ROW Mowing Tract 2 FY2026

6490-92-001 · let Feb 6, 2026 · Morris, Atlanta · Routine Maintenance Project

$200,828Low bid: AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY+1.1% vs estimate $198,632
$15,114Left on the table7.5% gap to the second bid
6BiddersSpread 21% low to high
2Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY $200,8281.1% $15,114 0 0
2SKYLINE CONSTRUCTION PAVING & STRIPING $215,942+7.5%8.7% $1,532 0 0
3ABESCAPE GROUP LLC $217,474+8.3%9.5% $20,070 0 1-$5,854
4HX FARMS, INC. $237,544+18.3%19.6% $1,836 0 0
5PERRY WEST $239,380+19.2%20.5% $4,000 1+$9,946 0
6CEHAND SERVICES LLC $243,380+21.2%22.5%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY vs SKYLINE CONSTRUCTION PAVING & STRIPING, biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7002 FULL - WIDTH MOWING - TRACT (2)4,964 AC $38.89$41.89$40.43 $14,892
730-7021 SPOT MOWING200 AC $38.89$40.00$30.27 $222

Positive: the low bidder was cheaper on that item. These 2 items account for $15,114 of the $15,114 gap.

ABESCAPE GROUP LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
730-7021 SPOT MOWING200 AC $1.00$30.270.03x-$5,854

PERRY WEST: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
730-7021 SPOT MOWING200 AC $80.00$30.272.64x$9,946