Let date Contract / PPS County / Division Highway Description Estimate Status Added Low bidder
Jan 16, 2026 61L81 WillDistrict 1 Resurfacing Remington Road from Weber Road to Claar Boulevard in Romeoville. — Executed Nov 25 New K-Five Construction Corporation $596,750 ·
Jan 16, 2026 61L99 WillDistrict 1 Decorative lighting, landscaping and parkway restoration on IL 50 from Bruce Street Road to Steger Drive in University Park. — Executed Nov 25 New Iroquois Paving Corporation $1,829,797 ·
Jan 16, 2026 61M01 WillDistrict 1 Widening and reconstruction of Seil Road and replacement of the Seil Road Bridge across the DuPage River in Shorewood. Includes; mini roundabouts and street lighting at Seil Road and Raven Road, and at Seil Road and States Lane. — Executed Nov 25 New Austin Tyler Construction, Inc. $8,923,156 ·
Jan 16, 2026 62F94 WillDistrict 1 The realignment and reconstruction of the mainline and interchange pavement and related roadway elements, incl (2,577-Ft) The work consists of the realignment and reconstruction of the mainline and interchange pavement and related roadway elements, including ramp and cross-road reconstruction, existing bridge removal, enclosed storm sewer system with drainage structures and detention ponds, earth excavation and embankment grading, installation of retaining and noise walls, barrier and moment slab construction, bridge replacement, roadway lighting, traffic signals ITS implementation, erosion and sediment — Executed Nov 25 New D. Construction, Inc. $104,386,503 ·
Jan 16, 2026 62R76 WillDistrict 1 Reconstruction of the expansion joints with strip seals, hydro scarification (3/4-), deck and approach slab re (290-Ft) Bridge Deck Overlay, (SN 099-0210) over I-55. The project consists of reconstruction of the expansion joints with strip seals, hydro scarification (3/4-), deck and approach slab repairs, latex concrete overlay (2¼-) with diamond grinding and longitudinal grooving, application of a protective coat, and substructure concrete repair. Roadway improvements include HMA on each side of the bridge. I-55 at Caton Farm Road (3 miles north of US 52) in the Village of Plainfield. — Executed Nov 25 New D. Construction, Inc. $647,187 ·
Jan 16, 2026 62Y09 WillDistrict 1 This is an advance procurement of selective mechanical, electrical, and structural components for the existing rolling movable bridges at Jackson Street and Jefferson Street over the Des Plaines River, Structure Number 099- 0239 and 099-0166 in Will County. — Executed Nov 25 New GRANITE CONSTRUCTION COMPANY $2,400,000 ·
Jan 16, 2026 80B11 WillDistrict 1 (6,160-Ft) Standard Overlay, New Shoulders, and ADA Improvements include: Hot- mix asphalt (HMA) surface removal (cold milling), full-depth patches (Class D), resurfacing (inlay) with HMA binder and surface course, longitudinal joint sealing, replacement of curb and gutter, sidewalk removal and replacement for curb ramps for sidewalks (ADA), replacement of existing aggregate shoulders with HMA, drainage structures adjustments and cleaning, new thermoplastic pavement markings and raised reflectiv — Executed Nov 25 New Iroquois Paving Corporation $1,297,699 ·
Jan 16, 2026 80B14 WillDistrict 1 Resurfacing the existing HMA pavement with HMA surface and binder course, thermoplastic pavement markings loca (1.19-Mile) This project-s scope is designed overlay. It consists of resurfacing the existing HMA pavement with HMA surface and binder course, thermoplastic pavement markings located along US 6 (Channahon Rd) from Terry Drive of IL 7 (Larkin Ave) in the City of Joliet in Will County. — Executed Nov 25 New D. Construction, Inc. $2,039,223 ·
Jan 16, 2026 80B34 WillDistrict 1 Resurfacing the existing HMA pavement with HMA surface and binder course, HMA Shoulder, thermoplastic pavement 3,241 Ft) Standard Overlay, consists of resurfacing the existing HMA pavement with HMA surface and binder course, HMA Shoulder, thermoplastic pavement markings, ADA Improvements for curb ramps. Located on IL 7(159th St.) from Robson Dr. to E of Adellman Dr. in the City of Lockport in Will County. — Executed Nov 25 New Gallagher Asphalt Corporation $977,777 ·
Jan 16, 2026 80B36 WillDistrict 1 Pavement patching, resurfacing with polymerized hot-mix asphalt surface course, binder course, ADA improvement (1.6-Mile) Project consists of pavement patching, resurfacing with polymerized hot-mix asphalt surface course, binder course, ADA improvement, median removal and replacement and curb and gutter replacement, thermoplastic pavement marking. This improvement is in the Village of Frankfort and Frankfort Township in Will County. — Executed Nov 25 New D. Construction, Inc. $3,250,096 ·
Jan 16, 2026 80B86 CookDuPageWillDistrict 1 The pickup, removal and satisfactory disposal of debris, deceased animal carcasses, refuse, Litter and any oth Litter Picking project shall consist of the pickup, removal and satisfactory disposal of debris, deceased animal carcasses, refuse, Litter and any other rubbish. This work is located on I-55 - Stevenson expressway from Reed Road to Lake Shore Dr in Cook, DuPage, and Will Counties. — Executed Nov 25 New Thor General Contracting LLC $515,515 ·
Jan 16, 2026 80C53 WillDistrict 1 Fabrication an delivery of structural steel and bearings for the construction of two bridges (SN 099-0902 EB and 099-0903 WB) carrying I-80 over Chicago Ramp B, BNSF RR, UP RR, and Gardner Street in Joliet. — Executed Nov 25 New Industrial Steel Construction, Inc. $10,415,094 ·
1–12 of 12

Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.