Bid code 506-6046

TRACKHOE WORK (EROSION & SEDMT CONT) · per HR

‹ All bid codes

$114.13Avg low bid / HR
$125.31Avg of all bids
$122.23Avg engineer's estimate
84Jobs · 12,100 HR

Average low bid by year

YearJobsQuantityAvg lowAvg all
20246180$169.56$168.05
2023193,717$147.95$166.64
2022112,147$80.04$82.20
2021102,180$87.91$104.01
202011955$99.29$97.14
20199737$84.08$110.61
2018111,330$130.94$137.51
20177854$124.18$135.73

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Jun 5, 20240246-01-037 RuskTyler5 HR $200.00GARRET SHIELDS INFRASTRUCTURE
Mar 6, 20240495-03-071 Van ZandtTyler50 HR $93.00REYNOLDS & KAY, LTD.
Mar 5, 20240203-05-039 WoodTyler50 HR $225.00LAMAR COMPANIES LLC
Feb 1, 20240206-06-032 RuskTyler13 HR $90.00REYNOLDS & KAY, LTD.
Jan 5, 20240203-05-047 WoodTyler15 HR $125.00TRUE ROADS CONSTRUCTION, LLC
Jan 4, 20240206-07-059 RuskTyler47 HR $225.00MADDEN CONTRACTING COMPANY, LLC.
Nov 1, 20230450-01-013 CherokeeTyler200 HR $125.00MADDEN CONTRACTING COMPANY, LLC.
Oct 5, 20230198-04-029 CherokeeTyler2,050 HR $130.00A. L. HELMCAMP, INC.
Sep 7, 20231322-02-017 Van ZandtTyler300 HR $92.00REYNOLDS & KAY, LTD.
Aug 3, 20230495-02-064 Van ZandtTyler300 HR $300.00INDUS ROAD & BRIDGE, INC.
Aug 3, 20230559-02-037 HendersonTyler20 HR $150.00BIG CREEK CONSTRUCTION, LTD.
Aug 3, 20232642-01-049 GreggTyler5 HR $100.00THK CONSTRUCTION LLC
Aug 3, 20230191-02-066 CherokeeTyler370 HR $150.00EAST TEXAS BRIDGE, INC.
Aug 2, 20232653-01-016 RuskTyler30 HR $200.00HIGHWAY 19 CONSTRUCTION LLC
Aug 2, 20230199-02-061 CherokeeTyler20 HR $100.00HIGHWAY 19 CONSTRUCTION LLC
Jun 27, 20230392-03-052 GreggTyler20 HR $91.00REYNOLDS & KAY, LTD.
May 5, 20231669-01-007 RuskTyler20 HR $125.00TRUE ROADS CONSTRUCTION, LLC
May 4, 20230910-16-154 SmithTyler10 HR $50.00HIGHWAY 19 CONSTRUCTION LLC
Apr 5, 20230164-04-163 SmithTyler16 HR $150.00FNH CONSTRUCTION, LLC
Feb 2, 20230096-06-075 GreggTyler50 HR $150.00EAST TEXAS BRIDGE, INC.
Feb 1, 20232075-01-058 SmithTyler16 HR $210.00DREWERY CONSTRUCTION COMPANY, INCORPORATED
Feb 1, 20230393-01-101 GreggTyler40 HR $250.00MADDEN CONTRACTING COMPANY, LLC.
Jan 6, 20230123-05-015 RuskTyler150 HR $195.00DREWERY CONSTRUCTION COMPANY, INCORPORATED
Jan 6, 20230058-04-022 CherokeeTyler40 HR $165.00MADDEN CONTRACTING COMPANY, LLC.
Jan 5, 20230123-04-023 RuskTyler60 HR $165.00MADDEN CONTRACTING COMPANY, LLC.
Sep 7, 20220392-03-050 GreggTyler40 HR $165.00MADDEN CONTRACTING COMPANY, LLC.
Sep 7, 20220138-16-005 GreggTyler20 HR $200.00MADDEN CONTRACTING COMPANY, LLC.
Aug 4, 20221171-01-022 Van ZandtTyler100 HR $107.00BAKER & COMPANY CONSTRUCTION, LLC
Aug 3, 20220522-04-032 SmithTyler200 HR $50.00HIGHWAY 19 CONSTRUCTION LLC
Aug 3, 20220245-06-087 SmithTyler100 HR $125.00L. S. EQUIPMENT CO., INC.
Jun 30, 20220198-03-026 AndersonTyler1,400 HR $80.00BIG CREEK CONSTRUCTION, LTD.
Mar 4, 20220964-01-009 WoodTyler152 HR $18.003LW CIVIL LLC
Mar 3, 20220910-07-072 GreggTyler80 HR $80.00RAGLE CONSTRUCTION, INC.
Feb 4, 20220910-07-078 GreggTyler5 HR $84.00SOUTH TEXAS ILLUMINATION, LLC
Jan 7, 20220910-16-147 SmithTyler30 HR $150.00THK CONSTRUCTION LLC
Jan 6, 20220378-06-022 CherokeeTyler20 HR $100.00HIGHWAY 19 CONSTRUCTION LLC
Aug 5, 20210108-02-033 Van ZandtTyler400 HR $50.00BIG CREEK CONSTRUCTION, LTD.
Aug 5, 20210118-04-032 CherokeeTyler100 HR $80.00A. L. HELMCAMP, INC.
Aug 4, 20210190-03-087 WoodTyler50 HR $125.00EAST TEXAS BRIDGE, INC.
