$151.85Avg low bid / TON
$171.31Avg of all bids
$162.15Avg engineer's estimate
12Jobs · 10,475.37 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 34 | $394.36 | $410.87 |
| 2023 | 1 | 4.6 | $600.00 | $600.00 |
| 2021 | 2 | 43.93 | $185.07 | $209.91 |
| 2020 | 1 | 42.84 | $194.00 | $184.60 |
| 2019 | 1 | 366 | $170.00 | $180.00 |
| 2018 | 3 | 8,747 | $146.77 | $166.30 |
| 2017 | 1 | 222 | $180.00 | $221.17 |
| 2016 | 2 | 1,015 | $169.55 | $175.59 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 5, 2024 | 0912-72-559 | HarrisHouston | 34 TON | $394.36 | R CONSTRUCTION CIVIL, LLC |
| Aug 3, 2023 | 0912-72-641 | HarrisHouston | 4.6 TON | $600.00 | MAIN LANE INDUSTRIES LTD. |
| Oct 8, 2021 | 0912-72-353 | HarrisHouston | 30.93 TON | $183.00 | JAMES CONSTRUCTION GROUP, LLC |
| Aug 5, 2021 | 0912-72-352 | HarrisHouston | 13 TON | $190.00 | ARANDA BROTHERS CONSTRUCTION CO., INC. |
| Mar 5, 2020 | 0912-72-348 | HarrisHouston | 42.84 TON | $194.00 | ARANDA BROTHERS CONSTRUCTION CO., INC. |
| Nov 6, 2019 | 1663-03-017 | NavarroDallas | 366 TON | $170.00 | A. L. HELMCAMP, INC. |
| Oct 2, 2018 | 0121-08-019 | NavarroDallas | 3,807 TON | $165.00 | A. K. GILLIS & SONS, INC. |
| Jun 6, 2018 | 1317-01-015 | EllisDallas | 1,270 TON | $155.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jun 5, 2018 | 0092-13-023 | NavarroDallas | 3,670 TON | $125.00 | KNIFE RIVER CORPORATION - SOUTH |
| Dec 6, 2017 | 0786-01-083 | JeffersonBeaumont | 222 TON | $180.00 | OLDCASTLE MATERIALS TEXAS, INC. |
| Dec 1, 2016 | 0997-02-039 | NavarroDallas | 456 TON | $169.00 | KNIFE RIVER CORPORATION - SOUTH |
| Nov 4, 2016 | 0596-04-041 | EllisDallas | 559 TON | $170.00 | BIG CREEK CONSTRUCTION, LTD. |