2021-037-RS
- Let date
- Friday, August 5, 2022
- Contract
- 62N54 · job page
- District
- District 1
- County
- Kane
- Highway
- Limits
- (1.710-Mile) This is a SMART resurfacing project consisting of pavement patching, hot-mix asphalt surface removal, resurfacing with surface course, detector loop replacement, curb and gutter replacement in the city of Elgin and Village of East Dundee.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $1,051,036 | ||
| 2 | J. A. Johnson Paving Company | $1,095,700 | +4.2% | |
| 3 | Arrow Road Construction Co. | $1,107,070 | +5.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 J. A. Johnson P… | #3 Arrow Road Cons… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0100018 | TREE REMOV UNDER 6U | 10 | UNIT | $30.00 | $25.00 | $30.00 | |
| 2 | X0327120 | WEED CTRL NTV LSCP EN | 0.6 | ACRE | $4,000.00 | $6,500.00 | $4,000.00 | |
| 3 | X2010100 | TREE LIMB REM 4-10 | 20 | EACH | $150.00 | $100.00 | $150.00 | |
| 4 | X2010200 | TREE LIMB REM OVER 10 | 10 | EACH | $200.00 | $200.00 | $200.00 | |
| 5 | X2010350 | TREE REMOV ACRES SPL | 0.5 | ACRE | $16,640.00 | $30,000.00 | $16,640.00 | |
| 6 | X2100002 | PRUN SAFETY/EQUIP CLR | 25 | UNIT | $200.00 | $500.00 | $200.00 | |
| 7 | X4400501 | COMB C&G REMOV REPL < = 10FT | 50 | FOOT | $120.00 | $100.00 | $120.00 | |
| 8 | X5537800 | SS CLEANED 12 | 200 | FOOT | $5.00 | $5.00 | $4.00 | |
| 9 | X5537900 | SS CLEANED 15 | 200 | FOOT | $5.00 | $5.00 | $5.00 | |
| 10 | X6030310 | FR & LIDS ADJUST SPL | 5 | EACH | $1,150.00 | $2,650.00 | $1,177.00 | |
| 11 | X6700407 | ENGR FLD OFF A D1 | 12 | CAL MO | $3,000.00 | $2,500.00 | $3,500.00 | |
| 12 | Z0004562 | COMB C C&G REM & REPL | 789 | FOOT | $75.00 | $90.00 | $100.00 | |
| 13 | Z0018500 | DRAINAGE STR CLEANED | 40 | EACH | $350.00 | $350.00 | $300.00 | |
| 14 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $12.00 | $25.00 | $20.00 | |
| 15 | Z0064800 | SELECTIVE CLEARING | 8.5 | UNIT | $465.00 | $700.00 | $465.00 | |
| 16 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 17 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 18 | 20100110 | TREE REMOV 6-15 | 30 | UNIT | $40.00 | $25.00 | $40.00 | |
| 19 | 20100210 | TREE REMOV OVER 15 | 35 | UNIT | $50.00 | $55.00 | $50.00 | |
| 20 | 21101615 | TOPSOIL F & P 4 | 475 | SQ YD | $8.20 | $5.23 | $8.20 | |
| 21 | 25000210 | SEEDING CL 2A | 0.6 | ACRE | $3,600.00 | $3,200.00 | $3,600.00 | |
| 22 | 25000400 | NITROGEN FERT NUTR | 54 | POUND | $3.00 | $3.00 | $3.00 | |
| 23 | 25000500 | PHOSPHORUS FERT NUTR | 54 | POUND | $3.00 | $3.00 | $3.00 | |
| 24 | 25000600 | POTASSIUM FERT NUTR | 54 | POUND | $3.00 | $3.00 | $3.00 | |
| 25 | 25100127 | MULCH METHOD 3A | 0.6 | ACRE | $6,500.00 | $6,500.00 | $6,500.00 | |
| 26 | 25200110 | SODDING SALT TOLERANT | 475 | SQ YD | $18.00 | $15.00 | $18.00 | |
| 27 | 25200200 | SUPPLE WATERING | 1 | UNIT | $50.00 | $0.0100 | $50.00 | |
| 28 | 35501316 | HMA BASE CSE 8 | 14 | SQ YD | $200.00 | $205.00 | $410.00 | |
| 29 | 40600290 | BIT MATLS TACK CT | 24,750 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 30 | 40600370 | LONG JOINT SEALANT | 21,000 | FOOT | $2.40 | $2.17 | $2.40 | |
| 31 | 40600400 | MIX CR JTS FLANGEWYS | 83 | TON | $75.00 | $250.00 | $125.00 | |
