Tree & Stump Removal/Trimming - Harrison
6502-13-001 · let Jul 15, 2026 · Harrison, Atlanta · Routine Maintenance Project
$354,692Low bid: RHINO EQUITY, LLC-26.4% vs estimate $482,105
$90,275Left on the table25.5% gap to the second bid
4BiddersSpread 126% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RHINO EQUITY, LLC | $354,692 | -26.4% | $90,275 | 2+$69,783 | 0 | |
| 2 | WESTERN CERTIFIED ARBORISTS | $444,967 | +25.5% | -7.7% | $12,975 | 7+$141,358 | 0 |
| 3 | CEHAND SERVICES LLC | $457,943 | +29.1% | -5.0% | $344,350 | 9+$108,739 | 1-$2,693 |
| 4 | S FOWLER SERVICES LLC | $802,293 | +126.2% | 66.4% | 8+$492,944 | 1-$10,879 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RHINO EQUITY, LLC vs WESTERN CERTIFIED ARBORISTS, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 75 EA | $130.00 | $750.00 | $208.61 | $46,500 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 175 EA | $125.00 | $350.00 | $141.37 | $39,375 |
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 57.917 MI | $2,200.00 | $1,600.00 | $1,716.86 | -$34,750 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 250 EA | $120.00 | $225.00 | $100.44 | $26,250 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 1,000 EA | $115.00 | $90.00 | $60.77 | -$25,000 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $250.00 | $2,500.00 | $529.99 | $11,250 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $200.00 | $750.00 | $293.05 | $11,000 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $200.00 | $350.00 | $217.57 | $7,500 |
| 7020-7001 GEN DEBRIS REMOVE ON HWY ROW | 500 CY | $50.00 | $40.00 | $18.89 | -$5,000 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $100.00 | $1,200.00 | $600.85 | $4,400 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 5 EA | $250.00 | $750.00 | $334.81 | $2,500 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 5 EA | $250.00 | $750.00 | $436.67 | $2,500 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 5 EA | $250.00 | $750.00 | $450.06 | $2,500 |
| 752-7004 STUMP REMOVAL | 25 EA | $250.00 | $300.00 | $157.73 | $1,250 |
Positive: the low bidder was cheaper on that item. These 14 items account for $90,275 of the $90,275 gap.
RHINO EQUITY, LLC: unbalanced items
Placed 1WESTERN CERTIFIED ARBORISTS: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 75 EA | $750.00 | $208.61 | 3.60x | $40,604 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 175 EA | $350.00 | $141.37 | 2.48x | $36,511 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 250 EA | $225.00 | $100.44 | 2.24x | $31,140 |
| 7020-7001 GEN DEBRIS REMOVE ON HWY ROW | 500 CY | $40.00 | $18.89 | 2.12x | $10,557 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $2,500.00 | $529.99 | 4.72x | $9,850 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $750.00 | $293.05 | 2.56x | $9,139 |
| 752-7004 STUMP REMOVAL | 25 EA | $300.00 | $157.73 | 1.90x | $3,557 |
CEHAND SERVICES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 175 EA | $300.00 | $141.37 | 2.12x | $27,761 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 250 EA | $200.00 | $100.44 | 1.99x | $24,890 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 75 EA | $400.00 | $208.61 | 1.92x | $14,354 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $500.00 | $217.57 | 2.30x | $14,121 |
| 7020-7001 GEN DEBRIS REMOVE ON HWY ROW | 500 CY | $40.00 | $18.89 | 2.12x | $10,557 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $600.00 | $293.05 | 2.05x | $6,139 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $1,400.00 | $529.99 | 2.64x | $4,350 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 5 EA | $1,200.00 | $450.06 | 2.67x | $3,750 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 5 EA | $1,000.00 | $436.67 | 2.29x | $2,817 |
| 752-7004 STUMP REMOVAL | 25 EA | $50.00 | $157.73 | 0.32x | -$2,693 |
S FOWLER SERVICES LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 1,000 EA | $300.00 | $60.77 | 4.94x | $239,226 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 250 EA | $500.00 | $100.44 | 4.98x | $99,890 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 175 EA | $500.00 | $141.37 | 3.54x | $62,761 |
| 7020-7001 GEN DEBRIS REMOVE ON HWY ROW | 500 CY | $100.00 | $18.89 | 5.29x | $40,557 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 75 EA | $500.00 | $208.61 | 2.40x | $21,854 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $3,000.00 | $529.99 | 5.66x | $12,350 |
| 752-7004 STUMP REMOVAL | 25 EA | $500.00 | $157.73 | 3.17x | $8,557 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 5 EA | $2,000.00 | $450.06 | 4.44x | $7,750 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $0.0010 | $217.57 | 0.00x | -$10,879 |