| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| FY 2025 | 1-71354-0200 1713540200 | District 1 | Half Day RdIL-22 | Initial Construction - Pa Tree Removal Quentin Rd to W of ILL 83 (Mundelein Rd) | $200,000 | Planned | ||
| FY 2025 | 1-73626-2001 1736262001 | District 1 | Willow Rd | Miscellaneous Improvement Reconstruction, Intersection Improvement, Lighting Culligan Pkwy (Allstate Entrance) to Landwehr Rd & Over I-294 (Tri-State Tollway) | $3,000,000 | Planned | ||
| FY 2025 | 1-75204-1030 1752041030 | District 1 | Eisenhower ExpwyI-290IL-110 | Reconstruction - Bridges Bridge Replacement At Laramie Ave (Overhead) | $25,000,000 | Planned | ||
| FY 2025 | 1-75939-0000 1759390000 | District 1 | Front StIL-31 | Initial Construction - Pa Additional Lanes Ill 120 to Bull Valley Rd | $29,650,000 | Planned | ||
| FY 2025 | 1-75939-0010 1759390010 | District 1 | Front StIL-31 | Reconstruction - Pavement Reconstruction, Widening Existing Pavement, Traf Signal Modernization Ill 120 to Bull Valley Rd | $44,475,000 | Planned | ||
| FY 2025 | 1-75939-0200 1759390200 | District 1 | Front StIL-31 | Initial Construction - Pa Additional Lanes, ADA Improvements Bull Valley Rd to ILL 176 (Terra Cotta Ave) | $40,000,000 | Planned | ||
| FY 2025 | 1-75939-0201 1759390201 | District 1 | Front StIL-31 | Initial Construction - Pa Utility Adjustment S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) | $4,000,000 | Planned | ||
| FY 2025 | 1-75939-0202 1759390202 | District 1 | Front StIL-31 | Initial Construction - Pa Utility Adjustment S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) | $4,000,000 | Planned | ||
| FY 2025 | 1-75939-0800 1759390800 | District 1 | Front StIL-31 | Miscellaneous Improvement Miscellaneous Bull Valley Rd to ILL 176 (Terra Cotta Ave) | $500,000 | Planned | ||
| FY 2025 | 1-75939-1200 1759391200 | District 1 | Front StIL-31 | Reconstruction - Pavement Culvert (New) Bull Valley Rd to ILL 176 (Terra Cotta Ave) | $60,000,000 | Planned | ||
| FY 2025 | 1-75939-3001 1759393001 | District 1 | Front StIL-31 | Miscellaneous Improvement Tree Removal S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) | $400,000 | Planned | ||
| FY 2025 | 1-76353-0100 1763530100 | District 1 | Touhy Ave | Reconstruction - Bridges Bridge Replacement At N Branch Chicago River 0.6 Mi E of ILL 43 | $5,200,000 | Planned | ||
| FY 2025 | 1-77247-0010 1772470010 | District 1 | I-80 | Miscellaneous Improvement Landscaping Gardner St to Gougar Rd | $5,335,000 | Planned | ||
| FY 2025 | 1-77247-6600 1772476600 | District 1 | I-80 | Initial Construction - Br Bridge (New) At Des Plaines River | $145,957,000 | Planned | ||
| FY 2025 | 1-77247-6602 1772476602 | District 1 | I-80 | Maintenance - Pavements Miscellaneous At Des Plaines River | $500,000 | Planned | ||
| FY 2025 | 1-77247-6640 1772476640 | District 1 | I-80 | Reconstruction - Bridges Utility Adjustment At Des Plaines River | $15,000,000 | Planned | ||
| FY 2025 | 1-77247-6700 1772476700 | District 1 | I-80 | Reconstruction - Pavement Bridge Replacement At Center St Intchg | $81,910,000 | Planned | ||
