IDOT Jobs

All dates · 88 jobs · $2,097,291,000 Sign up free
★ My Jobs

Filtered by: Work type: Initial Construction - Pa Clear all

88 jobs · $2,097,291,000 estimated

ExcelCSV
Let date Contract / PPS County / Division Highway Description Estimate Status Added Low bidder
— 1-71097-0100 1710970100 District 1 Lake StUS-45 Initial Construction - Pa Additional Lanes, ADA Improvements 0.1 Mi N of Ill 132 (Grand Ave) to Washington St $18,000,000 Planned Nov 25 New
— 1-71097-0102 1710970102 District 1 Lake StUS-45 Initial Construction - Pa Utility Adjustment 0.1 Mi N of Ill 132 (Grand Ave) to Washington St $1,000,000 Planned Nov 25 New
— 1-71097-0800 1710970800 District 1 Lake StUS-45 Initial Construction - Pa Miscellaneous 0.1 Mi N of Ill 132 (Grand Ave) to Washington St $1,000,000 Planned Nov 25 New
— 1-71354-0100 1713540100 District 1 Half Day RdIL-22 Initial Construction - Pa Additional Lanes Quentin Rd to E of ILL 83 (Mundelein Rd) $44,808,000 Planned Nov 25 New
— 1-71621-1100 1716211100 District 1 IL-21Milwaukee Ave Initial Construction - Pa Additional Lanes N of Sanders Rd to S of Euclid Ave / Lake Ave $1,375,000 Planned Nov 25 New
— 1-73626-0001 1736260001 District 1 Willow Rd Initial Construction - Pa Utility Adjustment E of Des Plaines River to Waterview Dr / Protection Pkwy $500,000 Planned Nov 25 New
— 1-73626-3000 1736263000 District 1 Willow Rd Initial Construction - Pa Additional Lanes E of Des Plaines River to Waterview Dr / Protection Pkwy $11,400,000 Planned Nov 25 New
— 1-75131-0500 1751310500 District 1 Green Bay RdIL-131 Initial Construction - Pa Utility Adjustment Wadsworth Rd to Sunset Ave $1,000,000 Planned Nov 25 New
— 1-75131-2000 1751312000 District 1 Green Bay RdIL-131 Initial Construction - Pa Additional Lanes, ADA Improvements Wadsworth Rd to Sunset Ave $26,280,000 Planned Nov 25 New
— 1-75131-2500 1751312500 District 1 Green Bay RdIL-131 Initial Construction - Pa Utility Adjustment Wadsworth Rd to Sunset Ave $1,000,000 Planned Nov 25 New
— 1-77065-4000 1770654000 District 1 I-190Kennedy Expwy Initial Construction - Pa Bridge Replacement At Bessie Coleman Intchg $90,000,000 Planned Nov 25 New
— 1-77065-5011 1770655011 District 1 I-190Kennedy Expwy Initial Construction - Pa Add Auxiliary Lanes Des Plaines River Bridge to River Rd $26,307,000 Planned Nov 25 New
— 1-77065-5021 1770655021 District 1 I-190Kennedy Expwy Initial Construction - Pa Add Auxiliary Lanes Bessie Coleman Intchg (EB) to I-294 (Tri-State Tollway) $48,287,000 Planned Nov 25 New
— 1-77065-5041 1770655041 District 1 (westbound)I-190Kennedy Expwy Initial Construction - Pa Add Auxiliary Lanes Des Plaines River Rd to Bessie Coleman Intchg (WB) $32,440,000 Planned Nov 25 New
— 1-77065-5051 1770655051 District 1 I-190Kennedy Expwy Initial Construction - Pa Add Auxiliary Lanes I-294 (Tri-State Tollway) to Des Plaines River Rd $29,929,000 Planned Nov 25 New
— 1-77065-5064 1770655064 District 1 I-190Kennedy Expwy Initial Construction - Pa Add Auxiliary Lanes At US 12/45 (Mannheim Rd) Intchg $34,394,000 Planned Nov 25 New
