ROW Mowing Tract 2 FY2026
6490-92-001 · let Feb 6, 2026 · Morris, Atlanta · Routine Maintenance Project
$200,828Low bid: AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY+1.1% vs estimate $198,632
$15,114Left on the table7.5% gap to the second bid
6BiddersSpread 21% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY | $200,828 | 1.1% | $15,114 | 0 | 0 | |
| 2 | SKYLINE CONSTRUCTION PAVING & STRIPING | $215,942 | +7.5% | 8.7% | $1,532 | 0 | 0 |
| 3 | ABESCAPE GROUP LLC | $217,474 | +8.3% | 9.5% | $20,070 | 0 | 1-$5,854 |
| 4 | HX FARMS, INC. | $237,544 | +18.3% | 19.6% | $1,836 | 0 | 0 |
| 5 | PERRY WEST | $239,380 | +19.2% | 20.5% | $4,000 | 1+$9,946 | 0 |
| 6 | CEHAND SERVICES LLC | $243,380 | +21.2% | 22.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
AABA MOWING CONTRACTORS, LIMITED LIABILITY COMPANY vs SKYLINE CONSTRUCTION PAVING & STRIPING, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7002 FULL - WIDTH MOWING - TRACT (2) | 4,964 AC | $38.89 | $41.89 | $40.43 | $14,892 |
| 730-7021 SPOT MOWING | 200 AC | $38.89 | $40.00 | $30.27 | $222 |
Positive: the low bidder was cheaper on that item. These 2 items account for $15,114 of the $15,114 gap.
ABESCAPE GROUP LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 730-7021 SPOT MOWING | 200 AC | $1.00 | $30.27 | 0.03x | -$5,854 |
PERRY WEST: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 730-7021 SPOT MOWING | 200 AC | $80.00 | $30.27 | 2.64x | $9,946 |