ROW Mowing Tract 1 FY2026
6490-91-001 · let Feb 6, 2026 · Panola, Atlanta · Routine Maintenance Project
$207,726Low bid: AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY-1.6% vs estimate $211,058
$6,366Left on the table3.1% gap to the second bid
5BiddersSpread 27% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY | $207,726 | -1.6% | $6,366 | 0 | 0 | |
| 2 | S G COMPANY, LLC | $214,092 | +3.1% | 1.4% | $5,634 | 0 | 0 |
| 3 | SKYLINE CONSTRUCTION PAVING & STRIPING | $219,726 | +5.8% | 4.1% | $22,939 | 0 | 0 |
| 4 | ABESCAPE GROUP LLC | $242,665 | +16.8% | 15.0% | $21,865 | 0 | 1-$5,854 |
| 5 | CEHAND SERVICES LLC | $264,530 | +27.3% | 25.3% | 1+$13,946 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY vs S G COMPANY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7001 FULL - WIDTH MOWING - TRACT (1) | 5,434 AC | $36.87 | $38.00 | $42.29 | $6,140 |
| 730-7021 SPOT MOWING | 200 AC | $36.87 | $38.00 | $30.27 | $226 |
Positive: the low bidder was cheaper on that item. These 2 items account for $6,366 of the $6,366 gap.
ABESCAPE GROUP LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 730-7021 SPOT MOWING | 200 AC | $1.00 | $30.27 | 0.03x | -$5,854 |
CEHAND SERVICES LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 730-7021 SPOT MOWING | 200 AC | $100.00 | $30.27 | 3.30x | $13,946 |