(580, 581)PP
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $214,416 | ||
| 2 | Kinney Contractors, Inc. | $279,739 | +30.5% | |
| 3 | Keeley & Sons, Inc. | $281,813 | +31.4% | |
| 4 | Keller Construction, Inc. | $284,364 | +32.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… | #3 Keeley & Sons, … | #4 Keller Construc… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 2 | 44200050 | WELDED WIRE REINF | 38 | SQ YD | $25.00 | $20.00 | $23.80 | $34.00 | |
| 3 | 44201007 | CL B PATCH T2 13 | 496 | SQ YD | $255.00 | $310.00 | $293.45 | $360.00 | |
| 4 | 44201011 | CL B PATCH T3 13 | 38 | SQ YD | $255.00 | $308.00 | $293.45 | $300.00 | |
| 5 | 44201299 | DOWEL BARS 1 1/2 | 1,176 | EACH | $10.00 | $27.00 | $38.90 | $31.00 | |
| 6 | 44213200 | SAW CUTS | 2,518 | FOOT | $8.95 | $9.00 | $8.67 | $7.00 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $10,500.00 | $16,000.00 | $16,700.00 | $23,600.00 | |
| 8 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $25,000.00 | $34,600.00 | $26,450.00 | $7,770.00 | |
| 9 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $500.00 | $2,990.00 | $0.0100 | |
| 10 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $500.00 | $2,988.60 | $160.00 | |
| 11 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $0.0100 | $1.00 | $0.0100 | $0.0100 |