— 1-77548-0000 1775480000 District 1 Skokie HwyUS-41 Initial Construction - Pa Additional Lanes, Interchange Construction, ADA Improvements At ILL 176 (Rockland Rd) $30,600,000 Planned Nov 25 New
— 1-77633-1300 1776331300 District 1 I-55 Initial Construction - Pa Add Auxiliary Lanes ILL 129 to Lorenzo Rd $14,375,000 Planned Nov 25 New
— 1-79214-0000 1792140000 District 1 I-55 Initial Construction - Pa Bridge Replacement At Airport Rd / Lockport Rd $85,500,000 Planned Nov 25 New
— 1-79214-0500 1792140500 District 1 I-55 Initial Construction - Pa Utility Adjustment At Airport Rd / Lockport Rd $1,000,000 Planned Nov 25 New
— 1-79214-1000 1792141000 District 1 I-55 Initial Construction - Pa Bridge Replacement At Ill 126 (Main St) $85,500,000 Planned Nov 25 New
— 1-79214-1500 1792141500 District 1 I-55 Initial Construction - Pa Utility Adjustment At Ill 126 (Main St) $4,000,000 Planned Nov 25 New
— 1-79735-0000 1797350000 District 1 I-55 Initial Construction - Pa Add Auxiliary Lanes I-355 to Ill 53 (Bolingbrook Dr) $24,800,000 Planned Nov 25 New
— 1-79735-0400 1797350400 District 1 I-55 Initial Construction - Pa Utility Adjustment I-355 to Ill 53 (Bolingbrook Dr) $2,000,000 Planned Nov 25 New
— 1-79967-2001 1799672001 District 1 Jefferson StUS-52 Initial Construction - Pa Additional Lanes River Rd to Houbolt Rd $45,600,000 Planned Nov 25 New
— 1-79967-2600 1799672600 District 1 Jefferson StUS-52 Initial Construction - Pa Utility Adjustment River Rd to Houbolt Rd $4,000,000 Planned Nov 25 New
— 1-80552-0000 1805520000 District 1 I-57 Initial Construction - Pa Interchange (New) at Eagle Lake Rd $150,000,000 Planned Nov 25 New
— 1-80552-0400 1805520400 District 1 I-57 Initial Construction - Pa Utility Adjustment at Eagle Lake Rd $2,000,000 Planned Nov 25 New
— 1-80552-0500 1805520500 District 1 I-57 Initial Construction - Pa RR Crossing Construction at Eagle Lake Rd $2,000,000 Planned Nov 25 New
— 1-80558-0000 1805580000 District 1 Belvidere RdIL-120 Initial Construction - Pa Additional Lanes Ashford Ln to US 45 $13,410,000 Planned Nov 25 New
— 1-80558-0400 1805580400 District 1 Belvidere RdIL-120 Initial Construction - Pa Utility Adjustment Ashford Ln to US 45 $500,000 Planned Nov 25 New
— 1-88560-0000 1885600000 District 1 IL-60IL-83 Initial Construction - Pa Additional Lanes ILL 176 (Maple Ave) to Midlothian Rd $33,000,000 Planned Nov 25 New
— 1-88560-0106 1885600106 District 1 IL-60IL-83 Initial Construction - Pa Utility Adjustment ILL 176 (Maple Ave) to CN RR $6,000,000 Planned Nov 25 New
— 1-88560-0116 1885600116 District 1 IL-60IL-83 Initial Construction - Pa Utility Adjustment ILL 176 (Maple Ave) to Midlothian Rd $3,000,000 Planned Nov 25 New
— 1-88560-1115 1885601115 District 1 IL-60IL-83 Initial Construction - Pa Additional Lanes Midlothian Rd to 0.1 mi W of Diamond Lake Rd $22,461,000 Planned Nov 25 New
— 2-06700-0200 2067000200 District 2 IL-2N Main St Initial Construction - Pa Culvert Replacement 0.4 Mi N of Latham Rd to 0.8 mi N of Roscoe Rd $35,000,000 Planned Nov 25 New
