168Let jobs
$527,229,584Total low bids
$634,936,827Total estimates
-17.0%Low bids vs estimates
Nov 2025 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Nov 25, 2025 | 6494-22-001SUP - A00218557 | Bee Corpus Christi |
6494-22-001 Picnic MaintenanceUS0181 · State Use Project | $71,964 | — | 0 | ||
| Nov 24, 2025 | 6494-03-001MMC - A00218472 | Hidalgo Pharr |
6494-03-001 Flexible Base District WideSH0495 · Material Maintenance Project - Sealed | $340,000 | $469,239 | VULCAN CONSTRUCTION MATERIALS, LLC | +38.0% | 3 |
| Nov 24, 2025 | 6493-61-001RMC - A00218353 | Moore Amarillo |
Guardrail Dumas AE FY 26US0087 · Routine Maintenance Project - Sealed | $396,075 | $376,352 | E.V.G. ENTERPRISE | -5.0% | 2 |
| Nov 24, 2025 | 6470-78-001MMC - A00211265 | Hidalgo Pharr |
Asphalt Patching Material (FY 26)IH0002 · Material Maintenance Project - Sealed | $371,000 | $370,670 | WALLER COUNTY ASPHALT INC. | -0.1% | 1 |
| Nov 24, 2025 | 6494-00-001MMC - A00218469 | Ector Odessa |
6494-00-001 ASPPMSL0338 · Material Maintenance Project | $160,000 | $161,200 | TOUCHSTONE RESOURCES, LLC | +0.8% | 1 |
| Nov 24, 2025 | 6494-05-001MMC - A00218481 | Nueces Corpus Christi |
6494-05-001 Brine CCAO-AAOSH0358 · Material Maintenance Project | $118,080 | $123,328 | TOUCHSTONE RESOURCES, LLC | +4.4% | 1 |
| Nov 24, 2025 | 6493-41-001BPM - A00218325 | Walker Bryan |
FY26 - Walker IH45 Bridge Repair - 11IH0045 · Bridge Preventative Maintenance | $210,237 | $114,511 | BK FIELD OPERATIONS LLC | -45.5% | 8 |
| Nov 24, 2025 | 6494-04-001MMC - A00218480 | Karnes Corpus Christi |
6494-04-001 Brine KAO-SAOUS0181 · Material Maintenance Project | $71,280 | $79,200 | TOUCHSTONE RESOURCES, LLC | +11.1% | 1 |
| Nov 24, 2025 | 6493-47-001SUP - A00218331 | Harris Houston |
FY26 Landscape Mesa DrIH0610 · State Use Project | $16,080 | — | 0 | ||
| Nov 23, 2025 | 6492-31-001SUP - A00218063 | Hunt Paris |
Janitorial - Hunt FY2025IH0030 · State Use Project | $33,126 | — | 0 | ||
| Nov 20, 2025 | 6491-99-001MMC - A00217983 | Shelby Lufkin |
2025-11 Shelby HMASH0007 · Material Maintenance Project | $775,750 | $724,255 | TEXAS MATERIALS GROUP, INC. | -6.6% | 1 |
| Nov 20, 2025 | 6491-97-001MMC - A00217981 | San Augustine Lufkin |
2025-11 San Augustine HMAUS0096 · Material Maintenance Project | $721,500 | $695,641 | TEXAS MATERIALS GROUP, INC. | -3.6% | 1 |
| Nov 20, 2025 | 6492-01-001MMC - A00217985 | Houston Lufkin |
2025-11 Houston HMASL0304 · Material Maintenance Project | $752,900 | $667,785 | TEXAS MATERIALS GROUP, INC. | -11.3% | 2 |
| Nov 20, 2025 | 6492-00-001MMC - A00217984 | Polk Lufkin |
2025-11 Polk HMAUS0059 · Material Maintenance Project | $626,250 | $583,920 | TEXAS MATERIALS GROUP, INC. | -6.8% | 1 |
| Nov 20, 2025 | 6486-28-001BPM - A00216245 | Tom Green San Angelo |