| 32 | 40600982 | HMA SURF REM BUTT JT | 190 | SQ YD | $10.00 | $1.00 | $5.00 | |
| 33 | 40604060 | HMA SC IL-9.5 D N50 | 1.6 | TON | $600.00 | $445.00 | $690.00 | |
| 34 | 40604062 | HMA SC IL-9.5 D N70 | 4,620 | TON | $89.00 | $80.00 | $86.25 | |
| 35 | 42001300 | PROTECTIVE COAT | 265 | SQ YD | $0.0100 | $5.00 | $0.0100 | |
| 36 | 42300400 | PCC DRIVEWAY PAVT 8 | 6 | SQ YD | $350.00 | $100.00 | $350.00 | |
| 37 | 44000155 | HMA SURF REM 1 1/2 | 54,960 | SQ YD | $3.00 | $2.60 | $3.13 | |
| 38 | 44000200 | DRIVE PAVEMENT REM | 20 | SQ YD | $120.00 | $100.00 | $120.00 | |
| 39 | 44003100 | MEDIAN REMOVAL | 550 | SQ FT | $15.00 | $18.00 | $15.00 | |
| 40 | 44201839 | CL D PATCH T2 16 | 225 | SQ YD | $25.00 | $135.00 | $82.00 | |
| 41 | 44201843 | CL D PATCH T3 16 | 140 | SQ YD | $25.00 | $135.00 | $82.00 | |
| 42 | 60250200 | CB ADJUST | 3 | EACH | $550.00 | $550.00 | $515.00 | |
| 43 | 60252800 | CB RECONST | 1 | EACH | $1,100.00 | $2,150.00 | $943.00 | |
| 44 | 60255500 | MAN ADJUST | 4 | EACH | $650.00 | $650.00 | $648.00 | |
| 45 | 60257900 | MAN RECONST | 1 | EACH | $1,200.00 | $2,350.00 | $943.00 | |
| 46 | 60260100 | INLETS ADJUST | 10 | EACH | $550.00 | $550.00 | $536.00 | |
| 47 | 60300305 | FR & LIDS ADJUST | 3 | EACH | $685.00 | $685.00 | $833.00 | |
| 48 | 60618300 | CONC MEDIAN SURF 4 | 550 | SQ FT | $15.00 | $18.00 | $15.00 | |
| 49 | 67100100 | MOBILIZATION | 1 | L SUM | $63,000.00 | $59,989.01 | $56,500.41 | |
| 50 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $70,000.00 | $92,800.00 | $71,000.00 | |
| 51 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $100.00 | $1.00 | |
| 52 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $100.00 | $8,500.00 | |
| 53 | 70300100 | SHORT TERM PAVT MKING | 42,325 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 54 | 70300150 | SHRT TRM PAVT MK REM | 14,108 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 55 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 402.6 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 56 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 23,233 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 57 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 2,010 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 58 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 390 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 59 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 230 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 60 | 70306120 | TEMP PVT MK L4 T3 TAPE | 10,582 | FOOT | $0.0100 | $1.00 | $0.5000 | |
| 61 | 78000100 | THPL PVT MK LTR & SYM | 402.6 | SQ FT | $5.00 | $5.00 | $5.75 | |
| 62 | 78000200 | THPL PVT MK LINE 4 | 23,233 | FOOT | $0.6500 | $0.6800 | $0.6500 | |
| 63 | 78000400 | THPL PVT MK LINE 6 | 2,010 | FOOT | $1.20 | $1.20 | $1.15 | |
| 64 | 78000600 | THPL PVT MK LINE 12 | 390 | FOOT | $2.50 | $2.50 | $2.50 | |
| 65 | 78000650 | THPL PVT MK LINE 24 | 230 | FOOT | $5.00 | $5.00 | $5.75 | |
| 66 | 78100100 | RAISED REFL PAVT MKR | 715 | EACH | $32.00 | $34.90 | $36.30 | |
| 67 | 78300200 | RAISED REF PVT MK REM | 700 | EACH | $8.00 | $1.00 | $5.00 | |
| 68 | 78300202 | PAVMT MRKG REM WTR BL | 13,430 | SQ FT | $0.0100 | $0.0100 | $0.1000 | |
| 69 | 88600600 | DET LOOP REPL | 355 | FOOT | $15.79 | $18.00 | $15.55 |