Bid tab 0910-12-138

Let Mar 4, 2020 · Tyler · Van Zandt Sign up free

‹ Mar 2020 results

BRIDGE REPLACEMENT

Let date
Wednesday, March 4, 2020
CCSJ
0910-12-138
District
Tyler
County
Van Zandt
Highway
CR
Limits
CR2318 AT ALLIGATOR CREEK to W OF SH 19
Classification
Construction
Project number
BR 1902(398)
Working days
122

Bidders 9

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$499,749
1 STATELINE CONSTRUCTION, LLC Low bidder $552,443 +10.5%
2 EAST TEXAS BRIDGE, INC. $555,926 +11.2% +0.6%
3 LONGVIEW BRIDGE AND ROAD, LTD. $579,404 +15.9% +4.9%
4 HIGHWAY 19 CONSTRUCTION LLC $580,652 +16.2% +5.1%
5 PIERCE R & B LLC $597,060 +19.5% +8.1%
6 HODGES AND SON CONSTRUCTION COMPANY, INC. $612,884 +22.6% +10.9%
7 ED BELL CONSTRUCTION COMPANY $732,792 +46.6% +32.6%
8 A. L. HELMCAMP, INC. $786,891 +57.5% +42.4%
9 FNH CONSTRUCTION, LLC $956,340 +91.4% +73.1%