| FY 2025 | 1-77247-6740 1772476740 | District 1 | I-80 | Reconstruction - Pavement Utility Adjustment At Center St Intchg | $5,000,000 | Planned | ||
| FY 2025 | 1-77247-6907 1772476907 | District 1 | I-80 | Miscellaneous Improvement Demolition At Des Plaines River (Demo #4) | $300,000 | Planned | ||
| FY 2025 | 1-77247-7100 1772477100 | District 1 | I-80 | Miscellaneous Improvement Miscellaneous Ridge Rd to Wheeler Ave & Gardner St to Gougar Rd (ITS Integration) | $15,000,000 | Planned | ||
| FY 2025 | 1-77358-1000 1773581000 | District 1 | Archer AveIL-171 | Rehabilitation - Pavement Designed Overlay ILL 83 to Will Co Line | $9,600,000 | Planned | ||
| FY 2025 | 1-77548-1000 1775481000 | District 1 | Skokie HwyUS-41 | Miscellaneous Improvement Storm Sewer (New), Drainage, Grading 0.5 MI N of ILL 176 (Rockland Rd) | $1,550,000 | Planned | ||
| FY 2025 | 1-77727-0000 1777270000 | District 1 | IL-47US-30 | Initial Construction - Pa Additional Lanes, ADA Improvements Cross St to Jericho Rd | $24,771,000 | Planned | ||
| FY 2025 | 1-77727-0005 1777270005 | District 1 | IL-47US-30 | Reconstruction - Pavement Utility Adjustment Cross St to 0.4 Mi s of Galena Rd | $1,000,000 | Planned | ||
| FY 2025 | 1-77727-0006 1777270006 | District 1 | IL-47US-30 | Reconstruction - Pavement RR Relocation, RR Flagger Cross St to 0.4 Mi S of Galena Rd | $7,500,000 | Planned | ||
| FY 2025 | 1-77727-1000 1777271000 | District 1 | IL-47US-30 | Reconstruction - Pavement Bridge Replacement Cross St to Jericho Rd | $39,500,000 | Planned | ||
| FY 2025 | 1-77727-1005 1777271005 | District 1 | IL-47US-30 | Reconstruction - Pavement Utility Adjustment Cross St to 0.4 Mi s of Galena Rd | $1,600,000 | Planned | ||
| FY 2025 | 1-77727-2000 1777272000 | District 1 | IL-47US-30 | Initial Construction - Pa Additional Lanes Jericho Rd to 0.4 Mi S of Galena Rd | $24,600,000 | Planned | ||
| FY 2025 | 1-77727-2010 1777272010 | District 1 | IL-47US-30 | Reconstruction - Pavement Culvert Replacement Jericho Rd to 0.4 Mi S of Galena Rd | $16,400,000 | Planned | ||
| FY 2025 | 1-77727-2400 1777272400 | District 1 | IL-47US-30 | Initial Construction - Pa Utility Adjustment Jericho Rd to 0.4 Mi S of Galena Rd | $2,500,000 | Planned | ||
| FY 2025 | 1-77865-0800 1778650800 | District 1 | US-20 | Safety Channelization, Safety Improvements Ill 31 to E of Grace St | $250,000 | Planned | ||
| FY 2025 | 1-78146-0000 1781460000 | District 1 | Sacramento Blvd | Rehabilitation - Pavement Designed Overlay, ADA Improvements, RR Flagger N of Carroll Ave to Roosevelt Rd | $1,100,000 | Planned | ||
| FY 2025 | 1-78216-1000 1782161000 | District 1 | IL-25St Charles St | Rehabilitation - Pavement Designed Overlay, ADA Improvements, Milled Rumble Strip Bluff City Blvd to 0.4 Mi N of Stearns Rd | $4,000,000 | Planned | ||
| FY 2025 | 1-78236-1000 1782361000 | District 1 | 96th Ave/lagrangeUS-45US-52 | Rehabilitation - Pavement Designed Overlay, Shoulder Reconstruction N of Monee Manhattan Rd to Wilmington Peotone Rd | $6,200,000 | Planned | ||
