Bid Day Forecast: 6505-42-001

Gregg · Dec 1, 2026 Sign up free
Set your company to personalize scores

Material Maintenance Project

CCSJ 6505-42-001 · lets Dec 1, 2026 · Gregg, Tyler · SL0281

$1,020,300Engineer's estimate Items at market: $1,034,035 (+1.3%)
$997,804Most likely low bid$948,189 to $1,116,286 (middle half)
1.7Expected bidders6 plan holders, 5 regular bidders
82/100Strong fit: bid itMarket only. Set your company for a personal score

Where the low bid should land

$883,804 (1 in 10 go lower)$1,234,493 (1 in 10 go higher)

From 18 comparable let jobs (district + work type, estimates of $408,120 to $2,550,750, last 3 years). 56% of them went under the estimate; the typical low bid was -2.2% vs estimate.

Bid / no-bid score

  • Competition25 / 25Jobs like this draw about 1.7 bidders.
  • Margin12 / 20Low bids land at 98% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Nov 2026 6504-49-001Smith · 1 bidders $635,290+11.6%
Nov 2026 6504-71-001Wood · 1 bidders $905,160+24.0%
Jul 2026 6501-35-001Wood · 2 bidders $2,206,460+0.6%
May 2026 6500-76-001Rusk · 2 bidders $2,302,000-4.7%
May 2026 6500-78-001Henderson · 2 bidders $1,561,000-14.5%
Nov 2025 6491-57-001Anderson · 2 bidders $1,572,500-0.1%
Jun 2025 6482-60-001Smith · 3 bidders $1,960,848-14.0%
Apr 2025 6482-15-001Anderson · 3 bidders $883,890-4.8%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn TylerAvg bid vs est.Avg win vs est.Their typical bid here
LONGVIEW BRIDGE AND ROAD, LTD. SharpestBidders 97158 of 37 3.5%-6.8% $1,055,606
SOUTHERN SOURCING SOLUTIONS, LLCBidders 100241 of 2 5.2%-9.5% $1,073,373
USA AMTECH, INC.Bidders 218 5.6%-3.1% $1,076,977
LONGVIEW ASPHALT, INC.Bidders 22154 of 7 8.2%4.0% $1,103,911
TOUCHSTONE RESOURCES, LLCBidders 4131701 of 6 11.0%0.5% $1,132,843
HARRIS TRUCKING SERVICE, LLCBidders 10 131.6% $2,363,051

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

9 of 9 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
8017-7011 SP MIXTURES SP-C PG70-22 (DEL)(SITE 1)12 low bids 5,000 TON$122.15$107.90 – $132.00 $610,75659.1%
8017-7010 SP MIXTURES SP-C PG70-22 (PICKUP)17 low bids 2,000 TON$104.70$85.25 – $118.90 $209,39620.3%
8017-7020 SP MIXTURES SP-D PG64-22 (DEL)(SITE 1)12 low bids 500 TON$115.75$102.90 – $128.90 $57,8765.6%
8017-7019 SP MIXTURES SP-D PG64-22 (PICKUP)19 low bids 500 TON$96.97$72.00 – $115.90 $48,4854.7%
8017-7013 SP MIXTURES SP-C PG70-22 (DEL)(SITE 3)11 low bids 200 TON$125.42$107.90 – $136.90 $25,0832.4%
8017-7012 SP MIXTURES SP-C PG70-22 (DEL)(SITE 2)11 low bids 200 TON$123.37$107.90 – $133.90 $24,6732.4%
8017-7022 SP MIXTURES SP-D PG64-22 (DEL)(SITE 3)11 low bids 200 TON$121.52$103.90 – $133.90 $24,3032.4%
8017-7021 SP MIXTURES SP-D PG64-22 (DEL)(SITE 2)11 low bids 200 TON$119.57$103.90 – $130.90 $23,9132.3%
8017-7001 SP MIXTURES SP-C PF64-22 (PICKUP)4 low bids 100 TON$95.50$80.00 – $114.90 $9,5500.9%