BPM - FY 2026SH0208 · Bridge Preventative Maintenance - Sealed | $750,055 | $505,934 | BK FIELD OPERATIONS LLC | -32.5% | 11 |
| Nov 20, 2025 | 6491-56-001RMC - A00217878 | Lamar Paris |
Illumination Maintenance-FY26US0082 · Routine Maintenance Project - Sealed | $497,445 | $488,025 | VACA UNDERGROUND UTILITIES INC | -1.9% | 3 |
| Nov 20, 2025 | 6492-02-001MMC - A00217986 | Trinity Lufkin |
2025-11 Trinity HYD CEMUS0287 · Material Maintenance Project | $263,672 | $243,936 | AKA-MATERIALS | -7.5% | 2 |
| Nov 20, 2025 | 6491-30-001RMC - A00217804 | Hopkins Paris |
Concrete transition work-Hopkins Co.SH0019 · Routine Maintenance Project - Sealed | $246,623 | $190,653 | SCOUT 5 CONSTRUCTION LLC | -22.7% | 6 |
| Nov 20, 2025 | 6490-56-001RMC - A00217651 | Lamar Paris |
On Call Ditch and Culvert-PAO FY26US0082 · Routine Maintenance Project - Sealed | $217,250 | $167,950 | TEXAS DRAINAGE INC. | -22.7% | 3 |
| Nov 20, 2025 | 6477-68-001RMC - A00213098 | Taylor Abilene |
Callout RPMIH0020 · Routine Maintenance Project | $291,000 | $157,200 | TRP INFRASTRUCTURE SERVICES, LLC | -46.0% | 3 |
| Nov 19, 2025 | 6487-91-001RMC - A00216897 | Tarrant Fort Worth |
FY26 Herbicide North and South TarrantIH0030 · Routine Maintenance Project - Sealed | $916,517 | $1,145,406 | OPTERRA SOLUTIONS, INC. | +25.0% | 4 |
| Nov 19, 2025 | 6489-89-001MMC - A00217544 | Johnson Fort Worth |
FY2026 - Hot Mix - JohnsonIH0035W · Material Maintenance Project | $942,250 | $910,250 | NORTHEASTERN PAVERS, LLC | -3.4% | 2 |
| Nov 19, 2025 | 6488-52-001RMC - A00217130 | Parker Fort Worth |
FY26 Callout ParkerIH0020 · Routine Maintenance Project - Sealed | $841,871 | $570,733 | THE CONFIDENCE GROUP, INC | -32.2% | 3 |
| Nov 19, 2025 | 6487-21-001RMC - A00216531 | Wise Fort Worth |
FY26 Tree Brush Removal Jack WiseSH0114 · Routine Maintenance Project - Sealed | $544,810 | $495,494 | UMD Construction | -9.1% | 6 |
| Nov 19, 2025 | 6493-30-001MMC - A00218298 | Runnels San Angelo |
AGGREGATE-TY B GR 4US0067 · Material Maintenance Project | $223,000 | $211,194 | MARTIN MARIETTA MATERIALS, INC. | -5.3% | 3 |
| Nov 19, 2025 | 6489-05-001RMC - A00217264 | Erath Fort Worth |
FY26 Tree Brush Removal ErathUS0377 · Routine Maintenance Project - Sealed | $384,767 | $203,290 | ALLIES LAND CLEARING | -47.2% | 11 |
| Nov 19, 2025 | 6493-29-001MMC - A00218297 | Concho San Angelo |
SAND-SOUTHUS0083 · Material Maintenance Project | $115,596 | $116,000 | TOUCHSTONE RESOURCES, LLC | +0.3% | 1 |
| Nov 19, 2025 | 6493-28-001MMC - A00218296 | Runnels San Angelo |
SAND-NORTHUS0067 · Material Maintenance Project | $131,150 | $111,000 | TOUCHSTONE RESOURCES, LLC | -15.4% | 1 |
| Nov 19, 2025 | 6493-14-001RMC - A00218271 | De Witt Yoakum |