| FY 2025 | 1-78551-0000 1785510000 | District 1 | Lake StUS-20 | Safety Intersection Improvement At Oak Ave & At Bartlett Rd | $3,058,000 | Planned | ||
| FY 2025 | 1-78736-0000 1787360000 | District 1 | I-57 | Rehabilitation - Bridges Culvert Repair At Pauling Rd (Overhead) | $5,870,000 | Planned | ||
| FY 2025 | 1-79180-0000 1791800000 | District 1 | Main St | Reconstruction - Bridges Culvert Replacement Wheeler Dr to Ill 83/171 (Archer Ave) | $16,000,000 | Planned | ||
| FY 2025 | 1-79279-0000 1792790000 | District 1 | Chicago-ottawa ConIL-53US-6 | Rehabilitation - Pavement Designed Overlay, ADA Improvements Jackson St to Chicago St (SB) | $2,500,000 | Planned | ||
| FY 2025 | 1-79287-0000 1792870000 | District 1 | IL-7Theodore St | Rehabilitation - Pavement Designed Overlay, ADA Improvements US 30 (Plainfield Rd) to Ill 53 (Broadway St) | $1,650,000 | Planned | ||
| FY 2025 | 1-79364-0000 1793640000 | District 1 | 143rd St | Reconstruction - Pavement Reconstruction Will-Cook Rd to Wolf Rd | $25,000,000 | Planned | ||
| FY 2025 | 1-79433-0001 1794330001 | District 1 | Eisenhower ExpwyI-290IL-53 | Preservation - Bridges Bridge Repair, Bridge Joint Replace/Repair Ill 62 (Algonquin Rd) to Ill 72 (Higgins Rd) and At I-90 (Jane Addams Memorial Tollway), Ill 58 (Golf Rd), Woodfield Rd & Ill 72 (Higgins Rd) | $3,000,000 | Planned | ||
| FY 2025 | 1-79433-0002 1794330002 | District 1 | Eisenhower ExpwyI-290IL-53 | Preservation - Pavements Smart Overlay, Standard Overlay, Miscellaneous Ill 62 (Algonquin Rd) to Ill 72 (Higgins Rd) and At I-90 (Jane Addams Memorial Tollway), Ill 58 (Golf Rd), Woodfield Rd & Ill 72 (Higgins Rd) | $40,000,000 | Planned | ||
| FY 2025 | 1-79449-0000 1794490000 | District 1 | Des Plaines Ave | Preservation - Pavements Smart Overlay, ADA Improvements Randolph St to Madison St | $340,000 | Planned | ||
| FY 2025 | 1-79459-0000 1794590000 | District 1 | Dundee RdIL-68 | Rehabilitation - Pavement Designed Overlay, ADA Improvements, RR Flagger E of Kennicott Ave to Northgate Pkwy | $4,500,000 | Planned | ||
| FY 2025 | 1-79537-1000 1795371000 | District 1 | IL-129Washington St | Rehabilitation - Pavement Designed Overlay, ADA Improvements, RR Flagger Coal City Rd to E Eureka St | $2,500,000 | Planned | ||
| FY 2025 | 1-79595-0000 1795950000 | District 1 | Lincoln Ave | Rehabilitation - Pavement Standard Overlay, ADA Improvements 138th St to ILL 83 (Sibley Blvd) | $2,200,000 | Planned | ||
| FY 2025 | 1-79840-0000 1798400000 | District 1 | Eisenhower ExpwyI-290IL-53 | Maintenance - Pavements Shoulder Repair, Signing (New), Pavement Marking Lake-Cook Rd to Des Plaines Ave - (Bus On Shoulder) | $22,100,000 | Planned | ||
| FY 2025 | 1-79858-0000 1798580000 | District 1 | IL-59 | Rehabilitation - Pavement Standard Overlay, ADA Improvements, Milled Rumble Strip N of Ill 132 (Grand Ave) to Longwood Dr | $2,115,000 | Planned | ||
| FY 2025 | 1-79875-0011 1798750011 | District 1 | First AveIL-171 | Maintenance - Pavements Drainage Roosevelt Rd to 22nd St (Cermak Rd) | $700,000 | Planned | ||
