 | $175.00 | |
| 31 | 40600827 | P LB MM IL-4.75 N50 | 1,524 | TON | $80.00 | $83.00 | |
| 32 | 40600982 | HMA SURF REM BUTT JT | 319 | SQ YD | $1.00 | $22.00 | |
| 33 | 40603335 | HMA SC "D" N50 | 3,041 | TON | $80.00 | $69.00 | |
| 34 | 42001300 | PROTECTIVE COAT | 1,775 | SQ YD | $0.1000 | $1.00 | |
| 35 | 42300200 | PCC DRIVEWAY PAVT 6 | 493 | SQ YD | $50.00 | $55.00 | |
| 36 | 42300400 | PCC DRIVEWAY PAVT 8 | 85 | SQ YD | $75.00 | $65.00 | |
| 37 | 42400200 | PC CONC SIDEWALK 5 | 4,549 | SQ FT | $6.50 | $6.25 | |
| 38 | 42400800 | DETECTABLE WARNINGS | 453 | SQ FT | $30.00 | $35.00 | |
| 39 | 44000200 | DRIVE PAVEMENT REM | 636 | SQ YD | $7.50 | $20.00 | |
| 40 | 44000600 | SIDEWALK REM | 4,821 | SQ FT | $1.00 | $3.00 | |
| 41 | 44201725 | CL D PATCH T1 7 | 59 | SQ YD | $80.00 | $55.00 | |
| 42 | 44201729 | CL D PATCH T2 7 | 503 | SQ YD | $65.00 | $48.00 | |
| 43 | 44201733 | CL D PATCH T3 7 | 763 | SQ YD | $50.00 | $46.00 | |
| 44 | 44201735 | CL D PATCH T4 7 | 6,800 | SQ YD | $35.00 | $43.00 | |
| 45 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $1,500.00 | $2,500.00 | |
| 46 | 67100100 | MOBILIZATION | 1 | L SUM | $68,384.77 | $74,000.00 | |
| 47 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $35,000.00 | $80,000.00 | |
| 48 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $1,000.00 | |
| 49 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $1,000.00 | |
| 50 | 70300100 | SHORT TERM PAVT MKING | 4,509 | FOOT | $0.2500 | $0.4500 | |
| 51 | 70300150 | SHRT TRM PAVT MK REM | 507 | SQ FT | $2.50 | $1.30 | |
| 52 | 70300210 | TEMP PVT MK LTR & SYM | 291 | SQ FT | $0.0100 | $1.50 | |
| 53 | 70300220 | TEMP PVT MK LINE 4 | 22,932 | FOOT | $0.0100 | $0.2000 | |
| 54 | 70300240 | TEMP PVT MK LINE 6 | 705 | FOOT | $0.0100 | $0.3000 | |
| 55 | 70300280 | TEMP PVT MK LINE 24 | 473 | FOOT | $0.0100 | $1.20 | |
| 56 | 72000100 | SIGN PANEL T1 | 193 | SQ FT | $17.50 | $17.50 | |
| 57 | 72400100 | REMOV SIN PAN ASSY TA | 55 | EACH | $35.00 | $35.00 | |
| 58 | 72800100 | TELES STL SIN SUPPORT | 176 | FOOT | $15.50 | $15.50 | |
| 59 | 78000100 | THPL PVT MK LTR & SYM | 146 | SQ FT | $4.00 | $4.00 | |
| 60 | 78000200 | THPL PVT MK LINE 4 | 22,324 | FOOT | $0.5300 | $0.5300 | |
| 61 | 78000400 | THPL PVT MK LINE 6 | 1,947 | FOOT | $0.7500 | $0.7500 | |
| 62 | 78000600 | THPL PVT MK LINE 12 | 48 | FOOT | $1.50 | $1.50 | |
| 63 | 78000650 | THPL PVT MK LINE 24 | 238 | FOOT | $4.00 | $4.00 | |
| 64 | 78100100 | RAISED REFL PAVT MKR | 28 | EACH | $100.00 | $100.00 | |
| 65 | 78300200 | RAISED REF PVT MK REM | 22 | EACH | $10.00 | $20.00 |