Callout MBGF Repair (S) FY '26
6495-71-001 · let Mar 18, 2026 · Harrison, Atlanta · Routine Maintenance Project
$232,465Low bid: AUSTIN BARRICADE COMPANY, L.L.C.+15.5% vs estimate $201,210
$73,585Left on the table31.7% gap to the second bid
2BiddersSpread 32% low to high
33Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AUSTIN BARRICADE COMPANY, L.L.C. | $232,465 | 15.5% | $73,585 | 6+$67,347 | 7-$72,465 | |
| 2 | CATOCON, INC. | $306,050 | +31.7% | 52.1% | 6+$90,749 | 1-$11,757 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
AUSTIN BARRICADE COMPANY, L.L.C. vs CATOCON, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 15 EA | $1,000.00 | $2,000.00 | $975.38 | $15,000 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 25 CY | $100.00 | $500.00 | $616.83 | $10,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1,500.00 | $2,000.00 | $600.85 | $10,000 |
| 774-7029 REPAIR (NARROW QUAD BAY) | 20 EA | $500.00 | $1,000.00 | $1,490.11 | $10,000 |
| 774-7028 REPAIR (NARROW QUAD NOSE) | 5 EA | $1.00 | $2,000.00 | $1,384.06 | $9,995 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $100.00 | $217.57 | $9,900 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 10 EA | $80.00 | $1,000.00 | $65.99 | $9,200 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 10 EA | $4,900.00 | $4,000.00 | $3,190.07 | -$9,000 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 250 LF | $100.00 | $65.00 | $31.82 | -$8,750 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 5 EA | $1,250.00 | $2,000.00 | $1,297.32 | $3,750 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 350 LF | $38.00 | $45.00 | $25.60 | $2,450 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 40 SF | $50.00 | $100.00 | $192.68 | $2,000 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 50 EA | $120.00 | $80.00 | $46.70 | -$2,000 |
| 770-7009 REPLACE STEEL POST W/ CONC FND | 50 EA | $120.00 | $80.00 | $41.43 | -$2,000 |
| 770-7023 REPLACE SGT CABLE ASSEMBLY | 10 EA | $1.00 | $200.00 | $98.88 | $1,990 |
| 770-7002 REPLACE RAIL ELEMENT (THRIE-BEAM) | 25 LF | $50.00 | $100.00 | $40.34 | $1,250 |
| 770-7006 REPLACE TIMBER POST W/O CONC FND | 50 EA | $55.00 | $80.00 | $89.82 | $1,250 |
| 770-7008 REPLACE TIMBER POST W/ CONC FND | 50 EA | $55.00 | $80.00 | $94.21 | $1,250 |
| 770-7019 REPAIR STEEL POST WITH BASE PLATE | 5 EA | $85.00 | $300.00 | $137.68 | $1,075 |
| 542-7001 REMOVE METAL BEAM GUARD FENCE | 500 LF | $6.00 | $4.00 | $2.84 | -$1,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $66,360 of the $73,585 gap.
AUSTIN BARRICADE COMPANY, L.L.C.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 1,000 LF | $44.00 | $22.03 | 2.00x | $21,973 |
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $1,500.00 | $600.85 | 2.50x | $17,983 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 250 LF | $100.00 | $31.82 | 3.14x | $17,046 |
| 770-7009 REPLACE STEEL POST W/ CONC FND | 50 EA | $120.00 | $41.43 | 2.90x | $3,928 |
| 770-7007 REPLACE STEEL POST W/O CONC FND | 50 EA | $120.00 | $46.70 | 2.57x | $3,665 |
| 770-7018 REPLACE BLOCKOUT | 50 EA | $100.00 | $44.95 | 2.22x | $2,752 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $1.00 | $217.57 | 0.00x | -$21,657 |
| 774-7029 REPAIR (NARROW QUAD BAY) | 20 EA | $500.00 | $1,490.11 | 0.34x | -$19,802 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 25 CY | $100.00 | $616.83 | 0.16x | -$12,921 |
| 774-7028 REPAIR (NARROW QUAD NOSE) | 5 EA | $1.00 | $1,384.06 | 0.00x | -$6,915 |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 40 SF | $50.00 | $192.68 | 0.26x | -$5,707 |
| 544-7003 GUARDRAIL END TREATMENT (REMOVE) | 10 EA | $1.00 | $284.94 | 0.00x | -$2,839 |
| 542-7002 REMOVE TERMINAL ANCHOR SECTION | 10 EA | $1.00 | $263.33 | 0.00x | -$2,623 |
CATOCON, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 20 EA | $2,000.00 | $600.85 | 3.33x | $27,983 |
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 1,000 LF | $45.00 | $22.03 | 2.04x | $22,973 |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 15 EA | $2,000.00 | $975.38 | 2.05x | $15,369 |
| 770-7003 REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM) | 10 EA | $1,000.00 | $65.99 | 15.15x | $9,340 |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 250 LF | $65.00 | $31.82 | 2.04x | $8,296 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 350 LF | $45.00 | $25.60 | 1.76x | $6,789 |
| 505-7001 TMA (STATIONARY) | 100 DAY | $100.00 | $217.57 | 0.46x | -$11,757 |