| FY 2025 | 1-79875-0015 1798750015 | District 1 | First AveIL-171 | Maintenance - Pavements Drainage Roosevelt Rd to 22nd St (Cermak Rd) | $2,000,000 | Planned | ||
| FY 2025 | 1-79887-0000 1798870000 | District 1 | Ogden AveUS-34 | Safety Intersection Improvement, ADA Improvements Rickert Dr to Feldott Ln | $1,500,000 | Planned | ||
| FY 2025 | 1-79892-0800 1798920800 | District 1 | Baltimore StIL-53 | Maintenance - Pavements Drainage Strip Mine Rd to Markle Rd | $241,000 | Planned | ||
| FY 2025 | 1-79906-0000 1799060000 | District 1 | Cicero AveIL-50 | Miscellaneous Improvement Traf Signal Modernization, Channelization, Traf Signal Installation At Governors Hwy & At Dralle Rd | $2,295,000 | Planned | ||
| FY 2025 | 1-79921-0000 1799210000 | District 1 | Cicero AveIL-50 | Reconstruction - Pavement Bridge Repair At I-55 (Stevenson Expwy) | $8,750,000 | Planned | ||
| FY 2025 | 1-79969-0000 1799690000 | District 1 | Des Plaines RiverDes Plaines RiverRd | Maintenance - Pavements Drainage, Erosion Control, Retaining Wall N of Winona Ave | $4,000,000 | Planned | ||
| FY 2025 | 1-79969-1000 1799691000 | District 1 | Des Plaines RiverRd | Maintenance - Pavements Landscaping N of Winona Ave | $15,000 | Planned | ||
| FY 2025 | 1-79994-0000 1799940000 | District 1 | Edens Expwy /I-94Tri-st Connector | Reconstruction - Bridges Bridge Replacement at Pfingsten Rd (Overhead) | $2,200,000 | Planned | ||
| FY 2025 | 1-79996-0000 1799960000 | District 1 | Edens ExpwyI-94 | Reconstruction - Bridges Bridge Replacement At Devon Ave (Overhead) | $16,000,000 | Planned | ||
| FY 2025 | 1-80008-0000 1800080000 | District 1 | Eisenhower ExpwyI-290 | Reconstruction - Bridges Bridge Replacement at Central Park Ave (Overhead) | $16,000,000 | Planned | ||
| FY 2025 | 1-80137-0000 1801370000 | District 1 | IL-7Southwest Hwy | Miscellaneous Improvement Traf Signal Modernization, Left Turn Lanes At Ill 43 (Harlem Ave) | $1,400,000 | Planned | ||
| FY 2025 | 1-80227-0000 1802270000 | District 1 | IL-47 | Rehabilitation - Pavement Standard Overlay, ADA Improvements Kreutzer Rd to N of Jim Dhamer Dr | $3,230,000 | Planned | ||
| FY 2025 | 1-80370-1010 1803701010 | District 1 | Baltimore StIL-53 | Rehabilitation - Pavement Designed Overlay, Patching, ADA Improvements Kankakee St to W of Forked Creek | $1,300,000 | Planned | ||
| FY 2025 | 1-80428-0000 1804280000 | District 1 | I-55 W Fr Rd NbW Frontage Rd Nb | Rehabilitation - Pavement Standard Overlay Front Rd to Bluff Rd | $660,000 | Planned | ||
| FY 2025 | 1-80819-0000 1808190000 | District 1 | Eisenhower ExpwyI-290IL-110 | Rehabilitation - Bridges Bridge Substructure Rehab, Bridge Superstructure Rehab At Keeler Ave (Overhead) | $14,000,000 | Planned | ||
| FY 2025 | 1-80864-0000 1808640000 | District 1 | Busse RdIL-83 | Preservation - Pavements Smart Overlay Ill 72 (Higgins Rd) to Devon Ave | $6,420,000 | Planned | ||
| FY 2025 | 1-80882-0000 1808820000 | District 1 | IL-53 | Preservation - Pavements Smart Overlay 75th St to Will Co Line | $3,900,000 | Planned | ||
| FY 2025 | 1-80897-0000 1808970000 | District 1 | Halsted StIL-1 | Maintenance - Bridges Bridge Repair At Little Calumet River | $4,500,000 | Planned | ||