Janitorial - Yoakum ComplexBU0077Q · Routine Maintenance Project | $77,400 | $64,500 | RWCS JANITORIAL LLC | -16.7% | 2 |
| Nov 18, 2025 | 6492-47-001RMC - A00218136 | Kinney Laredo |
Mowing of highways ROWUS0277 · Routine Maintenance Project - Sealed | $295,530 | $241,954 | ABESCAPE GROUP LLC | -18.1% | 2 |
| Nov 18, 2025 | 6487-51-001MMC - A00216675 | Taylor Abilene |
Traffic Paint & Beads ABLUS0083 · Material Maintenance Project | $207,240 | $190,440 | ENNIS-FLINT, INC. | -8.1% | 1 |
| Nov 18, 2025 | 6493-10-001SUP - A00218263 | Travis Austin |
Travis East Maintenance Litter FY26US0290 · State Use Project | $296,807 | — | 0 | ||
| Nov 17, 2025 | 6491-61-001SUP - A00217901 | Collin Dallas |
Collin Janitorial Grounds FY26SH0005 · State Use Project | $85,176 | — | 0 | ||
| Nov 17, 2025 | 6494-14-001SUP - A00218534 | Collin Dallas |
Collin Litter 07 1125SH0005 · State Use Project | $260,966 | — | 0 | ||
| Nov 13, 2025 | 6493-04-001RMC - A00218252 | Live Oak Corpus Christi |
6493-04-001 Mowing (Live Oak)IH0037 · Routine Maintenance Project - Sealed | $997,875 | $832,767 | CROSS PLUS CONSTRUCTION, LLC | -16.5% | 3 |
| Nov 13, 2025 | 6492-60-001RMC - A00218176 | San Patricio Corpus Christi |
6492-60-001 StripingUS0181 · Routine Maintenance Project - Sealed | $907,685 | $687,912 | PAVEMENT MARKINGS INC. | -24.2% | 4 |
| Nov 13, 2025 | 6487-07-001MMC - A00216511 | Hill Waco |
FY26 LRA DistrictwideUS0077 · Material Maintenance Project | $557,832 | $576,400 | VULCAN CONSTRUCTION MATERIALS, LLC | +3.3% | 2 |
| Nov 13, 2025 | 6492-75-001RMC - A00218212 | Duval Laredo |
Right of Way Mowing Duval CountySH0016 · Routine Maintenance Project - Sealed | $478,179 | $569,033 | R&M INCORPORATED | +19.0% | 2 |
| Nov 13, 2025 | 6492-99-001RMC - A00218247 | Val Verde Laredo |
Mowing of highways ROW - Val VerdeUS0277 · Routine Maintenance Project - Sealed | $558,680 | $528,285 | ABESCAPE GROUP LLC | -5.4% | 3 |
| Nov 13, 2025 | 6485-60-001RMC - A00216032 | McLennan Waco |
Mowing - McLennan FY26US0084 · Routine Maintenance Project | $628,987 | $476,955 | T&L CLEANING SERVICES LLC | -24.2% | 6 |
| Nov 13, 2025 | 6493-05-001RMC - A00218253 | Ector Odessa |
6493-05-001 Street SweepingIH0020 · Routine Maintenance Project | $445,820 | $393,801 | J-MEN CONCRETE CONSTRUCTION | -11.7% | 2 |
| Nov 13, 2025 | 6485-61-001RMC - A00216033 | Hill Waco |
Mowing - Hill FY26FM0308 · Routine Maintenance Project | $410,807 | $389,974 | CEN-TEX IRRIGATION SYSTEMS, INC. | -5.1% | 4 |
| Nov 13, 2025 | 6493-46-001MMC - A00218330 | Jim Wells Corpus Christi |
6493-46-001 Flex Base Kingsville MaintUS0281 · Material Maintenance Project | $432,000 | $384,000 | TOUCHSTONE RESOURCES, LLC | -11.1% | 6 |
| Nov 13, 2025 | 6485-62-001RMC - A00216034 | Falls Waco |