— 2-11540-0100 2115400100 District 2 US-20 BUS Initial Construction - Pa Additional Lanes Shaw Rd E of Winnebago Co Line to 0.1 Mi NE of State St in Belvidere $25,530,000 Planned Nov 25 New
— 2-11540-0104 2115400104 District 2 US-20 BUS Initial Construction - Pa Utility Adjustment Shaw Rd E of Winnebago Co Line to 0.1 Mi NE of State St in Belvidere $250,000 Planned Nov 25 New
— 2-15230-0100 2152300100 District 2 US-20 BUS Initial Construction - Pa Additional Lanes Belvidere Byp: ILL 76 to US 20 in Belvidere $12,600,000 Planned Nov 25 New
— 2-20270-0050 2202700050 District 2 I-39US-51 Initial Construction - Pa Utility Adjustment Lee Co Line to 0.8 Mi N of Blackhawk Rd $250,000 Planned Nov 25 New
— 2-25000-0200 2250000200 District 2 IL-5 Initial Construction - Pa Additional Lanes E of 27th St to 0.2 mi w of 38th St in Moline $2,750,000 Planned Nov 25 New
— 2-25000-0400 2250000400 District 2 I-74US-6 Initial Construction - Pa Additional Lanes 0.9 Mi S of 23rd Ave (Ave of The Cities) in Moline to 0.5 mi S of ILL 5 $2,750,000 Planned Nov 25 New
— 2-98030-0300 2980300300 District 2 IL-251IL-38 Initial Construction - Pa Additional Lanes ILL 251: 0.3 mi N of Flagg Rd to 0.2 mi S of ILL 38 (E) & ILL 38: ILL 251 to 0.1 mi E in Rochelle $2,839,000 Planned Nov 25 New
— 3-04747-0010 3047470010 District 3 IL-47 Initial Construction - Pa Additional Lanes ILL 71 to Caton Farm Rd $20,000,000 Planned Nov 25 New
— 3-20627-5180 3206275180 District 3 E 494th Rd Initial Construction - Pa New Construction ILL 71 to 0.2 mi NE (Dead End) $500,000 Planned Nov 25 New
— 3-36940-0100 3369400100 District 3 US-6 Initial Construction - Pa Additional Lanes Ashton Rd to ILL 47 in Morris $25,000,000 Planned Nov 25 New
— 3-36940-0109 3369400109 District 3 US-6 Initial Construction - Pa Utility Adjustment Ashton Rd to ILL 47 in Morris $2,000,000 Planned Nov 25 New
— 4-00018-0100 4000180100 District 4 IL-6 Initial Construction - Pa Interchange (New) At Proposed Pioneer Pkwy Ext in Peoria $70,000,000 Planned Nov 25 New
— 4-03623-0000 4036230000 District 4 US-34 Initial Construction - Pa New Construction 0.9 Mi W of Carman Rd to 1350 E Rd (TR 111) $155,000,000 Planned Nov 25 New
— 4-03623-0050 4036230050 District 4 US-34 Initial Construction - Pa Utility Adjustment 0.9 Mi W of Carman Rd to 1350 E Rd (TR 111) $500,000 Planned Nov 25 New
— 4-04510-0100 4045100100 District 4 IL-9US-24 Initial Construction - Pa Additional Lanes Banner to E of Romine Rd $49,000,000 Planned Nov 25 New
— 4-04510-0102 4045100102 District 4 IL-9US-24 Initial Construction - Pa Utility Adjustment Banner to E of Romine Rd $700,000 Planned Nov 25 New
— 4-04510-0203 4045100203 District 4 IL-9US-24 Initial Construction - Pa Utility Adjustment E of Romine Rd to Kingston Mines $700,000 Planned Nov 25 New
— 4-04510-0400 4045100400 District 4 IL-9US-24 Initial Construction - Pa Additional Lanes E of Romine Rd to Kingston Mines $62,000,000 Planned Nov 25 New
— 4-04510-0403 4045100403 District 4 IL-9US-24 Initial Construction - Pa Utility Adjustment E of Romine Rd to Kingston Mines $600,000 Planned Nov 25 New
