$96.14Avg low bid / TON
$97.35Avg of all bids
$91.77Avg engineer's estimate
24Jobs · 212,541.6 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2019 | 7 | 108,450 | $97.72 | $96.93 |
| 2018 | 11 | 90,447 | $94.25 | $99.39 |
| 2017 | 6 | 13,644.6 | $96.04 | $90.83 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 7, 2019 | 0378-03-017 | SmithTyler | 18,667 TON | $110.00 | DREWERY CONSTRUCTION COMPANY, INCORPORATED |
| Jun 5, 2019 | 6343-32-001 | NavarroDallas | 2,512 TON | $115.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jun 4, 2019 | 6338-97-001 | EllisDallas | 5,575 TON | $125.00 | BIG CREEK CONSTRUCTION, LTD. |
| Apr 2, 2019 | 0173-02-071 | KaufmanDallas | 48,727 TON | $85.00 | STERLING DELAWARE HOLDING COMPANY, INC. |
| Apr 2, 2019 | 0206-04-042 | CherokeeTyler | 15,789 TON | $105.00 | MADDEN CONTRACTING COMPANY, LLC. |
| Mar 6, 2019 | 2249-01-008 | KaufmanDallas | 448 TON | $136.50 | ED BELL CONSTRUCTION COMPANY |
| Jan 8, 2019 | 0246-01-034 | RuskTyler | 16,732 TON | $101.50 | MADDEN CONTRACTING COMPANY, LLC. |
| Dec 6, 2018 | 6335-49-001 | ReevesOdessa | 1,000 TON | $190.00 | DAN WILLIAMS COMPANY |
| Nov 6, 2018 | 0697-02-039 | HendersonTyler | 10,771 TON | $85.00 | AUSTIN BRIDGE & ROAD SERVICES, LP |
| Aug 8, 2018 | 0191-01-063 | SmithTyler | 23,670 TON | $97.00 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Aug 7, 2018 | 0117-01-052 | BrazosBryan | 31 TON | $130.92 | FLORIDA TRAFFIC CONTROL DEVICES, INC. |
| Jul 11, 2018 | 1685-05-118 | HarrisHouston | 2 TON | $500.00 | MBN ENTERPRISES LLC |
| Jul 10, 2018 | 0191-03-081 | SmithTyler | 18,758 TON | $97.00 | HIGHWAY 19 CONSTRUCTION LLC |
| Jun 5, 2018 | 0095-03-093 | KaufmanDallas | 4,388 TON | $75.00 | OLDCASTLE MATERIALS TEXAS, INC. |
| May 1, 2018 | 0123-03-021 | CherokeeTyler | 10,707 TON | $94.50 | MADDEN CONTRACTING COMPANY, LLC. |
| May 1, 2018 | 1024-01-074 | ChambersBeaumont | 3,324 TON | $76.00 | OLDCASTLE MATERIALS TEXAS, INC. |
| Feb 2, 2018 | 0495-07-075 | GreggTyler | 4,928 TON | $100.50 | MADDEN CONTRACTING COMPANY, LLC. |
| Feb 1, 2018 | 1385-02-024 | GreggTyler | 12,868 TON | $94.00 | MADDEN CONTRACTING COMPANY, LLC. |
| Dec 6, 2017 | 0393-03-034 | PanolaAtlanta | 5,430 TON | $94.00 | MADDEN CONTRACTING COMPANY, LLC. |
| Aug 9, 2017 | 0675-07-101 | WalkerBryan | 293 TON | $110.00 | JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY |
| Aug 9, 2017 | 0918-47-114 | DallasDallas | 207.6 TON | $180.00 | HIGHWAY 19 CONSTRUCTION LLC |
| Jun 7, 2017 | 0522-02-037 | Van ZandtTyler | 4,391 TON | $105.00 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Jun 7, 2017 | 0081-13-057 | DentonDallas | 1,492 TON | $67.16 | ED BELL CONSTRUCTION COMPANY |
| Jan 4, 2017 | 0675-07-096 | WalkerBryan | 1,831 TON | $92.39 | WEBBER, LLC |