| FY 2025 | 1-80901-0000 1809010000 | District 1 | Southwest HwyUS-6 | Rehabilitation - Pavement Designed Overlay, ADA Improvements, Miscellaneous S of Wolf Rd to Will-Cook Rd | $900,000 | Planned | ||
| FY 2025 | 1-80929-0000 1809290000 | District 1 | Paulina St | Rehabilitation - Pavement Designed Overlay, Pavement Replacement, Reconstruction 127th St to Vermont Ave | $146,000 | Planned | ||
| FY 2025 | 1-80964-0000 1809640000 | District 1 | Collins StIL-171US-6 | Preservation - Pavements Smart Overlay US 6/30 (Lincoln Hwy) (Cass St) to Division St | $3,000,000 | Planned | ||
| FY 2025 | 1-81090-0000 1810900000 | District 1 | IL-171 | Preservation - Bridges Bridge Joint Replace/Repair, Bridge Deck Overlay At Joliet Rd & BN RR Spur | $1,774,000 | Planned | ||
| FY 2025 | 1-81126-0000 1811260000 | District 1 | I-55 | Maintenance - Bridges Bridge Repair At Cass Ave (Overhead) | $2,000,000 | Planned | ||
| FY 2025 | 1-81127-0002 1811270002 | District 1 | Edens ExpwyI-94 | Maintenance - Pavements Bridge Repair At Touhy Ave (Overhead) | $1,000,000 | Planned | ||
| FY 2025 | 1-81182-0000 1811820000 | District 1 | US-14 | Preservation - Pavements Smart Overlay State Line Rd to N of Oak Grove Rd | $1,100,000 | Planned | ||
| FY 2025 | 1-81185-0000 1811850000 | District 1 | IL-72 | Preservation - Pavements Smart Overlay Reinking Rd to Industrial Dr | $1,240,000 | Planned | ||
| FY 2025 | 1-81187-0000 1811870000 | District 1 | Cumberland AveIL-171 | Preservation - Pavements Smart Overlay N of Forest Preserve Dr to Des Plaines River | $2,200,000 | Planned | ||
| FY 2025 | 1-81196-0000 1811960000 | District 1 | Busse RdIL-83 | Preservation - Pavements Smart Overlay S of Bryn Mawr Ave to Ill 19 (Irving Park Rd) | $3,005,000 | Planned | ||
| FY 2025 | 1-81205-0000 1812050000 | District 1 | Cicero AveIL-50US-41 | Preservation - Pavements Smart Overlay N of Golf Rd to Devon Ave | $9,100,000 | Planned | ||
| FY 2025 | 1-81206-0000 1812060000 | District 1 | Governors HwyIL-50 | Preservation - Pavements Smart Overlay Beecher Rd to Tucker Rd | $1,010,000 | Planned | ||
| FY 2025 | 1-81211-0000 1812110000 | District 1 | Lake StUS-45 | Preservation - Pavements Smart Overlay Ill 176 (Maple Ave) to Woodlawn Dr | $1,340,000 | Planned | ||
| FY 2025 | 1-81231-0000 1812310000 | District 1 | Higgins RdIL-72 | Preservation - Pavements Smart Overlay N Meacham Rd to I-290 Ramps (NB) | $2,000,000 | Planned | ||
| FY 2025 | 1-81263-0000 1812630000 | District 1 | Grand AveWolf Rd | Miscellaneous Improvement Signal Timing/Progression 1) Grand Ave - Northwest Ave to Wolf Rd, 2) Wolf Rd - Grand Ave to Diversey Ave | $400,000 | Planned | ||
| FY 2025 | 1-81265-0000 1812650000 | District 1 | Elgin RdIL-25 | Miscellaneous Improvement Signal Timing/Progression Longmeadow Pkwy to Helm Rd | $135,000 | Planned | ||
| FY 2025 | 1-81269-0000 1812690000 | District 1 | IL-25John F Kennedy Dr | Miscellaneous Improvement Traf Signal Installation, Signal Timing/Progression Golfview Rd to Ill 72 (Higgins Rd) | $425,000 | Planned | ||
