MMC Superpave Hot Mix For Wood Co FY 27
6501-35-001 · let Jul 1, 2026 · Wood, Tyler · Material Maintenance Project
$2,206,460Low bid: LONGVIEW ASPHALT, INC.+0.6% vs estimate $2,194,000
$104,640Left on the table4.7% gap to the second bid
2BiddersSpread 5% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONGVIEW ASPHALT, INC. | $2,206,460 | 0.6% | $104,640 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $2,311,100 | +4.7% | 5.3% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
LONGVIEW ASPHALT, INC. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8017-7020 SP MIXTURES SP-D PG64-22 (DEL)(SITE 1) | 10,000 TON | $115.90 | $125.00 | $115.75 | $91,000 |
| 8017-7019 SP MIXTURES SP-D PG64-22 (PICKUP) | 5,000 TON | $104.90 | $110.00 | $96.97 | $25,500 |
| 8017-7001 SP MIXTURES SP-C PF64-22 (PICKUP) | 1,000 TON | $111.90 | $107.00 | $95.50 | -$4,900 |
| 8017-7010 SP MIXTURES SP-C PG70-22 (PICKUP) | 1,500 TON | $113.90 | $111.00 | $104.70 | -$4,350 |
| 8017-7012 SP MIXTURES SP-C PG70-22 (DEL)(SITE 2) | 100 TON | $133.90 | $123.00 | $123.37 | -$1,090 |
| 8017-7013 SP MIXTURES SP-C PG70-22 (DEL)(SITE 3) | 100 TON | $130.90 | $121.00 | $125.42 | -$990 |
| 8017-7021 SP MIXTURES SP-D PG64-22 (DEL)(SITE 2) | 100 TON | $125.90 | $122.00 | $119.57 | -$390 |
| 8017-7022 SP MIXTURES SP-D PG64-22 (DEL)(SITE 3) | 100 TON | $122.90 | $120.00 | $121.52 | -$290 |
| 8017-7011 SP MIXTURES SP-C PG70-22 (DEL)(SITE 1) | 1,500 TON | $125.90 | $126.00 | $122.15 | $150 |
Positive: the low bidder was cheaper on that item. These 9 items account for $104,640 of the $104,640 gap.