(60Z)RS-1, 261RS-3
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Charles E. Mahoney Co. Low bidder | $4,047,724 | ||
| 2 | Christ Bros. Asphalt, Inc. | $4,157,951 | +2.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Charles E. Maho… | #2 Christ Bros. As… |
|---|---|---|---|---|---|---|---|
| 1 | X4402400 | CURB REMOVAL SPL | 8,846 | FOOT | $6.11 | $4.62 | |
| 2 | X4421385 | CL C PATCH T1 13 SPL | 4 | SQ YD | $1,145.85 | $1,146.00 | |
| 3 | X4421389 | CL C PATCH T2 13 SPL | 11 | SQ YD | $937.15 | $938.00 | |
| 4 | X8860105 | DET LOOP REPL | 2,482 | FOOT | $20.77 | $20.00 | |
| 5 | Z0034105 | MATL TRANSFER DEVICE | 13,038 | TON | $6.61 | $4.71 | |
| 6 | Z0036200 | PAINT CURB | 11,901 | FOOT | $2.25 | $3.25 | |
| 7 | Z0049000 | RAISED CURB MARKER | 22 | EACH | $13.35 | $13.35 | |
| 8 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 49,384 | POUND | $1.53 | $2.79 | |
| 11 | 40600370 | LONG JOINT SEALANT | 16,113 | FOOT | $4.42 | $2.50 | |
| 12 | 40600990 | TEMPORARY RAMP | 480 | SQ YD | $17.49 | $0.0100 | |
| 13 | 40602970 | HMA BC IL-9.5FG N70 | 3,511 | TON | $132.47 | $127.03 | |
| 14 | 40604162 | P HMA SC IL-9.5 D N70 | 4,214 | TON | $149.41 | $135.55 | |
| 15 | 44000160 | HMA SURF REM 2 3/4 | 84,663 | SQ YD | $5.73 | $5.42 | |
| 16 | 44201299 | DOWEL BARS 1 1/2 | 5 | EACH | $87.45 | $88.00 | |
| 17 | 44213200 | SAW CUTS | 68 | FOOT | $49.85 | $50.00 | |
| 18 | 44213204 | TIE BARS 3/4 | 23 | EACH | $57.85 | $58.00 | |
| 19 | 48203100 | HMA SHOULDERS | 5,313 | TON | $137.27 | $127.03 | |
| 20 | 63000001 | SPBGR TY A 6FT POSTS | 11,639 | FOOT | $27.25 | $38.00 | |
| 21 | 63100045 | TRAF BAR TERM T2 | 4 | EACH | $2,125.00 | $2,200.00 | |
| 22 | 63100085 | TRAF BAR TERM T6 | 13 | EACH | $4,050.00 | $4,100.00 | |
| 23 | 63100167 | TR BAR TRM T1 SPL TAN | 16 | EACH | $3,750.00 | $3,800.00 | |
| 24 | 63200310 | GUARDRAIL REMOV | 11,714 | FOOT | $5.75 | $6.00 | |
| 25 | 66101150 | HMA SHLD CURB | 8,846 | FOOT | $17.42 | $26.32 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $465,392.31 | $384,446.00 | |
| 27 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $0.0100 | |
| 28 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $53,678.44 | $70,400.00 | |
| 29 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $3,790.00 | $23,790.00 | |
| 30 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $24,626.69 | $139,425.00 | |
| 31 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $6,166.83 | $0.0100 | |
| 32 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1,875.00 | $1,875.00 | |
| 33 | 70107025 | CHANGEABLE MESSAGE SN | 476 | CAL DA | $41.00 | $41.00 | |
| 34 | 70300100 | SHORT TERM PAVT MKING | 4,506 | FOOT | $2.70 | $4.17 | |
| 35 | 70300150 | SHRT TRM PAVT MK REM | 752 | SQ FT | $6.13 | $0.0100 | |
| 36 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 250 | SQ FT | $0.0100 | $0.0100 | |
| 37 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 61,105 | FOOT | $0.0100 | $0.0100 | |
| 38 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 126 | FOOT | $0.0100 | $0.0100 | |
| 39 | 72501000 | TERMINAL MARKER - DA | 16 | EACH | $42.00 | $42.00 | |
| 40 | 78000100 | THPL PVT MK LTR & SYM | 250 | SQ FT | $12.00 | $12.00 | |
| 41 | 78000400 | THPL PVT MK LINE 6 | 61,105 | FOOT | $0.7400 | $0.7400 | |
| 42 | 78000650 | THPL PVT MK LINE 24 | 126 | FOOT | $12.00 | $12.00 | |
| 43 | 78100100 | RAISED REFL PAVT MKR | 308 | EACH | $41.55 | $41.55 | |
| 44 | 78200005 | GRDRAIL REF TYPE A | 323 | EACH | $10.50 | $11.00 | |
| 45 | 78300200 | RAISED REF PVT MK REM | 308 | EACH | $5.51 | $0.0100 | |
| 46 | 78300202 | PVT MKG REM WTR BLAST | 31,056 | SQ FT | $0.0100 | $0.0100 |