— 6-00200-0000 6002000000 District 6 I-55 Initial Construction - Pa Additional Lanes 0.5 MI N OF ILL 54 / SANGAMON AVE IN SPRINGFIELD TO 2.7 MI S OF ILL 123 IN WILLIAMSVILLE $15,000,000 Planned Nov 25 New
— 6-00779-0100 6007790100 District 6 IL-125IL-97 Initial Construction - Pa Bridge (New) 0.5 MI W OF ILL 97/125 JCT TO OLD COVERED BRIDGE LN $16,500,000 Planned Nov 25 New
— 6-01048-0100 6010480100 District 6 E Cook StS Grand Ave ETansey Ave Initial Construction - Pa New Construction E COOK ST 0.4 MI E OF I-55 TO S GRAND AVE E / TANSEY AVE 0.2 MI N OF ILL 29 E OF SPRINGFIELD $1,400,000 Planned Nov 25 New
— 6-01048-0101 6010480101 District 6 E Cook StS Grand Ave ETansey Ave Initial Construction - Pa Utility Adjustment E COOK ST 0.4 MI E OF I-55 TO S GRAND AVE E / TANSEY AVE 0.2 MI N OF ILL 29 E OF SPRINGFIELD $300,000 Planned Nov 25 New
— 8-00176-0000 8001760000 District 8 US-40 Initial Construction - Pa Additional Lanes, Intersection Reconstn, Bi-Direct Left Turn Lane E of Formosa Rd in Troy to ILL 162 $48,200,000 Planned Nov 25 New
— 8-00176-0040 8001760040 District 8 US-40 Initial Construction - Pa Utility Adjustment E of Formosa Rd in Troy to ILL 162 $2,000,000 Planned Nov 25 New
— 8-00522-3000 8005223000 District 8 IL-3 CONNECTOR Initial Construction - Pa New Construction, Retaining Wall Fairmont City Blvd in Fairmont City to ILL 3/203 in Madison $34,000,000 Planned Nov 25 New
— 8-05082-0000 8050820000 District 8 Lebanon Byp Initial Construction - Pa Bridge (New) ILL 4 to US 50 0.1 mi W of Old US 50 $77,800,000 Planned Nov 25 New
— 8-81050-0200 8810500200 District 8 IL-3Relocation Initial Construction - Pa Bridge (New) 0.1 Mi S of River Park Connector to 0.1 Mi S of Trendley Ave Connector in East St Louis $95,000,000 Planned Nov 25 New
— 8-81050-0212 8810500212 District 8 IL-3Relocation Initial Construction - Pa Bridge (New) 0.1 Mi S of Trendley Ave Connector in East St Louis to Monsanto Ave in Sauget $68,000,000 Planned Nov 25 New
— 8-81050-0240 8810500240 District 8 IL-3Relocation Initial Construction - Pa Utility Adjustment 0.1 Mi S of River Park Connector to 0.1 Mi S of Trendley Ave Connector in East St Louis $1,500,000 Planned Nov 25 New
— 8-81050-0260 8810500260 District 8 IL-3Relocation Initial Construction - Pa Bridge (New) 0.1 Mi S of River Park Connector to 0.1 Mi S of Trendley Ave Connector in East St Louis $75,000,000 Planned Nov 25 New
— 8-81050-0262 8810500262 District 8 IL-3Relocation Initial Construction - Pa Bridge (New) 0.1 Mi S of Trendley Ave Connector in East St Louis to Monsanto Ave in Sauget $45,000,000 Planned Nov 25 New
— 8-81050-4212 8810504212 District 8 IL-3Relocation Initial Construction - Pa Utility Adjustment 0.1 Mi S of Trendley Ave Connector in East St Louis to Monsanto Ave in Sauget $5,000,000 Planned Nov 25 New
— 8-82220-5020 8822205020 District 8 I-270 Initial Construction - Pa Additional Lanes Chain of Rocks Canal in Granite City to 0.1 mi E of St. Thomas Rd $11,000,000 Planned Nov 25 New
— 8-89500-0000 8895000000 District 8 Greenmount Rd Initial Construction - Pa Additional Lanes ILL 161 to ILL 158/177 in Belleville $11,000,000 Planned Nov 25 New
