| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 19, 2024 | 76F88 | MadisonDistrict 8 | Superstructure replacement on the north Southern Illinois University - Edwardsville entrance road over the Norfolk Southern Railroad (SN 060-0142 and SN 060-0143). | — | Rejected | Keller Construction, Inc. $4,559,532 · | ||
| Jan 19, 2024 | 76H49 | MadisonDistrict 8 | Replacement of SN 060-0347 carrying IL 111 southbound over Cahokia Canal, 0.24 miles north of I-55/70. Project also includes maintenance of the northbound structure, SN 060-0244. | — | Active | Plocher Construction Company, Inc. $8,868,716 · | ||
| Jan 19, 2024 | 76L82 | MadisonDistrict 8 | Bridge deck sealing on SN 060-0345 carrying I-270 over Chain of Rocks Canal. | — | Executed | All States Painting, Inc. $64,882 · | ||
| Jan 19, 2024 | 76R91 | MadisonDistrict 8 | New platform scales and patching at the Maryville Weight Station on westbound I-55 / I-70 approximately 1 mile west of Maryville. | — | Executed | Stutz Excavating, Inc. $739,349 · | ||
| Jan 19, 2024 | 97769 | MadisonDistrict 8 | HMA resurfacing with concrete curb and gutter, storm sewers, and signage on Sugar Loaf Road from west of Hone Lane to IL 157 in Collinsville. | — | Executed | DMS Contracting, Inc. $778,107 · | ||
| Jan 19, 2024 | 97824 | MadisonDistrict 8 | Resurfacing Johnson Road from Wabash Avenue to Edgewood Avenue in Granite City. | — | Executed | Hank's Excavating & Landscaping, Inc. $938,631 · | ||
| Jan 19, 2024 | 97826 | MadisonDistrict 8 | HMA resurfacing with sidewalks, driveways, curb and gutter on Keebler Road from Sher Nan Drive to West Main Street in Maryville | — | Rejected | Stutz Excavating, Inc. $829,420 · | ||
| Mar 8, 2024 | 76R84 | MadisonSt. ClairDistrict 8 | Traffic signal modernization at various intersections in District 8. (IL 3 / IL 111 at Godfrey Road; IL 203 at Madison Avenue / High Street; IL 203 at Ohio Avenue) | — | Executed | Electrico, Inc. $546,454 · | ||
| Mar 8, 2024 | 76T19 | MadisonDistrict 8 | Patching on IL 203 from Eagle Creek Road to the St. Clair County line. | — | Executed | G. M. Sipes Construction, Inc. $214,416 · | ||
| Mar 8, 2024 | 76T24 | MadisonDistrict 8 | 2.19 miles of SMART overlay milling and resurfacing, pavement patching, guardrail improvements, and pavement marking on W Frontage Rd from 0.1 miles east of of Park Street in Livingston to the Macoupin County Line. | — | Executed | The Kilian Corporation $1,320,855 · | ||
| Mar 8, 2024 | 76T27 | BondMadisonDistrict 8 | 4.9 miles of fog seal on Schuster Road in Madison County from IL 143 to Bauman Road and on Freys Meadow Avenue in Bond County from Bauman Road to 1 mile west of Pokey Road. | — | Executed | DMS Contracting, Inc. $289,901 · | ||
| Mar 8, 2024 | 76T33 | MadisonDistrict 8 | 0.9 miles of resurfacing on Vadalabene Drive from IL 162 to IL 159 in Maryville. | — | Executed | Charles E. Mahoney Co. $367,895 · | ||
| Mar 8, 2024 | 97830 | MadisonDistrict 8 | PCC Pavement, sidewalks, driveways, storm sewers, and pavement markings on Sixth Street from Pine Street to Poplar Street in Highland. | — | Executed | RCS Construction, Inc. $1,549,285 · | ||
| Apr 26, 2024 | 76R12 | MadisonDistrict 8 | Bridge deck sealing on US 67 at the Clark Bridge (SN 0606-0255) over the Mississippi River in Alton. | — | Executed | All States Painting, Inc. $77,994 · | ||
| Apr 26, 2024 | 76R39 | MadisonDistrict 8 | 6.3 miles of crack and joint sealing on I-70 from 0.1 miles west of Prairie Road to the Bond County line. | — | Executed | Complete Asphalt Service Co. $199,270 · | ||
| Apr 26, 2024 | 76R59 | MadisonDistrict 8 | Milling and resurfacing of the District 8 office parking area (west, southwest parking area and loading docks). | — | Executed | Christ Bros. Asphalt, Inc. $539,212 · | ||
| Apr 26, 2024 | 76T53 | MadisonSt. ClairDistrict 8 | Traffic signal modernization at various locations: St. Clair Ave. and 37th/38th Street; Foley Drive/70th Street and W. Main Street; 74th Street and Foley Drive; IL 159 and IL 13/158; IL 15 and 74th Street; IL 161 and Frank Scott Parkway in Belleville; IL 3 and Pontoon Road in Granite City. | — | Executed | Electrico, Inc. $263,300 · | ||
| Apr 26, 2024 | 76T54 | JerseyMadisonDistrict 8 | Bridge approach roadway on IL 255 and US 67 at various locations: IL 255 over Humbert Road (SN 060-0309), UP and KCS Railroad (SN 060-0311), and over IL 111/IL 267 (SN 060-0331); US 67 over IL 255 (SN 060-0332) and over Piasa Creek (SN 042-0027). | — | Executed | Charles E. Mahoney Co. $626,537 · | ||
| Apr 26, 2024 | 76T65 | MadisonDistrict 8 | 6.6 miles of overlay on IL 140 from 0.2 miles west of IL 159 to 0.1 miles west of Park Avenue. | — | Executed | Charles E. Mahoney Co. $2,396,248 · | ||