| FY 2025 | 1-81271-0000 1812710000 | District 1 | Belvidere StIL-120 | Miscellaneous Improvement Signal Timing/Progression Ruth Wilcox Ave/Knight Ave to Ill 131 (Green Bay Rd) | $185,000 | Planned | ||
| FY 2025 | 1-81272-0000 1812720000 | District 1 | Belvidere RdIL-120 | Miscellaneous Improvement Signal Timing/Progression US 45 (Lake St) to Mill St | $335,000 | Planned | ||
| FY 2025 | 1-81281-0000 1812810000 | District 1 | Dempster StUS-14 | Miscellaneous Improvement Signal Timing/Progression Ill 21 (Milwaukee Ave) to Ozark Ave | $165,000 | Planned | ||
| FY 2025 | 1-81283-0000 1812830000 | District 1 | 211th StUS-30 | Miscellaneous Improvement Signal Timing/Progression Matteson Ave to Brookwood Dr | $185,000 | Planned | ||
| FY 2025 | 1-81287-0000 1812870000 | District 1 | 25th Ave | Miscellaneous Improvement Signal Timing/Progression Armitage Ave to Ill 64 (North Ave) - (Centracs Econ 100) | $175,000 | Planned | ||
| FY 2025 | 1-81288-0000 1812880000 | District 1 | Touhy AveUS-14 | Miscellaneous Improvement Signal Timing/Progression Ill 43 (Harlem Ave) to US 41 (Lincoln Ave) - (Centracs Econ 156 & Eagle 4D) | $1,325,000 | Planned | ||
| FY 2025 | 1-81289-0000 1812890000 | District 1 | IL-21Milwaukee Ave | Miscellaneous Improvement Signal Timing/Progression Sanders Rd to Euclid Ave (Centracs) | $150,000 | Planned | ||
| FY 2025 | 1-81299-0000 1812990000 | District 1 | Eisenhower ExpwyI-290IL-110 | Maintenance - Pavements Storm Sewer (New), Drainage Des Plaines River to Austin Blvd | $50,000,000 | Planned | ||
| FY 2025 | 1-81306-0000 1813060000 | District 1 | US-20 | Maintenance - Pavements Ramp Modifications, Noise Barriers At Illinois Ave & Lavoie Ave Ramps | $25,000,000 | Planned | ||
| FY 2025 | 1-81350-0000 1813500000 | District 1 | Various Routes | Miscellaneous Improvement Traf Signal Modernization At Various Locations | $3,500,000 | Planned | ||
| FY 2025 | 1-81354-0000 1813540000 | District 1 | Various Routes | Miscellaneous Improvement Traf Signal Modernization, ADA Improvements At Various Locations | $2,750,000 | Planned | ||
| FY 2025 | 1-81355-0000 1813550000 | District 1 | Various Routes | Miscellaneous Improvement Intersection Improvement, Traf Signal Modernization At Various Locations | $2,500,000 | Planned | ||
| FY 2025 | 1-81376-0020 1813760020 | District 1 | IL-19Irving Park Rd | Preservation - Bridges Bridge Joint Replace/Repair, Bridge Deck Overlay At Des Plaines River | $1,500,000 | Planned | ||
| FY 2025 | 1-81379-0010 1813790010 | District 1 | IL-31 | Preservation - Bridges Bridge Joint Replace/Repair, Bridge Deck Overlay At Nippersink Creek | $1,000,000 | Planned | ||
| FY 2025 | 1-81413-0000 1814130000 | District 1 | IL-120Washington St | Rehabilitation - Pavement Standard Overlay, ADA Improvements, Miscellaneous US 14 to IL 47 | $3,000,000 | Planned | ||
| FY 2025 | 1-81424-0000 1814240000 | District 1 | Church Rd | Rehabilitation - Pavement Designed Overlay N of Maclean Ave to S of Central Ave | $1,500,000 | Planned |
1–100 of 516Next ›
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.