— 8-89500-0400 8895000400 District 8 Greenmount Rd Initial Construction - Pa Utility Adjustment ILL 161 to ILL 158/177 in Belleville $1,500,000 Planned Nov 25 New
FY 2025 1-71354-0200 1713540200 District 1 Half Day RdIL-22 Initial Construction - Pa Tree Removal Quentin Rd to W of ILL 83 (Mundelein Rd) $200,000 Planned Nov 25 New
FY 2025 1-75939-0000 1759390000 District 1 Front StIL-31 Initial Construction - Pa Additional Lanes Ill 120 to Bull Valley Rd $29,650,000 Planned Nov 25 New
FY 2025 1-75939-0200 1759390200 District 1 Front StIL-31 Initial Construction - Pa Additional Lanes, ADA Improvements Bull Valley Rd to ILL 176 (Terra Cotta Ave) $40,000,000 Planned Nov 25 New
FY 2025 1-75939-0201 1759390201 District 1 Front StIL-31 Initial Construction - Pa Utility Adjustment S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) $4,000,000 Planned Nov 25 New
FY 2025 1-75939-0202 1759390202 District 1 Front StIL-31 Initial Construction - Pa Utility Adjustment S of ILL 120 (Belvidere Rd) to N of ILL 176 (Terra Cotta Ave) $4,000,000 Planned Nov 25 New
FY 2025 1-77727-0000 1777270000 District 1 IL-47US-30 Initial Construction - Pa Additional Lanes, ADA Improvements Cross St to Jericho Rd $24,771,000 Planned Nov 25 New
FY 2025 1-77727-2000 1777272000 District 1 IL-47US-30 Initial Construction - Pa Additional Lanes Jericho Rd to 0.4 Mi S of Galena Rd $24,600,000 Planned Nov 25 New
FY 2025 1-77727-2400 1777272400 District 1 IL-47US-30 Initial Construction - Pa Utility Adjustment Jericho Rd to 0.4 Mi S of Galena Rd $2,500,000 Planned Nov 25 New
FY 2025 1-90013-1151 1900131151 District 1 IL-47Seminary St Initial Construction - Pa Utility Adjustment 0.1 Mi N of ILL 120 (McHenry Ave) to US 14 $1,400,000 Planned Nov 25 New
FY 2025 1-90013-4001 1900134001 District 1 IL-47Seminary St Initial Construction - Pa Additional Lanes Lake Ave to McConnell Rd $5,000,000 Planned Nov 25 New
FY 2025 2-15970-0415 2159700415 District 2 Harrison AveUS-20 Initial Construction - Pa Additional Lanes Mill Rd to 0.3 mi E of Kishwaukee River $3,315,000 Planned Nov 25 New
FY 2025 4-50401-1100 4504011100 District 4 US-34 Initial Construction - Pa Additional Lanes TR 190 E of Biggsville to 20th St S of Kirkwood $60,000,000 Planned Nov 25 New
FY 2025 4-50401-1150 4504011150 District 4 US-34 Initial Construction - Pa Utility Adjustment TR 190 E of Biggsville to 20th St S of Kirkwood $500,000 Planned Nov 25 New
FY 2025 7-50239-0000 7502390000 District 7 IL-33US-40US-45 Initial Construction - Pa Additional Lanes, Storm Sewer (New), Curb And Gutter Banker St to Salt Creek in Effingham $4,220,000 Planned Nov 25 New
FY 2025 9-05550-2000 9055502000 District 9 (proposed)AccessWalkers Bluff Initial Construction - Pa New Construction Herrin Rd to Meridian Rd at Walkers Bluff $19,000,000 Planned Nov 25 New
FY 2025 9-05550-2004 9055502004 District 9 (proposed)AccessWalkers Bluff Initial Construction - Pa Utility Adjustment Herrin Rd to Meridian Rd at Walkers Bluff $500,000 Planned Nov 25 New
1–88 of 88

Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.