| Apr 26, 2024 | 97807 | MadisonDistrict 8 | Construct a PCC Shared Use Path adjacent to IL 157 with concrete curb and gutter, driveway, drainage structures, retaining walls, traffic signal modifications, pavement markings and signage from the MCT Nature Trail to Levis Road in Edwardsville. | — | Executed | DMS Contracting, Inc. $1,053,422 · | ||
| Jun 14, 2024 | 76P46 | MadisonDistrict 8 | Bridge repair on SN 060-0124, HMA overlay and joint repair on IL 111 over NW and CNW and MCT Bike Trail, 0.2 miles north of IL 162 in Pontoon Beach. | — | Executed | Keeley & Sons, Inc. $2,475,979 · | ||
| Jun 14, 2024 | 76P58 | MadisonDistrict 8 | 2.2 miles of resurfacing and ADA improvements on Beltline Road from IL 157 to IL 159 in Collinsville. | — | Executed | Christ Bros. Asphalt, Inc. $3,984,987 · | ||
| Jun 14, 2024 | 76T28 | MadisonDistrict 8 | Bridge joint repair/replacement and bridge deck repairs on IL 4 over US 40. | — | Executed | Keeley & Sons, Inc. $1,211,533 · | ||
| Jun 14, 2024 | 76T88 | MadisonDistrict 8 | Patching, milling and resurfacing on US 67 from 10th Street in Alton to IL 111 in Godfrey. | — | Executed | Charles E. Mahoney Co. $4,047,724 · | ||
| Jun 14, 2024 | 97829 | MadisonDistrict 8 | Resurface Third Street from Ewing Avenue to McCambridge Avenue in Madison. | — | Executed | Stutz Excavating, Inc. $1,028,780 · | ||
| Jun 14, 2024 | 97832 | MadisonDistrict 8 | Resurface South Moreland Road from IL 143 to 0.2 miles south of IL 140. | — | Executed | The Kilian Corporation $1,971,366 · | ||
| Jun 14, 2024 | 97835 | MadisonDistrict 8 | HMA resurfacing with pavement patching, dowel bar retrofitting, thermoplastic pavement markings and signage on University Drive from University Park Drive to Stadium Drive on the SIU Campus in Edwardsville. | — | Executed | The Kilian Corporation $864,757 · | ||
| Jun 14, 2024 | 97836 | MadisonDistrict 8 | Rehabilitate the structure carrying Brown Street over Shields Branch in Alton. Includes linging the existing structure with precast concrete box culvert sections, HMA resurfacing, sidewalk, guardrail, pedestrian railing, riprap, storm sewer, pavment markings, and other work. | — | Executed | Stutz Excavating, Inc. $730,633 · | ||
| Aug 2, 2024 | 76818 | MadisonDistrict 8 | Reconstruction of the IL 111 and I-270 interchange. | — | Executed | Baxmeyer Construction, Inc. $25,120,777 · | ||
| Aug 2, 2024 | 76U11 | MadisonSt. ClairDistrict 8 | Dynamic message sign replacement at various locations in District 8. | — | Executed | CSD Environmental Services, Inc. $734,322 · | ||
| Aug 2, 2024 | 97840 | MadisonDistrict 8 | HMA resurfacing with patching, sidewalks, and curb and gutter, on Wood River Avenue from Gerguson Ave. to the north city limits of Wood River. | — | Rejected | Christ Bros. Asphalt, Inc. $1,584,636 · | ||
| Sep 20, 2024 | 76R46 | MadisonDistrict 8 | Addition of left turn lane and traffic signal modernization at the intersection of IL 111/IL 140 and Fosterburg Road. | — | Executed | Stutz Excavating, Inc. $1,956,212 · | ||
| Sep 20, 2024 | 76T73 | MadisonDistrict 8 | Tree removal at IL 162 and IL 157 in Glen Carbon. | — | Executed | Baxmeyer Construction, Inc. $97,978 · | ||
| Sep 20, 2024 | 97838 | MadisonDistrict 8 | HMA resurfacing, curb and gutter, sidewalks, ADA ramps, driveways, drainage improvements, pavement markings, traffic signal modifications, and other work on Troy Road from Franklin Avenue to 4th Avenue in Edwardsville. | — | Executed | Stutz Excavating, Inc. $909,557 · | ||
| Sep 20, 2024 | 97841 | MadisonDistrict 8 | Pavement widening, storm sewers, curb and guter and pavement markings at the intersection of Troy O'Fallon Road and Country lane in Troy. | — | Executed | The Kilian Corporation $1,151,288 · | ||
| Nov 8, 2024 | 76U19 | MadisonDistrict 8 | 8.25 miles of patching on IL 3 from the McKinley Bridge to 0.3 miles north of I-270. | — | Executed | Keeley & Sons, Inc. $449,676 · | ||
| Nov 8, 2024 | 97845 | MadisonDistrict 8 | Resurface Milton Road from Worden Avenue to Edgewood Avenue in Alton. | — | Executed | Charles E. Mahoney Co. $568,967 · | ||
| Nov 8, 2024 | 97846 | MadisonDistrict 8 | Replace bridge superstructure (PPC Deck Beams with composite deck) on Center Grove Road over the Nickel Plate Trail in Edwardsville. Work includes; concrete pier repair, PCC Pavement patching, guardrail replacement and pavement markings. | — | Executed | Keller Construction, Inc. $3,435,037 · | ||
| Dec 13, 2024 | 76U07 | MadisonDistrict 8 | Bridge joint replacement/repairs and bridge deck overlay on SN 060-0014 and 060-0015 carrying I-55/70 over Beltline Road. | — | Executed | Keeley & Sons, Inc. $2,833,156 · |
1–39 of 39
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.