20-06000-02-FP
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Builders Paving, LLC Low bidder | $985,000 | ||
| 2 | J. A. Johnson Paving Company | $1,032,243 | +4.8% | |
| 3 | Geneva Construction Company | $1,035,266 | +5.1% | |
| 4 | Curran Contracting Company | $1,036,224 | +5.2% | |
| 5 | Plote Construction, Inc. | $1,061,000 | +7.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Builders Paving… | #2 J. A. Johnson P… | #3 Geneva Construc… | #4 Curran Contract… | #5 Plote Construct… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | LR400899 | FD RECLAMATION 10.0 | 14,555 | SQ YD | $5.25 | $4.50 | $4.30 | $6.45 | $5.00 | |
| 2 | XX006520 | AGGREGATE DRIVEWAY 6" | 40 | SQ YD | $60.00 | $10.00 | $23.00 | $44.00 | $36.00 | |
| 3 | XX009524 | AGG BASE REM & REP 12 | 284 | SQ YD | $30.00 | $5.00 | $30.00 | $25.00 | $25.00 | |
| 4 | X2130010 | EXPLOR TRENCH SPL | 50 | FOOT | $52.00 | $52.00 | $52.00 | $14.15 | $52.00 | |
| 5 | X4021000 | TEMP ACCESS- PRIV ENT | 5 | EACH | $125.00 | $1.00 | $250.00 | $250.00 | $30.00 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,500.00 | $78,000.00 | $9,715.00 | $12,500.00 | $26,234.22 | |
| 7 | Z0004530 | HMA DRIVEWAY PAVT 8 | 75 | SQ YD | $50.00 | $60.00 | $75.00 | $85.00 | $85.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,000.00 | $5,000.00 | $5,495.00 | $7,500.00 | $5,495.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 318 | SQ FT | $20.00 | $20.00 | $11.50 | $11.50 | $11.50 | |
| 10 | Z0073510 | TEMP TR SIGNAL TIMING | 2 | EACH | $600.00 | $600.00 | $1,000.00 | $600.00 | $600.00 | |
| 11 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 13 | 20200600 | EXC & GR EX SHOULDER | 245 | UNIT | $18.00 | $26.00 | $40.00 | $135.00 | $20.00 | |
| 14 | 20201200 | REM & DISP UNS MATL | 500 | CU YD | $10.00 | $5.00 | $46.00 | $37.50 | $10.00 | |
| 15 | 20400800 | FURNISHED EXCAVATION | 10 | CU YD | $65.00 | $1.00 | $45.00 | $125.00 | $90.00 | |
| 16 | 20800150 | TRENCH BACKFILL | 7 | CU YD | $23.00 | $23.00 | $23.00 | $92.50 | $23.00 | |
| 17 | 21101615 | TOPSOIL F & P 4 | 121 | SQ YD | $10.00 | $7.00 | $15.00 | $25.00 | $7.00 | |
| 18 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $4,500.00 | $2,100.00 | $10,000.00 | $5,000.00 | $2,100.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 20 | POUND | $5.00 | $5.00 | $1.00 | $3.00 | $5.00 | |
| 20 | 25000600 | POTASSIUM FERT NUTR | 20 | POUND | $5.00 | $5.00 | $1.00 | $3.00 | $5.00 | |
| 21 | 25100630 | EROSION CONTR BLANKET | 121 | SQ YD | $5.00 | $4.00 | $17.75 | $5.00 | $4.00 | |
| 22 | 28000250 | TEMP EROS CONTR SEED | 20 | POUND | $10.00 | $3.75 | $0.1000 | $1.00 | $3.75 | |
| 23 | 28000305 | TEMP DITCH CHECKS | 400 | FOOT | $8.00 | $9.00 | $1.00 | $12.00 | $9.00 | |
| 24 | 28000400 | PERIMETER EROS BAR | 62 | FOOT | $6.00 | $6.00 | $5.00 | $20.00 | $6.00 | |
| 25 | 35101400 | AGG BASE CSE B | 830 | TON | $20.00 | $7.75 | $21.00 | $24.00 | $14.00 | |
| 26 | 35200500 | CEMENT | 9,750 | 100 WT | $7.90 | $7.90 | $7.90 | $8.31 | $7.90 | |
| 27 | 40600275 | BIT MATLS PR CT | 13,775 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 28 | 40600290 | BIT MATLS TACK CT | 6,806 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 29 | 40600370 | LONG JOINT SEALANT | 12,205 | FOOT | $2.75 | $2.04 | $2.15 | $2.20 | $2.04 | |
| 30 | 40600982 | HMA SURF REM BUTT JT | 75 | SQ YD | $30.00 | $1.00 | $14.00 | $18.00 | $17.00 | |
| 31 | 40603080 | HMA BC IL-19.0 N50 | 3,930 | TON | $68.00 | $75.00 | $80.00 | $66.50 | $79.00 | |
| 32 | 40604060 | HMA SC IL-9.5 D N50 | 2,675 | TON | $75.00 | $81.00 | $90.00 | $68.50 | $85.00 | |
| 33 | 44000163 | HMA SURF REM 3 1/2 | 30,249 | SQ YD | $4.00 | $3.20 | $2.75 | $3.45 | $4.00 | |
| 34 | 44000200 | DRIVE PAVEMENT REM | 75 | SQ YD | $17.00 | $10.00 | $15.00 | $15.00 | $14.60 | |
| 35 | 44201737 | CL D PATCH T1 8 | 75 | SQ YD | $100.00 | $40.00 | $65.00 | $100.00 | $85.00 | |
| 36 | 44201741 | CL D PATCH T2 8 | 85 | SQ YD | $85.00 | $60.00 | $65.00 | $98.00 | $81.00 | |
| 37 | 44201745 | CL D PATCH T3 8 | 105 | SQ YD | $75.00 | $60.00 | $58.00 | $95.00 | $81.00 | |
| 38 | 44201747 | CL D PATCH T4 8 | 125 | SQ YD | $70.00 | $60.00 | $58.00 | $92.00 | $81.00 | |
| 39 | 50105220 | PIPE CULVERT REMOV | 42 | FOOT | $10.00 | $10.00 | $10.00 | $105.00 | $10.00 | |
| 40 | 54262712 | METAL FL END SEC 12" | 2 | EACH | $685.00 | $985.00 | $685.00 | $380.00 | $685.00 | |
| 41 | 550B0050 | STORM SEW CL B 1 12 | 47 | FOOT | $165.00 | $165.00 | $165.00 | $118.00 | $165.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $49,705.13 | $61,963.39 | $61,000.00 | $61,750.00 | $63,000.00 | |
| 43 | 70300100 | SHORT TERM PAVT MKING | 8,920 | FOOT | $0.5000 | $0.0100 | $0.0100 | $0.3000 | $0.5000 | |
| 44 | 70300150 | SHRT TRM PAVT MK REM | 3,271 | SQ FT | $0.5000 | $0.0100 | $0.0100 | $1.00 | $0.0100 | |
| 45 | 78000200 | THPL PVT MK LINE 4 | 48,456 | FOOT | $0.5100 | $0.6600 | $0.5800 | $0.6600 | $0.5100 | |
| 46 | 78000600 | THPL PVT MK LINE 12 | 12 | FOOT | $2.25 | $5.99 | $2.00 | $6.00 | $2.25 | |
| 47 | 78000650 | THPL PVT MK LINE 24 | 85 | FOOT | $4.50 | $5.00 | $5.00 | $5.00 | $4.50 |