Mowing - Falls FY26US0077 · Routine Maintenance Project | $477,943 | $314,909 | P-VILLE, INCORPORATED | -34.1% | 6 |
| Nov 13, 2025 | 6491-71-001MMC - A00217933 | Brazos Bryan |
FY26 Bryan AO RipRap - 11SH0006 · Material Maintenance Project | $268,500 | $264,500 | TOUCHSTONE RESOURCES, LLC | -1.5% | 5 |
| Nov 13, 2025 | 6485-63-001RMC - A00216035 | Limestone Waco |
Mowing - Limestone FY26FM0339 · Routine Maintenance Project | $301,358 | $262,974 | P-VILLE, INCORPORATED | -12.7% | 5 |
| Nov 13, 2025 | 6493-35-001MMC - A00218311 | Ector Odessa |
6493-35-001 Paint and BeadsBI0020E · Material Maintenance Project | $241,200 | $228,600 | ENNIS-FLINT, INC. | -5.2% | 1 |
| Nov 13, 2025 | 6493-45-001MMC - A00218329 | Jim Wells Corpus Christi |
6493-45-001 Flex Base Alice MaintUS0281 · Material Maintenance Project | $240,000 | $199,750 | ANDERSON COLUMBIA CO., INC. | -16.8% | 6 |
| Nov 13, 2025 | 6491-69-001MMC - A00217930 | Washington Bryan |
FY26 Brenham AO Flexbase - 11SH0036 · Material Maintenance Project | $111,000 | $100,000 | TOUCHSTONE RESOURCES, LLC | -9.9% | 7 |
| Nov 13, 2025 | 6492-48-001RMC - A00218137 | Freestone Bryan |
FY26 - Huntsville AO Sweeping -11US0084 · Routine Maintenance Project | $120,942 | $99,000 | PINNACLE SERVICE | -18.1% | 2 |
| Nov 13, 2025 | 6490-57-001RMC - A00217652 | Nueces Corpus Christi |
6490-57-001 RMC Tree TrimmingSH0286 · Routine Maintenance Project - Sealed | $251,374 | $70,810 | S FOWLER SERVICES LLC | -71.8% | 6 |
| Nov 13, 2025 | 6493-82-001SUP - A00218404 | Washington Bryan |
FY26 Washington Litter Removal - 12SH0036 · State Use Project | $887,514 | — | 0 | ||
| Nov 13, 2025 | 6493-83-001SUP - A00218405 | Walker Bryan |
FY26 Walker Litter Removal - 12IH0045 · State Use Project | $539,428 | — | 0 | ||
| Nov 13, 2025 | 6493-85-001SUP - A00218407 | Brazos Bryan |
FY26 Brazos Litter Removal - 12SH0006 · State Use Project | $575,720 | — | 0 | ||
| Nov 12, 2025 | 6489-40-001RMC - A00217389 | El Paso El Paso |
Traffic Control Services WAOIH0010 · Routine Maintenance Project | $906,200 | $667,850 | BARRICADES UNLIMITED | -26.3% | 2 |
| Nov 12, 2025 | 6488-06-001MMC - A00217006 | Bell Waco |
HOT-MIX COLD-LAID-MATERIAL ONLYUS0190 · Material Maintenance Project | $636,928 | $642,838 | TEXAS MATERIALS GROUP, INC. | +0.9% | 3 |
| Nov 12, 2025 | 6476-10-001RMC - A00212747 | Harris Houston |
Traffic Control 2025US0290 · Routine Maintenance Project - Sealed | $775,125 | $634,000 | ROSS SA ENTERPRISE LLC | -18.2% | 6 |
| Nov 12, 2025 | 6488-01-001RMC - A00216981 | Kaufman Dallas |
Sweeping & Debris 06 11.25IH0020 · Routine Maintenance Project - Sealed | $679,865 | $596,459 | SWEEPING CORPORATION OF AMERICA, LLC | -12.3% | 1 |
| Nov 12, 2025 | 6484-50-001RMC - A00215474 | Travis Austin |
