Filtered by: County: Kane Clear all
| Let date | Contract / PPS | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 21, 2022 | 61H35 | KaneDistrict 1 | Reconfirguration of the ATC East Parking Lot to improve vehical and pedestrian traffic flow and to add additonal parking to lot on Spring Street between the BNSF Metra Line and the BNSF Railroad in Aurora. | — | Executed | Alliance Contractors, Inc. $1,093,662 · | ||
| Jan 21, 2022 | 61H40 | KaneDistrict 1 | Replace the bridge carrying Farnsworth Avenue over Indian Creek in Aurora | — | Executed | D. Construction, Inc. $2,563,926 · | ||
| Jan 21, 2022 | 61H41 | KaneDistrict 1 | Resurfacing, Curb and Gutter, Sidewalk replacement and pavement markings on Indian Trail from Farnsworth Avenue to the DuPage County line in Aurora. | — | Executed | Geneva Construction Company $706,127 · | ||
| Jan 21, 2022 | 61H43 | KaneDistrict 1 | Resurfacing Spring Street from McLean Boulevard to La Fox Steet in Sourth Elgin . | — | Executed | Plote Construction, Inc. $1,181,000 · | ||
| Jan 21, 2022 | 61H48 | KaneDistrict 1 | Resurfcing, curb and gutter replacement and sidewalk replacement on East New York Street from Ohio Street to Farnsworth Avenue in Aurora. | — | Executed | J. Nardulli Concrete, Inc. $1,441,342 · | ||
| Jan 21, 2022 | 61H49 | KaneDistrict 1 | Reconstruct the intersection of Orchard Road and US 30 in Montgomery. | — | Executed | D. Construction, Inc. $3,616,283 · | ||
| Jan 21, 2022 | 62N59 | KaneDistrict 1 | Roadway resurfacing, patching, aggregate shoulders, and centerline rumble strips (7.05-Mile) SMART Overlay project consists of roadway resurfacing, patching, aggregate shoulders, and centerline rumble strips. The project is along IL 47 from Big Timber Rd to Plato Rd in the Villages of Hampshire, Huntley, and Pingree Grove. | — | Executed | Builders Paving, LLC $3,208,000 · | ||
| Mar 11, 2022 | 62L90 | KaneDistrict 1 | (1.017-Mile) SMART Overlay and Drainage on US 20 (Grant Hwy) from McHenry County Line to I-90 (Jane Addams Memorial Tollway) in the Village of Hampshire. | — | Executed | Curran Contracting Company $1,168,843 · | ||
| Mar 11, 2022 | 62N60 | KaneDistrict 1 | (3.26-Mile) Resurfacing HMA pavement and shoulders, restriping pavement marking lines, making existing curb ramps ADA compliant, and described herein along IL-47, from Burlington Rd to IL-64 (North Ave) in the villages of Lily Lake and Campton Hills, Kane County. | — | Executed | Builders Paving, LLC $1,178,000 · | ||
| Apr 29, 2022 | 61G32 | KaneDistrict 1 | Replace the superstructure and the abutments of the existing bridge carrying Coombs Road over the DMandE Railroad in Elgin Township, Kane County. | — | Executed | Lorig Construction Company $2,279,677 · | ||
| Apr 29, 2022 | 61H60 | KaneDistrict 1 | Pavement reclamation, resurfacing and aggregate should improvements on Anderson Road from IL 64 to IL 38 in Compton Township. | — | Executed | Builders Paving, LLC $985,000 · | ||
| Apr 29, 2022 | 62R46 | KaneMcHenryDistrict 1 | Cleaning(sweeping) various arterial highways in District One throughout Kane and McHenry counties (299.5-Mile) The improvement consists of cleaning(sweeping) various arterial highways in District One throughout Kane and McHenry counties. | — | Executed | Elgin Sweeping Services, Inc. $1,249,890 · | ||
| Jul 15, 2022 | 62N57 | KaneDistrict 1 | (9.07-Mile) Crack and Joint Sealing, Kane County. | — | Executed | Freehill Asphalt, Inc. $322,192 · | ||
| Aug 5, 2022 | 62N54 | KaneDistrict 1 | (1.710-Mile) This is a SMART resurfacing project consisting of pavement patching, hot-mix asphalt surface removal, resurfacing with surface course, detector loop replacement, curb and gutter replacement in the city of Elgin and Village of East Dundee. | — | Executed | Plote Construction, Inc. $1,051,036 · | ||
| Sep 23, 2022 | 46605 | KaneDistrict 1 | Removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and p This work shall consist of removing reflectors, placing new reflectors, removing damaged raised reflective pavement marker castings and placing new raised pavement marker castings within the limits shown. | — | Executed | Precision Pavement Markings Inc. $502,490 · | ||
| Sep 23, 2022 | 61H97 | KaneDistrict 1 | Traffic Signal installation and reconstruction of the crosswalk at Montgomery Road and Virgil Gilman Trail in Montgomery. | — | Executed | Geneva Construction Company $187,124 · |
1–16 of 16
Lettings: IDOT Transportation Bulletin (Notice of Letting and Contract Detail pages). Planned projects: IDOT Multi-Year Highway Improvement Program (roadway, structure and spot layers on the IDOT open data hub), listed by program year, not let date. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.