Routine Maintenance Project
CCSJ 6509-73-001 · lets Dec 11, 2026 · Upshur, Atlanta · FM0556
$207,284Engineer's estimate
Items at market: $186,619 (-10.0%)
$191,383Most likely low bid$179,573 to $204,043 (middle half)
4.9Expected bidders2 plan holders, 2 regular bidders
56/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$191,383
Estimate $207,284
$157,139 (1 in 10 go lower)$209,925 (1 in 10 go higher)
From 32 comparable let jobs (district + work type, estimates of $82,914 to $518,210, last 3 years). 81% of them went under the estimate; the typical low bid was -7.7% vs estimate.
Bid / no-bid score
- Competition17 / 25Jobs like this draw about 4.9 bidders.
- Margin8 / 20Low bids land at 92% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 6509-69-001Bowie · 3 bidders | $204,500-8.6% |
| Oct 2026 | 6509-70-001Harrison · 3 bidders | $297,000+22.5% |
| Jul 2026 | 6502-12-001Marion · 6 bidders | $338,876-27.7% |
| Jul 2026 | 6502-13-001Harrison · 4 bidders | $354,692-26.4% |
| Mar 2026 | 6495-70-001Bowie · 3 bidders | $180,035-1.5% |
| Mar 2026 | 6495-71-001Harrison · 2 bidders | $232,465+15.5% |
| Mar 2026 | 6495-72-001Titus · 2 bidders | $173,785-4.9% |
| Feb 2026 | 6490-91-001Panola · 5 bidders | $207,726-1.6% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Atlanta | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| CENTRAL NORTH CONSTRUCTION, LLC SharpestBidders | 62 | 12 | 5.7% | -22.3% | $219,027 | |
| HX FARMS, INC.Bidders | 30 | 5 | 5 of 25 | 12.5% | -5.8% | $233,201 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.