Callout MBGF Repair (N) FY '26
6495-70-001 · let Mar 18, 2026 · Bowie, Atlanta · Routine Maintenance Project
$180,035Low bid: CATOCON, INC.-1.5% vs estimate $182,810
$43,135Left on the table24.0% gap to the second bid
3BiddersSpread 31% low to high
31Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CATOCON, INC. | $180,035 | -1.5% | $43,135 | 4+$41,147 | 4-$44,198 | |
| 2 | AUSTIN BARRICADE COMPANY, L.L.C. | $223,170 | +24.0% | 22.1% | $11,969 | 7+$60,500 | 5-$45,548 |
| 3 | H. V. CAVER, INC. | $235,139 | +30.6% | 28.6% | 3+$18,568 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
CATOCON, INC. vs AUSTIN BARRICADE COMPANY, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1.00 | $1,500.00 | $600.85 | $29,980 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 10 EA | $4,000.00 | $5,000.00 | $3,190.07 | $10,000 |
| 770-7018 REPLACE BLOCKOUT | 50 EA | $30.00 | $180.00 | $44.95 | $7,500 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 25 CY | $300.00 | $100.00 | $616.83 | -$5,000 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 10 EA | $500.00 | $1.00 | $65.99 | -$4,990 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 50 EA | $85.00 | $180.00 | $67.59 | $4,750 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 50 EA | $10.00 | $100.00 | $46.70 | $4,500 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 5 EA | $1,000.00 | $1,500.00 | $1,297.32 | $2,500 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 500 LF | $3.00 | $8.00 | $2.84 | $2,500 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 250 LF | $60.00 | $50.00 | $31.82 | -$2,500 |
| 770-7022 REPLACE SGT CABLE ANCHOR | 10 EA | $200.00 | $1.00 | $95.89 | -$1,990 |
| 770-7024 REPLACE SGT STRUT | 10 EA | $200.00 | $1.00 | $96.41 | -$1,990 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 40 SF | $100.00 | $55.00 | $192.68 | -$1,800 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 350 LF | $45.00 | $40.00 | $25.60 | -$1,750 |
| 770-7008 REPLACE TIMBER POST W/ CONC FND | 50 EA | $60.00 | $85.00 | $94.21 | $1,250 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 5 DAY | $1.00 | $250.00 | $87.82 | $1,245 |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 1,000 LF | $45.00 | $44.00 | $22.03 | -$1,000 |
| 770-7009 REPLACE STEEL POST W/ CONC FND | 50 EA | $80.00 | $100.00 | $41.43 | $1,000 |
| 770-7021 REPLACE SGT OBJECT MARKER | 10 EA | $100.00 | $1.00 | $34.21 | -$990 |
| 770-7023 REPLACE SGT CABLE ASSEMBLY | 10 EA | $100.00 | $1.00 | $98.88 | -$990 |
Positive: the low bidder was cheaper on that item. These 20 items account for $42,225 of the $43,135 gap.
CATOCON, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 1,000 LF | $45.00 | $22.03 | 2.04x | $22,973 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 250 LF | $60.00 | $31.82 | 1.89x | $7,046 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 350 LF | $45.00 | $25.60 | 1.76x | $6,789 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 10 EA | $500.00 | $65.99 | 7.58x | $4,340 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1.00 | $600.85 | 0.00x | -$11,997 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 25 CY | $300.00 | $616.83 | 0.49x | -$7,921 |
| 542-7002 REMOVE TERMINAL ANCHOR SECTION | 10 EA | $1.00 | $263.33 | 0.00x | -$2,623 |
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 1,000 LF | $44.00 | $22.03 | 2.00x | $21,973 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1,500.00 | $600.85 | 2.50x | $17,983 |
| 770-7018 REPLACE BLOCKOUT | 50 EA | $180.00 | $44.95 | 4.00x | $6,752 |
| 770-7017 REPLACE SINGLE GDRAIL TERMINAL POST | 50 EA | $180.00 | $67.59 | 2.66x | $5,620 |
| 770-7009 REPLACE STEEL POST W/ CONC FND | 50 EA | $100.00 | $41.43 | 2.41x | $2,928 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 50 EA | $100.00 | $46.70 | 2.14x | $2,665 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 500 LF | $8.00 | $2.84 | 2.81x | $2,578 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 25 CY | $100.00 | $616.83 | 0.16x | -$12,921 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 40 SF | $55.00 | $192.68 | 0.29x | -$5,507 |
| 544-7003 GUARDRAIL END TREATMENT (REMOVE) | 10 EA | $1.00 | $284.94 | 0.00x | -$2,839 |
| 542-7002 REMOVE TERMINAL ANCHOR SECTION | 10 EA | $1.00 | $263.33 | 0.00x | -$2,623 |