Bid tab: unit prices 40 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 STATELINE CONST…#2 EAST TEXAS BRID…#3 LONGVIEW BRIDGE…#4 HIGHWAY 19 CONS…#5 PIERCE R & B LLC#6 HODGES AND SON …#7 ED BELL CONSTRU…#8 A. L. HELMCAMP,…
1100-6002 PREPARING ROW4.1STA $800.00 $2,200.00 $2,000.00 $2,400.00 $2,500.00 $2,000.00 $3,600.00 $2,000.00 $2,000.00
2105-6011 REMOVING STAB BASE AND ASPH PAV (2"-6")452SY $5.00 $12.00 $5.50 $6.00 $15.00 $11.00 $10.00 $8.74 $11.00
3110-6001 EXCAVATION (ROADWAY)23CY $8.00 $100.00 $20.00 $30.00 $25.00 $65.00 $45.00 $25.00 $43.00
4132-6005 EMBANKMENT (FINAL)(ORD COMP)(TY C)313CY $20.00 $22.00 $24.00 $25.00 $30.00 $30.00 $15.00 $25.00 $26.00
5160-6003 FURNISHING AND PLACING TOPSOIL (4")828SY $1.30 $4.50 $2.00 $8.50 $3.00 $4.00 $4.00 $4.12 $3.00
6164-6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND)1,656SY $1.00 $1.45 $1.60 $1.50 $1.00 $1.60 $2.00 $1.31 $1.30
7164-6055 BONDED FBR MTRX SEED (TEMP)(WARM)828SY $0.7000 $1.75 $1.00 $1.00 $1.00 $1.10 $2.50 $2.00 $2.20
8164-6056 BONDED FBR MTRX SEED (TEMP)(COOL)828SY $0.7000 $0.1000 $1.00 $1.00 $1.00 $1.25 $2.50 $2.00 $2.20
9168-6001 VEGETATIVE WATERING18.22MG $13.00 $25.00 $10.00 $20.00 $10.00 $50.00 $1.00 $388.50 $75.00
10275-6001 CEMENT17TON $150.00 $250.00 $165.00 $220.00 $350.00 $220.00 $250.00 $269.24 $215.00
11275-6011 CEMENT TREAT(EXIST MATL)(8")902SY $4.00 $9.75 $4.00 $6.00 $10.00 $9.50 $15.00 $5.92 $18.00
12340-6106 D-GR HMA(SQ) TY-D PG64-22273TON $150.00 $138.00 $125.00 $135.00 $180.00 $144.00 $150.00 $140.00 $170.00
13400-6005 CEM STABIL BKFL72CY $150.00 $295.00 $225.00 $290.00 $200.00 $215.00 $200.00 $300.00 $270.00
14416-6003 DRILL SHAFT (30 IN)360LF $200.00 $212.00 $295.00 $240.00 $174.00 $245.00 $150.00 $225.00 $250.00
15420-6013 CL C CONC (ABUT)34.4CY $875.00 $985.00 $900.00 $950.00 $1,000.00 $1,050.00 $1,000.00 $1,000.00 $1,300.00
16422-6005 REINF CONC SLAB (BOX BEAM)1,962SF $15.00 $18.75 $15.00 $19.50 $17.00 $21.00 $22.00 $35.00 $53.00
17422-6023 SHEAR KEY20CY $350.00 $325.00 $400.00 $430.00 $250.00 $325.00 $600.00 $250.00 $700.00
18425-6005 PRESTR CONC BOX BEAM (4B34)298LF $180.00 $240.00 $250.00 $245.00 $257.67 $248.00 $270.00 $350.00 $250.00
19425-6006 PRESTR CONC BOX BEAM (5B34)149LF $190.00 $240.00 $250.00 $245.00 $257.67 $224.00 $270.00 $375.00 $250.00
20432-6033 RIPRAP (STONE PROTECTION)(18 IN)533CY $125.00 $98.00 $125.00 $145.00 $180.00 $150.00 $160.00 $175.00 $140.00
21432-6045 RIPRAP (MOW STRIP)(4 IN)20CY $500.00 $440.00 $450.00 $500.00 $400.00 $525.00 $550.00 $1,000.00 $750.00
22450-6006 RAIL (TY T223)194LF $95.00 $110.00 $90.00 $90.00 $110.00 $115.00 $150.00 $173.06 $200.00
23496-6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH)1EA $15,000.00 $13,000.00 $15,000.00 $9,000.00 $10,000.00 $8,500.00 $10,000.00 $10,000.00 $16,000.00
24500-6001 MOBILIZATION1LS $45,431.83 $40,000.00 $40,000.00 $45,000.00 $50,000.00 $50,000.00 $61,000.00 $63,000.00 $70,000.00
25502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING4MO $4,200.00 $2,800.00 $1,500.00 $2,350.00 $1,200.00 $2,200.00 $3,000.00 $3,000.00 $9,000.00
26506-6002 ROCK FILTER DAMS (INSTALL) (TY 2)40LF $30.00 $55.00 $40.00 $38.00 $35.00 $39.00 $5.00 $29.40 $60.00
27506-6011 ROCK FILTER DAMS (REMOVE)40LF $10.00 $22.00 $8.00 $11.00 $10.00 $12.00 $5.00 $15.75 $25.00
28506-6029 EARTHWORK (EROSN & SEDMT CONT, IN VEH)20CY $25.00 $60.00 $40.00 $30.00 $1.00 $100.00 $10.00 $23.95 $95.00
29506-6030 BACKHOE WORK (EROSION & SEDMT CONT)15HR $100.00 $50.00 $50.00 $150.00 $1.00 $110.00 $10.00 $351.42 $70.00
30506-6038 TEMP SEDMT CONT FENCE (INSTALL)689LF $2.50 $4.00 $3.00 $2.65 $3.00 $3.00 $1.00 $1.58 $4.20
31506-6039 TEMP SEDMT CONT FENCE (REMOVE)689LF $1.00 $1.50 $0.5000 $1.20 $1.00 $1.25 $1.00 $0.1600 $2.00
32506-6046 TRACKHOE WORK (EROSION & SEDMT CONT)15HR $140.00 $95.00 $70.00 $150.00 $1.00 $120.00 $10.00 $426.44 $95.00
33540-6001 MTL W-BEAM GD FEN (TIM POST)100LF $20.00 $22.00 $22.00 $22.00 $20.00 $19.37 $25.00 $18.11 $27.00
34540-6021 MTL THRIE-BEAM GD FEN (TIM POST)4EA $1,600.00 $2,150.00 $1,500.00 $1,500.00 $1,350.00 $1,590.00 $1,500.00 $1,528.80 $1,800.00
35544-6001 GUARDRAIL END TREATMENT (INSTALL)4EA $2,700.00 $2,750.00 $2,600.00 $2,700.00 $2,500.00 $2,450.00 $2,600.00 $2,377.20 $2,600.00
36658-6014 INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)4EA $20.00 $20.00 $20.00 $16.50 $25.00 $32.00 $50.00 $25.20 $32.00
37658-6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)4EA $35.00 $30.00 $30.00 $27.50 $25.00 $37.00 $50.00 $30.45 $51.00
385070-6001 STEEL FENCE (REMOVE)63LF $10.00 $10.00 $10.00 $20.00 $10.00 $10.00 $10.00 $30.00 $30.00
395070-6002 STEEL FENCE (INSTALL)96LF $15.00 $45.00 $50.00 $35.00 $30.00 $50.00 $60.00 $55.00 $60.00
406001-6001 PORTABLE CHANGEABLE MESSAGE SIGN28DAY $120.00 $150.00 $100.00 $100.00 $100.00 $125.00 $120.00 $195.00 $500.00

Showing the first 8 bidders. The Excel and CSV downloads include all 9.