(31-15)Q
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Charles E. Mahoney Co. Low bidder | $367,895 | ||
| 2 | Christ Bros. Asphalt, Inc. | $387,422 | +5.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Charles E. Maho… | #2 Christ Bros. As… |
|---|---|---|---|---|---|---|---|
| 1 | 40600290 | BIT MATLS TACK CT | 6,178 | POUND | $1.51 | $2.77 | |
| 2 | 40600370 | LONG JOINT SEALANT | 4,752 | FOOT | $3.66 | $3.67 | |
| 3 | 40600990 | TEMPORARY RAMP | 84 | SQ YD | $20.00 | $0.0100 | |
| 4 | 40604062 | HMA SC IL-9.5 D N70 | 1,153 | TON | $123.14 | $149.45 | |
| 5 | 44000155 | HMA SURF REM 1 1/2 | 13,728 | SQ YD | $5.20 | $2.46 | |
| 6 | 48102100 | AGG WEDGE SHLD TYPE B | 185 | TON | $0.0100 | $85.70 | |
| 7 | 63000001 | SPBGR TY A 6FT POSTS | 235 | FOOT | $32.00 | $30.50 | |
| 8 | 63000030 | SPGR ATT TO CULVERT | 75 | FOOT | $252.25 | $180.00 | |
| 9 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,350.00 | $3,354.35 | |
| 10 | 63200310 | GUARDRAIL REMOV | 262 | FOOT | $17.25 | $9.80 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $47,750.00 | $32,111.00 | |
| 12 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $4,000.00 | $16,068.00 | |
| 13 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1,000.00 | $16,068.00 | |
| 14 | 70300100 | SHORT TERM PAVT MKING | 432 | FOOT | $2.54 | $3.00 | |
| 15 | 70300150 | SHRT TRM PAVT MK REM | 144 | SQ FT | $12.00 | $0.0100 | |
| 16 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 12,540 | FOOT | $0.0100 | $0.0100 | |
| 17 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $41.00 | $25.00 | |
| 18 | 78000300 | THPL PVT MK LINE 5 | 13,702 | FOOT | $1.61 | $1.80 | |
| 19 | 78100100 | RAISED REFL PAVT MKR | 60 | EACH | $61.98 | $61.98 | |
| 20 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $10.25 | $10.00 | |
| 21 | 78300200 | RAISED REF PVT MK REM | 60 | EACH | $0.0100 | $0.0100 | |
| 22 | 78300202 | PVT MKG REM WTR BLAST | 4,180 | SQ FT | $0.0100 | $0.0100 |