May 5, 20210165-02-065 SmithTyler500 HR $100.00MADDEN CONTRACTING COMPANY, LLC.
Mar 5, 20210520-06-043 SmithTyler450 HR $95.00MADDEN CONTRACTING COMPANY, LLC.
Mar 5, 20210910-12-134 Van ZandtTyler60 HR $20.00EAST TEXAS BRIDGE, INC.
Mar 4, 20210495-06-034 SmithTyler100 HR $100.00LONGVIEW BRIDGE AND ROAD, LTD.
Feb 5, 20210634-01-014 CherokeeTyler120 HR $45.00STATELINE CONSTRUCTION, LLC
Jan 8, 20210123-03-022 CherokeeTyler200 HR $150.00MADDEN CONTRACTING COMPANY, LLC.
Jan 7, 20210646-05-027 HendersonTyler200 HR $90.25COPASA INC
Aug 5, 20202073-01-010 GreggTyler200 HR $115.00EAST TEXAS BRIDGE, INC.
Jul 9, 20200458-01-025 HendersonTyler100 HR $60.00BIG CREEK CONSTRUCTION, LTD.
Jul 9, 20200910-16-151 SmithTyler40 HR $120.00BAKER & COMPANY CONSTRUCTION, LLC
Apr 9, 20201150-02-006 CherokeeTyler50 HR $100.00MADDEN CONTRACTING COMPANY, LLC.
Apr 8, 20202073-01-009 GreggTyler200 HR $125.00EAST TEXAS BRIDGE, INC.
Mar 5, 20201124-03-012 CherokeeTyler50 HR $90.00A. L. HELMCAMP, INC.
Mar 5, 20200910-12-021 Van ZandtTyler40 HR $40.00EAST TEXAS BRIDGE, INC.
Mar 4, 20200910-35-034 WoodTyler20 HR $85.00STATELINE CONSTRUCTION, LLC
Mar 4, 20200910-12-138 Van ZandtTyler15 HR $95.00STATELINE CONSTRUCTION, LLC
Mar 4, 20200910-36-129 CherokeeTyler200 HR $95.00STATELINE CONSTRUCTION, LLC
Feb 7, 20200520-08-068 AndersonTyler40 HR $70.00REYNOLDS & KAY, LTD.
Dec 3, 20190646-02-029 Van ZandtTyler123 HR $20.00HIGHWAY 19 CONSTRUCTION LLC
Sep 6, 20190198-01-031 HendersonTyler75 HR $90.00REYNOLDS & KAY, LTD.
Aug 7, 20190378-03-017 SmithTyler150 HR $170.00DREWERY CONSTRUCTION COMPANY, INCORPORATED
Apr 3, 20190889-04-078 SmithTyler60 HR $100.00LONGVIEW BRIDGE AND ROAD, LTD.
Apr 2, 20190206-04-042 CherokeeTyler150 HR $90.00MADDEN CONTRACTING COMPANY, LLC.
Mar 6, 20191390-03-005 WoodTyler24 HR $65.00STATELINE CONSTRUCTION, LLC
Mar 5, 20190910-16-140 SmithTyler30 HR $40.00EAST TEXAS BRIDGE, INC.
Jan 9, 20190926-01-023 CherokeeTyler75 HR $10.00HIGHWAY 19 CONSTRUCTION LLC
Jan 9, 20193240-01-019 WoodTyler50 HR $85.00REYNOLDS & KAY, LTD.
Nov 6, 20180697-02-039 HendersonTyler50 HR $275.00AUSTIN BRIDGE & ROAD SERVICES, LP
Oct 3, 20180109-01-062 AndersonTyler150 HR $86.00A. L. HELMCAMP, INC.
Aug 8, 20180592-02-015 RuskTyler150 HR $120.00PINTO CONSTRUCTION CO., INC.
Jul 11, 20183199-01-008 AndersonTyler50 HR $75.00A. L. HELMCAMP, INC.
Jul 11, 20182654-01-022 SmithTyler50 HR $100.00LONGVIEW BRIDGE AND ROAD, LTD.
Jul 10, 20180191-03-081 SmithTyler250 HR $100.00HIGHWAY 19 CONSTRUCTION LLC
Jul 10, 20180393-02-027 RuskTyler50 HR $125.00MADDEN CONTRACTING COMPANY, LLC.
Jun 6, 20180206-03-061 CherokeeTyler100 HR $175.00DREWERY CONSTRUCTION COMPANY, INCORPORATED
Jun 5, 20180495-04-065 SmithTyler320 HR $150.00LONGVIEW BRIDGE AND ROAD, LTD.
Apr 3, 20180245-02-031 Van ZandtTyler60 HR $150.00BIG CREEK CONSTRUCTION, LTD.
Feb 1, 20181385-02-024 GreggTyler100 HR $150.00MADDEN CONTRACTING COMPANY, LLC.
Aug 9, 20171163-01-022 SmithTyler24 HR $75.00STATELINE CONSTRUCTION, LLC
Jul 12, 20171673-01-008 Van ZandtTyler200 HR $100.00DREWERY CONSTRUCTION COMPANY, INCORPORATED
Jul 11, 20171672-01-004 Van ZandtTyler200 HR $50.00HIGHWAY 19 CONSTRUCTION LLC
Jun 7, 20170522-02-037 Van ZandtTyler50 HR $325.00LONGVIEW BRIDGE AND ROAD, LTD.
Apr 4, 20170096-04-066 GreggTyler200 HR $200.00LONGVIEW BRIDGE AND ROAD, LTD.
Jan 4, 20170429-01-023 WoodTyler150 HR $100.00HIGHWAY 19 CONSTRUCTION LLC
Jan 4, 20170634-01-012 CherokeeTyler30 HR $100.00HIGHWAY 19 CONSTRUCTION LLC