The realignment and reconstruction of the mainline and interchange pavement and related roadway elements, incl

Executed

(2,577-Ft) The work consists of the realignment and reconstruction of the mainline and interchange pavement and related roadway elements, including ramp and cross-road reconstruction, existing bridge removal, enclosed storm sewer system with drainage structures and detention ponds, earth excavation and embankment grading, installation of retaining and noise walls, barrier and moment slab construction, bridge replacement, roadway lighting, traffic signals ITS implementation, erosion and sediment

Let date
Friday, January 16, 2026
Bids open
Jan 16, 2026 12:00 PM
District
District 1
County
Will
Letting item
184
Added
Nov 25, 2026 No longer listed