CTTS Small Signs Set 3 FY 25SH0130 · Routine Maintenance Project - Sealed | $822,270 | $570,915 | RHINO EQUITY, LLC | -30.6% | 12 |
| Nov 12, 2025 | 6483-31-001RMC - A00215076 | Brazoria Houston |
FY26 Brazoria CCA RepairSH0288 · Routine Maintenance Project - Sealed | $651,149 | $520,525 | ROY JORGENSEN ASSOCIATES, INC. | -20.1% | 6 |
| Nov 12, 2025 | 6489-23-001RMC - A00217331 | Ellis Dallas |
Repair/Replace Concrete Barrier 09 1125IH0035E · Routine Maintenance Project - Sealed | $552,300 | $408,528 | BK FIELD OPERATIONS LLC | -26.0% | 7 |
| Nov 12, 2025 | 6488-09-001RMC - A00217012 | Bell Waco |
MOWING HIGHWAY RIGHT OF WAY- BELL COUNTYUS0190 · Routine Maintenance Project | $504,099 | $402,987 | T&L CLEANING SERVICES LLC | -20.1% | 5 |
| Nov 12, 2025 | 6485-33-001RMC - A00215931 | Denton Dallas |
Mowing 04 2026IH0035 · Routine Maintenance Project - Sealed | $496,848 | $395,027 | ORTEGA'S LAWN AND LANDSCAPING, LLC | -20.5% | 8 |
| Nov 12, 2025 | 6488-00-001RMC - A00216980 | Rockwall Dallas |
Rockwall Sweeping & DebrisIH0030 · Routine Maintenance Project - Sealed | $436,782 | $391,981 | SWEEPING CORPORATION OF AMERICA, LLC | -10.3% | 1 |
| Nov 12, 2025 | 6484-90-001RMC - A00215659 | Jasper Beaumont |
FY 26 Jasper Tree and Brush RemovalUS0096 · Routine Maintenance Project | $508,800 | $363,380 | AUSTIN BARRICADE COMPANY, L.L.C. | -28.6% | 3 |
| Nov 12, 2025 | 6487-32-001RMC - A00216583 | Collin Dallas |
On Call Traffic Control Services 07 1125US0075 · Routine Maintenance Project - Sealed | $313,650 | $352,230 | SUPERIOR TRAFFIC CONTROL, LLC | +12.3% | 2 |
| Nov 12, 2025 | 6488-10-001RMC - A00217013 | Coryell Waco |
MOWING HIGHWAY RIGHT OF WAY-CORYELLUS0084 · Routine Maintenance Project | $388,728 | $303,192 | T&L CLEANING SERVICES LLC | -22.0% | 4 |
| Nov 12, 2025 | 6484-83-001RMC - A00215630 | Jefferson Beaumont |
FY 26 Beaumont Tree and Brush RemovalUS0069 · Routine Maintenance Project | $551,050 | $300,165 | AUSTIN BARRICADE COMPANY, L.L.C. | -45.5% | 3 |
| Nov 12, 2025 | 6485-15-001RMC - A00215832 | Montgomery Houston |
Asphalt Repair RMC 6485-15-001IH0045 · Routine Maintenance Project - Sealed | $299,450 | $293,700 | FORDE CONSTRUCTION COMPANY, INC. | -1.9% | 2 |
| Nov 12, 2025 | 6488-16-001RMC - A00217050 | Collin Dallas |
MBGF 07 11.25US0075 · Routine Maintenance Project - Sealed | $446,954 | $281,455 | ROSS SA ENTERPRISE LLC | -37.0% | 4 |
| Nov 12, 2025 | 6488-12-001RMC - A00217016 | Bosque Waco |
MOWING HIGHWAY ROW BOSQUE COUNTYSH0006 · Routine Maintenance Project | $337,482 | $271,100 | T&L CLEANING SERVICES LLC | -19.7% | 4 |
| Nov 12, 2025 | 6492-34-001RMC - A00218078 | Walker Bryan |
FY26 - Walker Mowing -11FM1374 · Routine Maintenance Project | $277,699 | $252,861 | ROY LEE WALKER | -8.9% | 4 |
| Nov 12, 2025 | 6489-87-001RMC - A00217541 | Dallas Dallas |
