Aggregate (Seal Coat) - District Wide
6482-60-001 · let Jun 5, 2025 · Smith, Tyler · Material Maintenance Project
$1,960,848Low bid: RK HALL, LLC-14.0% vs estimate $2,279,200
$441,553Left on the table22.5% gap to the second bid
3BiddersSpread 30% low to high
26Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RK HALL, LLC | $1,960,848 | -14.0% | $441,553 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $2,402,400 | +22.5% | 5.4% | $153,709 | 3+$224,199 | 0 |
| 3 | MARTIN MARIETTA MATERIALS, INC. | $2,556,109 | +30.4% | 12.1% | 5+$423,369 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
RK HALL, LLC vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7145 AGGR (TY D GR 4)(DEL)(ST5) | 2,500 TON | $96.75 | $120.00 | $77.04 | $58,125 |
| 8000-7105 AGGR (TY B GR 4) (DEL) (ST7) | 2,100 TON | $97.25 | $120.00 | $77.59 | $47,775 |
| 8000-7099 AGGR (TY B GR 4) (DEL) (ST1) | 2,250 TON | $99.50 | $120.00 | $67.96 | $46,125 |
| 8000-7114 AGGR (TY B GR 5) (DEL) (ST2) | 1,000 TON | $79.28 | $120.00 | $67.10 | $40,720 |
| 8000-7118 AGGR (TY B GR 5) (DEL) (ST6) | 1,000 TON | $87.75 | $120.00 | $65.80 | $32,250 |
| 8000-7101 AGGR (TY B GR 4) (DEL) (ST3) | 2,170 TON | $105.25 | $120.00 | $78.78 | $32,008 |
| 8000-7100 AGGR (TY B GR 4) (DEL) (ST2) | 1,000 TON | $94.25 | $120.00 | $72.44 | $25,750 |
| 8000-7120 AGGR (TY B GR 5) (DEL) (ST8) | 500 TON | $73.75 | $120.00 | $70.82 | $23,125 |
| 8000-7106 AGGR (TY B GR 4) (DEL) (ST8) | 1,000 TON | $97.25 | $120.00 | $81.23 | $22,750 |
| 8000-7104 AGGR (TY B GR 4) (DEL) (ST6) | 1,100 TON | $102.75 | $120.00 | $81.72 | $18,975 |
| 8000-7116 AGGR (TY B GR 5) (DEL) (ST4) | 500 TON | $92.75 | $120.00 | $70.12 | $13,625 |
| 8000-7088 AGGR (TY B GR 3) (DEL) (ST4) | 1,000 TON | $107.75 | $120.00 | $92.82 | $12,250 |
| 8000-7102 AGGR (TY B GR 4) (DEL) (ST4) | 1,000 TON | $107.75 | $120.00 | $75.77 | $12,250 |
| 8000-7131 AGGR (TY D GR 3)(DEL)(ST5) | 500 TON | $96.75 | $120.00 | $96.75 | $11,625 |
| 8000-7127 AGGR (TY D GR 3)(DEL)(ST1) | 500 TON | $99.00 | $120.00 | $99.00 | $10,500 |
| 8000-7130 AGGR (TY D GR 3)(DEL)(ST4) | 500 TON | $107.75 | $120.00 | $107.75 | $6,125 |
| 8000-7144 AGGR (TY D GR 4)(DEL)(ST4) | 500 TON | $107.75 | $120.00 | $89.36 | $6,125 |
| 8000-7115 AGGR (TY B GR 5) (DEL) (ST3) | 150 TON | $90.25 | $120.00 | $66.22 | $4,463 |
| 8000-7113 AGGR (TY B GR 5) (DEL) (ST1) | 100 TON | $84.00 | $120.00 | $67.38 | $3,600 |
| 8000-7160 AGGR (TY D GR 5)(DEL)(ST6) | 100 TON | $87.25 | $120.00 | $87.25 | $3,275 |
Positive: the low bidder was cheaper on that item. These 20 items account for $431,440 of the $441,553 gap.
TOUCHSTONE RESOURCES, LLC: unbalanced items
Placed 2MARTIN MARIETTA MATERIALS, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 8000-7145 AGGR (TY D GR 4)(DEL)(ST5) | 2,500 TON | $136.57 | $77.04 | 1.77x | $148,823 |
| 8000-7099 AGGR (TY B GR 4) (DEL) (ST1) | 2,250 TON | $121.33 | $67.96 | 1.79x | $120,087 |
| 8000-7118 AGGR (TY B GR 5) (DEL) (ST6) | 1,000 TON | $131.41 | $65.80 | 2.00x | $65,613 |
| 8000-7114 AGGR (TY B GR 5) (DEL) (ST2) | 1,000 TON | $126.01 | $67.10 | 1.88x | $58,912 |
| 8000-7120 AGGR (TY B GR 5) (DEL) (ST8) | 500 TON | $130.69 | $70.82 | 1.85x | $29,935 |