Bid code 260-6060

LIME (HYDRATED OR COMMERCIAL)(SLURRY) · per TON

‹ All bid codes

$151.85Avg low bid / TON
$171.31Avg of all bids
$162.15Avg engineer's estimate
12Jobs · 10,475.37 TON

Average low bid by year

YearJobsQuantityAvg lowAvg all
2024134$394.36$410.87
202314.6$600.00$600.00
2021243.93$185.07$209.91
2020142.84$194.00$184.60
20191366$170.00$180.00
201838,747$146.77$166.30
20171222$180.00$221.17
201621,015$169.55$175.59

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Jun 5, 20240912-72-559 HarrisHouston34 TON $394.36R CONSTRUCTION CIVIL, LLC
Aug 3, 20230912-72-641 HarrisHouston4.6 TON $600.00MAIN LANE INDUSTRIES LTD.
Oct 8, 20210912-72-353 HarrisHouston30.93 TON $183.00JAMES CONSTRUCTION GROUP, LLC
Aug 5, 20210912-72-352 HarrisHouston13 TON $190.00ARANDA BROTHERS CONSTRUCTION CO., INC.
Mar 5, 20200912-72-348 HarrisHouston42.84 TON $194.00ARANDA BROTHERS CONSTRUCTION CO., INC.
Nov 6, 20191663-03-017 NavarroDallas366 TON $170.00A. L. HELMCAMP, INC.
Oct 2, 20180121-08-019 NavarroDallas3,807 TON $165.00A. K. GILLIS & SONS, INC.
Jun 6, 20181317-01-015 EllisDallas1,270 TON $155.00KNIFE RIVER CORPORATION - SOUTH
Jun 5, 20180092-13-023 NavarroDallas3,670 TON $125.00KNIFE RIVER CORPORATION - SOUTH
Dec 6, 20170786-01-083 JeffersonBeaumont222 TON $180.00OLDCASTLE MATERIALS TEXAS, INC.
Dec 1, 20160997-02-039 NavarroDallas456 TON $169.00KNIFE RIVER CORPORATION - SOUTH
Nov 4, 20160596-04-041 EllisDallas559 TON $170.00BIG CREEK CONSTRUCTION, LTD.