Bridge Maintenance
CCSJ 0913-00-140 · lets Dec 1, 2026 · De Witt, Yoakum · Various
$4,401,018Engineer's estimate
Items at market: $3,923,846 (-10.8%)
$4,119,339Most likely low bid$3,702,069 to $4,483,927 (middle half)
6.8Expected bidders10 plan holders, 10 regular bidders
40/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$4,119,339
Estimate $4,401,018
$3,452,241 (1 in 10 go lower)$4,904,941 (1 in 10 go higher)
From 72 comparable let jobs (district, estimates of $1,760,407 to $11,002,545, last 3 years). 71% of them went under the estimate; the typical low bid was -6.4% vs estimate.
Bid / no-bid score
- Competition9 / 25Jobs like this draw about 6.8 bidders.
- Margin9 / 20Low bids land at 94% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Sep 2026 | 0143-10-058Victoria · 7 bidders | $5,349,519-18.4% |
| Sep 2026 | 0913-09-134Wharton · 12 bidders | $2,677,071+14.2% |
| Aug 2026 | 0420-01-051Jackson · 3 bidders | $5,347,067-5.7% |
| Jul 2026 | 0266-04-053Colorado · 9 bidders | $4,778,226-8.2% |
| May 2026 | 0847-05-043Matagorda · 5 bidders | $5,637,915+25.8% |
| May 2026 | 1410-01-026Austin · 8 bidders | $2,587,895-6.1% |
| Apr 2026 | 0269-10-028Lavaca · 3 bidders | $2,566,089+17.8% |
| Mar 2026 | 0913-00-136De Witt · 6 bidders | $2,600,761+1.7% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Yoakum | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| THE TRUESDELL CORPORATION SharpestBidders | 36 | 6 | 0 of 1 | -0.7% | -12.8% | $4,369,676 |
| MYERS & SONS CONSTRUCTION LLCBidders | 3 | 0 | 1.4% | $4,461,761 | ||
| REAR CONTRACTORS LLCBidders | 42 | 8 | 3.2% | -25.8% | $4,541,603 | |
| GIBSON & ASSOCIATES, INC.Bidders | 107 | 21 | 1 of 2 | 5.1% | -13.7% | $4,627,624 |
| DIGG COMMERCIAL, LLCBidders | 187 | 42 | 0 of 7 | 6.8% | -5.7% | $4,699,153 |
| SCOTT TUCKER CONSTRUCTION COMPANY, LLCBidders | 75 | 8 | 7.0% | 4.0% | $4,709,593 | |
| STRUCTURAL INTEGRITY GROUP LLCBidders | 204 | 22 | 2 of 9 | 8.2% | -24.1% | $4,762,847 |
| RAGLE CONSTRUCTION, INC.Bidders | 251 | 38 | 2 of 15 | 13.0% | -5.0% | $4,972,918 |
| BLACKSMITH VENTURES LLCBidders | 136 | 21 | 0 of 4 | 13.2% | -7.1% | $4,980,160 |
| SOUTHERN ROAD & BRIDGE, LLCBidders | 62 | 4 | 0 of 4 | 51.2% | 24.3% | $6,656,430 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
67 of 71 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 439-7014 MULTI-LAYER POLYMER OVERLAY34 low bids · prices swing 10x | 27,215 SY | $40.32 | $28.00 – $275.00 | $1,097,304 | 28.0% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 13.4% |
| 439-7021 POLYESTER POLYMER CONC OVERLAY (1")6 low bids | 1,855 SY | $158.64 | $136.00 – $225.00 | $294,283 | 7.5% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 20 MO | $11,585.04 | $0.0010 – $273,686.48 | $231,701 | 5.9% |
| 483-7016 SHOT BLASTING34 low bids · prices swing 65x | 30,454 SY | $5.25 | $2.00 – $130.00 | $159,997 | 4.1% |
| 439-7017 POLYESTER POLYMER CONC OVERLAY (2")13 low bids · prices swing 3x | 661 SY | $234.43 | $151.00 – $525.10 | $154,961 | 3.9% |
| 446-7001 CLEAN & PAINT EXIST STR (SYSTEM I)3 low bids · prices swing 23x | 1 LS | $143,890.53 | $10,000.00 – $226,971.60 | $143,891 | 3.7% |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH))96 low bids · prices swing 200x | 1,450 SF | $95.74 | $5.00 – $1,000.00 | $138,828 | 3.5% |
| 439-7016 POLYESTER POLYMER CONC OVERLAY (1-1/2")3 low bids | 723 SY | $186.40 | $173.00 – $213.00 | $134,766 | 3.4% |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)110 low bids · prices swing 35x | 2,045 LF | $52.29 | $5.00 – $175.00 | $106,931 | 2.7% |
| 785-7004 BRIDGE JOINT REPAIR (ARMOR)23 low bids · prices swing 171x | 216 LF | $334.68 | $25.00 – $4,275.00 | $72,291 | 1.8% |
| 446-7007 CLEAN & PAINT EXIST PILING (SYSTEM I)4 low bids · prices swing 5x | 1 LS | $70,750.00 | $30,000.00 – $135,000.00 | $70,750 | 1.8% |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7)154 low bids · prices swing 24x | 1,808 LF | $38.57 | $9.00 – $214.00 | $69,737 | 1.8% |
| 662-7068 WK ZN PAV MRK REMOV (W)6"(SLD)225 low bids · prices swing 1,000x | 79,317 LF | $0.8015 | $0.0100 – $10.00 | $63,569 | 1.6% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 274 DAY | $217.57 | $0.0010 – $16,487.00 | $59,615 | 1.5% |