Landscape Maintenance - Gilmer FY 2026
6490-77-001 · let Mar 18, 2026 · Upshur, Atlanta · Routine Maintenance Project
$52,820Low bid: KJRM GENERAL CONTRACTORS, LLC-33.6% vs estimate $79,600
$480Left on the table0.9% gap to the second bid
2BiddersSpread 1% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | KJRM GENERAL CONTRACTORS, LLC | $52,820 | -33.6% | $480 | 0 | 1-$13,742 | |
| 2 | SCOUT 5 CONSTRUCTION LLC | $53,300 | +0.9% | -33.0% | 0 | 1-$13,742 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
KJRM GENERAL CONTRACTORS, LLC vs SCOUT 5 CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 751-7019 LITTER PICKUP | 48 CYC | $545.00 | $550.00 | $609.09 | $240 |
| 751-7028 MOWING, TRIMMING, AND EDGING | 48 CYC | $545.00 | $550.00 | $575.58 | $240 |
| 751-7008 PRUNING | 2 CYC | $250.00 | $250.00 | $7,121.14 | $0 |
Positive: the low bidder was cheaper on that item. These 3 items account for $480 of the $480 gap.
KJRM GENERAL CONTRACTORS, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 751-7008 PRUNING | 2 CYC | $250.00 | $7,121.14 | 0.04x | -$13,742 |
SCOUT 5 CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 751-7008 PRUNING | 2 CYC | $250.00 | $7,121.14 | 0.04x | -$13,742 |