Routine Maintenance Project
CCSJ 6509-74-001 · lets Dec 11, 2026 · Marion, Atlanta · SH0049
$172,467Engineer's estimate
Items at market: $168,798 (-2.1%)
$160,349Most likely low bid$149,774 to $169,796 (middle half)
4.8Expected bidders4 plan holders, 3 regular bidders
60/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$160,349
Estimate $172,467
$133,792 (1 in 10 go lower)$174,696 (1 in 10 go higher)
From 31 comparable let jobs (district + work type, estimates of $68,987 to $431,168, last 3 years). 81% of them went under the estimate; the typical low bid was -7.0% vs estimate.
Bid / no-bid score
- Competition18 / 25Jobs like this draw about 4.8 bidders.
- Margin9 / 20Low bids land at 93% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 6509-69-001Bowie · 3 bidders | $204,500-8.6% |
| Oct 2026 | 6509-70-001Harrison · 3 bidders | $297,000+22.5% |
| Mar 2026 | 6495-70-001Bowie · 3 bidders | $180,035-1.5% |
| Mar 2026 | 6495-71-001Harrison · 2 bidders | $232,465+15.5% |
| Mar 2026 | 6495-72-001Titus · 2 bidders | $173,785-4.9% |
| Mar 2026 | 6490-77-001Upshur · 2 bidders | $52,820-33.6% |
| Feb 2026 | 6490-91-001Panola · 5 bidders | $207,726-1.6% |
| Feb 2026 | 6490-92-001Morris · 6 bidders | $200,828+1.1% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Atlanta | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| CENTRAL NORTH CONSTRUCTION, LLC SharpestBidders | 62 | 12 | 5.7% | -22.3% | $182,238 | |
| PERRY WESTBidders | 16 | 6 | 6 of 16 | 10.2% | -4.8% | $190,090 |
| HX FARMS, INC.Bidders | 30 | 5 | 5 of 25 | 12.5% | -5.8% | $194,031 |
| ROTOLO CONSULTANTS, INC.Bidders | 0 | 0 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.