FY26 - Walker IH45 Bridge Repair - 11
- Let date
- Monday, November 24, 2025
- CCSJ
- 6493-41-001
- District
- Bryan
- County
- Walker
- Highway
- IH0045
- Limits
- Various to Various
- Classification
- Bridge Preventative Maintenance · Maintenance
- Project number
- BPM - A00218325
- Working days
- 12
- DBE goal
- 0%
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $210,237 | ||
| 1 | BK FIELD OPERATIONS LLC Low bidder | $114,511 | -45.5% | |
| 2 | STRUCTURAL INTEGRITY GROUP LLC | $148,886 | -29.2% | +30.0% |
| 3 | SCR CIVIL CONSTRUCTION, LLC | $157,215 | -25.2% | +37.3% |
| 4 | ROY JORGENSEN ASSOCIATES, INC. | $180,230 | -14.3% | +57.4% |
| 5 | FORDE CONSTRUCTION COMPANY, INC. | $183,525 | -12.7% | +60.3% |
| 6 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $196,875 | -6.4% | +71.9% |
| 7 | STRUCTURAL TECHNOLOGIES, LLC | $219,266 | +4.3% | +91.5% |
| 8 | AAD CONTRACTING INC. | $244,050 | +16.1% | +113.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BK FIELD OPERAT… | #2 STRUCTURAL INTE… | #3 SCR CIVIL CONST… | #4 ROY JORGENSEN A… | #5 FORDE CONSTRUCT… | #6 BUILT RIGHT CON… | #7 STRUCTURAL TECH… | #8 AAD CONTRACTING… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 495-7001 | RAISING EXIST STRUCT | 1 | LS | $100,062.50 | $50,000.00 | $50,000.00 | $70,000.00 | $70,000.00 | $69,000.00 | $75,000.00 | $88,500.00 | $90,000.00 |
| 2 | 500-7001 | MOBILIZATION | 1 | LS | $24,353.86 | $10,000.00 | $1,000.00 | $15,200.00 | $18,000.00 | $18,000.00 | $10,000.00 | $24,500.00 | $25,000.00 |
| 3 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 | MO | $13,103.56 | $1.00 | $18,000.00 | $15,200.00 | $8,775.00 | $35,000.00 | $4,500.00 | $38,020.00 | $10,000.00 |
| 4 | 503-7002 | PORTABLE CHANGEABLE MESSAGE SIGN | 1 | EA | $10,648.35 | $4,000.00 | $1,000.00 | $2,500.00 | $4,000.00 | $1,800.00 | $5,000.00 | $3,330.00 | $350.00 |
| 5 | 505-7001 | TMA (STATIONARY) | 15 | DAY | $216.85 | $1.00 | $250.00 | $375.00 | $100.00 | $200.00 | $300.00 | $950.00 | $350.00 |
| 6 | 786-7001 | CARBON FIBER REINF POLYMER PROTECTION | 623 | SF | $77.08 | $65.00 | $88.50 | $30.00 | $85.00 | $75.00 | $125.00 | $42.00 | $150.00 |
| 7 | 788-7001 | CONCRETE BEAM REPAIR | 2 | EA | $5,397.63 | $5,000.00 | $10,000.00 | $15,000.00 | $12,500.00 | $5,000.00 | $10,000.00 | $12,250.00 | $10,000.00 |