Bid Tab X-ray: 6501-35-001

Jul 1, 2026 · Wood Sign up free
Set your company to personalize scores

MMC Superpave Hot Mix For Wood Co FY 27

6501-35-001 · let Jul 1, 2026 · Wood, Tyler · Material Maintenance Project

$2,206,460Low bid: LONGVIEW ASPHALT, INC.+0.6% vs estimate $2,194,000
$104,640Left on the table4.7% gap to the second bid
2BiddersSpread 5% low to high
9Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1LONGVIEW ASPHALT, INC. $2,206,4600.6% $104,640 0 0
2TEXAS MATERIALS GROUP, INC. $2,311,100+4.7%5.3% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

LONGVIEW ASPHALT, INC. vs TEXAS MATERIALS GROUP, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
8017-7020 SP MIXTURES SP-D PG64-22 (DEL)(SITE 1)10,000 TON $115.90$125.00$115.75 $91,000
8017-7019 SP MIXTURES SP-D PG64-22 (PICKUP)5,000 TON $104.90$110.00$96.97 $25,500
8017-7001 SP MIXTURES SP-C PF64-22 (PICKUP)1,000 TON $111.90$107.00$95.50 -$4,900
8017-7010 SP MIXTURES SP-C PG70-22 (PICKUP)1,500 TON $113.90$111.00$104.70 -$4,350
8017-7012 SP MIXTURES SP-C PG70-22 (DEL)(SITE 2)100 TON $133.90$123.00$123.37 -$1,090
8017-7013 SP MIXTURES SP-C PG70-22 (DEL)(SITE 3)100 TON $130.90$121.00$125.42 -$990
8017-7021 SP MIXTURES SP-D PG64-22 (DEL)(SITE 2)100 TON $125.90$122.00$119.57 -$390
8017-7022 SP MIXTURES SP-D PG64-22 (DEL)(SITE 3)100 TON $122.90$120.00$121.52 -$290
8017-7011 SP MIXTURES SP-C PG70-22 (DEL)(SITE 1)1,500 TON $125.90$126.00$122.15 $150

Positive: the low bidder was cheaper on that item. These 9 items account for $104,640 of the $104,640 gap.