Traffic Control 063 11.25IH0035E · Routine Maintenance Project - Sealed | $295,625 | $249,375 | SUPERIOR TRAFFIC CONTROL, LLC | -15.6% | 2 |
| Nov 12, 2025 | 6488-59-001MMC - A00217144 | Harris Houston |
FY 26, Winter Weather MaterialsIH0045 · Material Maintenance Project | $254,450 | $245,670 | TOUCHSTONE RESOURCES, LLC | -3.5% | 2 |
| Nov 12, 2025 | 6489-24-001RMC - A00217332 | Ellis Dallas |
Mowing Highway Right of Way 09 0925SH0034 · Routine Maintenance Project - Sealed | $263,908 | $230,460 | CEN-TEX IRRIGATION SYSTEMS, INC. | -12.7% | 5 |
| Nov 12, 2025 | 6489-31-001RMC - A00217350 | Ellis Dallas |
Tree Trimming and Brush Removal 09 1125IH0045 · Routine Maintenance Project - Sealed | $341,770 | $222,280 | TEXWAY WASTEWATER SERVICES, LLC | -35.0% | 9 |
| Nov 12, 2025 | 6488-42-001BPM - A00217111 | Collin Dallas |
BPM SH 78 Erosion Control 07 11.25SH0078 · Bridge Preventative Maintenance - Sealed | $221,418 | $216,855 | AAD CONTRACTING INC. | -2.1% | 6 |
| Nov 12, 2025 | 6488-11-001RMC - A00217014 | Hamilton Waco |
MOWING HIGHWAY ROW - HAMILTON CPUNTYFM0219 · Routine Maintenance Project | $231,384 | $196,226 | T&L CLEANING SERVICES LLC | -15.2% | 6 |
| Nov 12, 2025 | 6485-47-001TMC - A00215967 | Dallas Dallas |
Battery Back Up System APC 2025US0080 · Material Only Traffic | $200,550 | $194,334 | CONSOLIDATED TRAFFIC CONTROLS, INC. | -3.1% | 2 |
| Nov 12, 2025 | 6492-11-001RMC - A00218000 | Brazos Bryan |
FY27 - Large Guide Sign -11SH0006 · Routine Maintenance Project - Sealed | $195,406 | $179,565 | HAZMAT INTERNATIONAL, INC. | -8.1% | 10 |
| Nov 12, 2025 | 6487-20-001BPM - A00216530 | Wood Tyler |
FY 26 Bridge Rail RepairUS0080 · Bridge Preventative Maintenance - Sealed | $152,821 | $143,287 | RED BARON BUILDING COMPANY, LLC | -6.2% | 7 |
| Nov 12, 2025 | 6487-88-001MMC - A00216870 | Ellis Dallas |
Winter Weather Material 09 1125FM0876 · Material Maintenance Project | $130,000 | $142,840 | NSG LOGISTICS, LLC | +9.9% | 1 |
| Nov 12, 2025 | 6489-04-001MMC - A00217261 | Ellis Dallas |
Flexible Base 09 0925FM0876 · Material Maintenance Project | $155,000 | $120,000 | TOUCHSTONE RESOURCES, LLC | -22.6% | 5 |
| Nov 12, 2025 | 6491-70-001MMC - A00217932 | Brazos Bryan |
FY26 Bryan AO Flexbase - 11SH0006 · Material Maintenance Project | $111,000 | $111,000 | TOUCHSTONE RESOURCES, LLC | 0.0% | 7 |
| Nov 12, 2025 | 6488-92-001MMC - A00217230 | Ellis Dallas |
Emulsion 09 1125FM0876 · Material Maintenance Project | $117,000 | $97,775 | ERGON ASPHALT & EMULSIONS, INC. | -16.4% | 1 |
| Nov 12, 2025 | 6486-05-001BPM - A00216189 | Wilson San Antonio |
FY26 US 87 AT GUNN BRANCHUS0087 · Bridge Preventative Maintenance - Sealed | $110,128 | $90,862 | DIAMOND R CONTRACTING, LLC | -17.5% | 6 |
