Tree & Stump Removal/Trimming - Marion
6502-12-001 · let Jul 15, 2026 · Marion, Atlanta · Routine Maintenance Project
$338,876Low bid: CEHAND SERVICES LLC-27.7% vs estimate $468,924
$1,179Left on the table0.3% gap to the second bid
6BiddersSpread 198% low to high
14Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CEHAND SERVICES LLC | $338,876 | -27.7% | $1,179 | 0 | 2-$9,797 | |
| 2 | RHINO EQUITY, LLC | $340,055 | +0.3% | -27.5% | $21,486 | 2+$64,783 | 0 |
| 3 | CATOCON, INC. | $361,541 | +6.7% | -22.9% | $46,759 | 4+$48,143 | 2-$6,563 |
| 4 | HX FARMS, INC. | $408,299 | +20.5% | -12.9% | $24,617 | 3+$88,736 | 1-$3,918 |
| 5 | WESTERN CERTIFIED ARBORISTS | $432,916 | +27.8% | -7.7% | $575,739 | 7+$141,358 | 0 |
| 6 | S FOWLER SERVICES LLC | $1,008,655 | +197.6% | 115.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CEHAND SERVICES LLC vs RHINO EQUITY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 7020-7001 GEN DEBRIS REMOVE ON HWY ROW | 500 CY | $20.00 | $50.00 | $18.89 | $15,000 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 175 EA | $200.00 | $120.00 | $141.37 | -$14,000 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 75 EA | $300.00 | $150.00 | $208.61 | -$11,250 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 1,000 EA | $100.00 | $110.00 | $60.77 | $10,000 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 250 EA | $150.00 | $115.00 | $100.44 | -$8,750 |
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 50.385 MI | $2,200.00 | $2,350.00 | $1,716.86 | $7,558 |
| 752-7004 STUMP REMOVAL | 25 EA | $1.00 | $250.00 | $157.73 | $6,225 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $100.00 | $200.00 | $217.57 | $5,000 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $400.00 | $200.00 | $293.05 | -$4,000 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 5 EA | $500.00 | $250.00 | $334.81 | -$1,250 |
| 752-7011 TREE REMOVAL (42" - 48" DIA) | 5 EA | $500.00 | $250.00 | $436.67 | -$1,250 |
| 752-7012 TREE REMOVAL (48" - 60" DIA) | 5 EA | $500.00 | $250.00 | $450.06 | -$1,250 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $500.00 | $250.00 | $529.99 | -$1,250 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $1.00 | $100.00 | $600.85 | $396 |
Positive: the low bidder was cheaper on that item. These 14 items account for $1,179 of the $1,179 gap.
CEHAND SERVICES LLC: unbalanced items
Placed 1RHINO EQUITY, LLC: unbalanced items
Placed 2CATOCON, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 7020-7001 GEN DEBRIS REMOVE ON HWY ROW | 500 CY | $60.00 | $18.89 | 3.18x | $20,557 |
| 505-7001 TMA (STATIONARY) | 50 DAY | $500.00 | $217.57 | 2.30x | $14,121 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $800.00 | $293.05 | 2.73x | $10,139 |
| 752-7010 TREE REMOVAL (36" - 42" DIA) | 5 EA | $1,000.00 | $334.81 | 2.99x | $3,326 |
| 752-7004 STUMP REMOVAL | 25 EA | $1.00 | $157.73 | 0.01x | -$3,918 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $1.00 | $529.99 | 0.00x | -$2,645 |
HX FARMS, INC.: unbalanced items
Placed 4WESTERN CERTIFIED ARBORISTS: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 75 EA | $750.00 | $208.61 | 3.60x | $40,604 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 175 EA | $350.00 | $141.37 | 2.48x | $36,511 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 250 EA | $225.00 | $100.44 | 2.24x | $31,140 |
| 7020-7001 GEN DEBRIS REMOVE ON HWY ROW | 500 CY | $40.00 | $18.89 | 2.12x | $10,557 |
| 752-7013 TREE REMOVAL (60" - 72" DIA) | 5 EA | $2,500.00 | $529.99 | 4.72x | $9,850 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 20 EA | $750.00 | $293.05 | 2.56x | $9,139 |
| 752-7004 STUMP REMOVAL | 25 EA | $300.00 | $157.73 | 1.90x | $3,557 |