| Nov 12, 2025 | 6481-18-001BPM - A00214345 | Wilson San Antonio |
FY2026 FM 2505 AT UNNAMED DRAWFM2505 · Bridge Preventative Maintenance - Sealed | $69,445 | $53,230 | DIAMOND R CONTRACTING, LLC | -23.3% | 5 |
| Nov 12, 2025 | 6481-10-001BPM - A00214337 | Bexar San Antonio |
FY2026 FM2252 AT DRAINFM2252 · Bridge Preventative Maintenance - Sealed | $75,833 | $50,807 | DIAMOND R CONTRACTING, LLC | -33.0% | 7 |
| Nov 12, 2025 | 6488-96-001MMC - A00217236 | Ellis Dallas |
Hydraulic Cement 09 0925FM0876 · Material Maintenance Project | $35,750 | $44,000 | TOUCHSTONE RESOURCES, LLC | +23.1% | 1 |
| Nov 10, 2025 | 6487-84-001BPM - A00216832 | Nueces Corpus Christi |
6487-84-001 Bridge Preventative Maint.US0077 · Bridge Preventative Maintenance - Sealed | $880,711 | $379,500 | SCR CIVIL CONSTRUCTION, LLC | -56.9% | 8 |
| Nov 10, 2025 | 6489-65-001MMC - A00217509 | El Paso El Paso |
De-Icing/Anti-Icing WAOSL0375 · Material Maintenance Project | $282,800 | $308,799 | NSG LOGISTICS, LLC | +9.2% | 1 |
| Nov 7, 2025 | 6491-08-001MMC - A00217750 | Val Verde Laredo |
Brine - Val Verde & MaverickUS0277 · Material Maintenance Project - Sealed | $56,000 | $80,000 | TOUCHSTONE RESOURCES, LLC | +42.9% | 1 |
| Nov 7, 2025 | 6491-06-001MMC - A00217748 | Duval Laredo |
Lower Counties Brine SolutionSH0044 · Material Maintenance Project - Sealed | $37,250 | $54,000 | TOUCHSTONE RESOURCES, LLC | +45.0% | 1 |
| Nov 7, 2025 | 6493-09-001SUP - A00218262 | Williamson Austin |
Taylor Maintenance Litter FY26US0079 · State Use Project | $249,969 | — | 0 | ||
| Nov 6, 2025 | 0113-13-168F 2026(116) | Travis Austin |
SL 360 AT COURTYARD DRIVESL 360 · Interchange (New or Reconstructed) | $69,364,953 | $68,389,116 | WEBBER, LLC | -1.4% | 8 |
| Nov 6, 2025 | 0354-04-041F 2024(538) | Winkler Odessa |
SH115__FM874_3MI_S_ANDREWS_C/LSH 115 · Super-2 Highway | $35,916,484 | $28,204,481 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | -21.5% | 6 |
| Nov 6, 2025 | 0040-01-051F 2026(059) | Dallam Amarillo |
FY 26 DISTRICT WIDE SEALCOAT - 119US 87 · Seal Coat | $19,238,161 | $17,475,909 | Missouri Petroleum Products Company | -9.2% | 1 |
| Nov 6, 2025 | 0007-15-003F 2026(104) | Eastland Brownwood |
FM3363 IH20 FRONTAGE ROAD E FY26 SCFM 3363 · Seal Coat | $15,709,024 | $12,031,352 | NORTHEASTERN PAVERS, LLC | -23.4% | 4 |
| Nov 6, 2025 | 0108-01-030F 2026(119) | Van Zandt Tyler |
SH19,US80-IH20,SP2SH 19 · Super-2 Highway | $14,999,624 | $11,187,838 | BIG CREEK CONSTRUCTION, LTD. | -25.4% | 9 |
| Nov 6, 2025 | 1978-01-058STP 2026(171)MM | Tarrant Fort Worth |
FM 1938; FM 1709 TO STARNES RDFM 1938 · Safety Improvement Projects | $11,406,087 | $9,907,252 | RAGLE CONSTRUCTION, INC. | -13.1% | 9 |
1–100 of 168Next ›
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.