FM 1456 REHABILITATE ROADWAY HSIP 2605
1410-01-026 · let May 6, 2026 · Austin, Yoakum · Safety Improvement Projects
$2,587,895Low bid: BIG CREEK CONSTRUCTION, LTD.-6.1% vs estimate $2,755,374
$109,225Left on the table4.2% gap to the second bid
8BiddersSpread 41% low to high
59Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $2,587,895 | -6.1% | $109,225 | 0 | 4-$413,556 | |
| 2 | MATAGORDA CONSTRUCTION & MATERIALS | $2,697,120 | +4.2% | -2.1% | $21,027 | 4+$123,280 | 2-$545,116 |
| 3 | HUNTER INDUSTRIES, LTD. | $2,718,147 | +5.0% | -1.4% | $144,408 | 3+$67,934 | 5-$516,586 |
| 4 | CLARK CONSTRUCTION OF TEXAS, INC. | $2,862,555 | +10.6% | 3.9% | $109,415 | 4+$213,884 | 2-$466,688 |
| 5 | KNIFE RIVER CORPORATION - SOUTH | $2,971,971 | +14.8% | 7.9% | $154,667 | 5+$287,255 | 2-$204,991 |
| 6 | TEXAS MATERIALS GROUP, INC. | $3,126,638 | +20.8% | 13.5% | $134,499 | ||
| 7 | STX CIVIL | $3,261,137 | +26.0% | 18.4% | $398,213 | ||
| 8 | ACME BRIDGE COMPANY, INC. | $3,659,350 | +41.4% | 32.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs MATAGORDA CONSTRUCTION & MATERIALS, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $38,000.00 | $523,850.32 | -$212,000 |
| 247-7193 FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS) | 9,994 CY | $92.00 | $113.00 | $91.27 | $209,874 |
| 462-7007 CONC BOX CULV (5 FT X 3 FT) | 240 LF | $425.00 | $675.00 | $428.08 | $60,000 |
| 110-7001 EXCAV (ROADWAY) | 10,116 CY | $15.00 | $10.00 | $11.68 | -$50,580 |
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 47,863 SY | $2.50 | $1.58 | $2.25 | -$44,034 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 9,859 CY | $15.00 | $12.00 | $18.71 | -$29,577 |
| 467-7100 SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1)(C) | 8 EA | $4,000.00 | $7,600.00 | $10,052.01 | $28,800 |
| 316-7229 AGGR (TY-PE, GR-3)(SAC-B) | 473 CY | $150.00 | $205.00 | $100.41 | $26,015 |
| 462-7061 CONC BOX CULV (5 FT X 2 FT)(EXTEND) | 90 LF | $600.00 | $850.00 | $695.65 | $22,500 |
| 467-7306 SET (TY II) (18 IN) (RCP) (4: 1) (C) | 14 EA | $1,400.00 | $3,000.00 | $1,482.25 | $22,400 |
| 467-7096 SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1)(C) | 6 EA | $3,000.00 | $6,500.00 | $8,337.42 | $21,000 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 10 EA | $1,500.00 | $3,500.00 | $1,176.76 | $20,000 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 293 CY | $150.00 | $213.00 | $156.13 | $18,459 |
| 400-7010 CEM STABIL BKFL | 141 CY | $185.00 | $75.00 | $138.14 | -$15,510 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 30,290 GAL | $4.00 | $4.50 | $4.17 | $15,145 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 325 CY | $160.00 | $202.00 | $111.76 | $13,650 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 1,167 SY | $30.00 | $20.00 | $34.56 | -$11,670 |
| 275-7001 CEMENT | 359 TON | $195.00 | $176.00 | $224.93 | -$6,821 |
| 496-7001 REMOV STR (BOX CULVERT) | 1 EA | $6,000.00 | $12,000.00 | $4,831.36 | $6,000 |
| 6025-7001 TMSP RADAR SPEED CONTROL MONITOR | 2 EA | $7,000.00 | $10,000.00 | $8,404.45 | $6,000 |
Positive: the low bidder was cheaper on that item. These 20 items account for $99,651 of the $109,225 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $5,000.00 | $11,585.04 | 0.43x | -$59,265 |
| 467-7100 SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1)(C) | 8 EA | $4,000.00 | $10,052.01 | 0.40x | -$48,416 |
| 467-7096 SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1)(C) | 6 EA | $3,000.00 | $8,337.42 | 0.36x | -$32,025 |
MATAGORDA CONSTRUCTION & MATERIALS: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7229 AGGR (TY-PE, GR-3)(SAC-B) | 473 CY | $205.00 | $100.41 | 2.04x | $49,470 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 325 CY | $202.00 | $111.76 | 1.81x | $29,329 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 10 EA | $3,500.00 | $1,176.76 | 2.97x | $23,232 |
| 467-7306 SET (TY II) (18 IN) (RCP) (4: 1) (C) | 14 EA | $3,000.00 | $1,482.25 | 2.02x | $21,249 |
| 500-7001 MOBILIZATION | 1 LS | $38,000.00 | $523,850.32 | 0.07x | -$485,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $5,000.00 | $11,585.04 | 0.43x | -$59,265 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 10 EA | $3,700.00 | $1,176.76 | 3.14x | $25,232 |
| 467-7306 SET (TY II) (18 IN) (RCP) (4: 1) (C) | 14 EA | $3,200.00 | $1,482.25 | 2.16x | $24,049 |
| 464-7003 RC PIPE (CL III)(18 IN) | 153 LF | $205.00 | $83.08 | 2.47x | $18,654 |
| 500-7001 MOBILIZATION | 1 LS | $197,101.83 | $523,850.32 | 0.38x | -$326,748 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $3,759.61 | $11,585.04 | 0.32x | -$70,429 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $1,125.80 | $9,253.78 | 0.12x | -$48,768 |
| 467-7100 SET (TY I)(S= 5 FT)(HW= 4 FT)(4:1)(C) | 8 EA | $4,400.00 | $10,052.01 | 0.44x | -$45,216 |
| 467-7096 SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1)(C) | 6 EA | $4,100.00 | $8,337.42 | 0.49x | -$25,425 |
CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 462-7007 CONC BOX CULV (5 FT X 3 FT) | 240 LF | $1,058.00 | $428.08 | 2.47x | $151,181 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 22,200 LF | $2.00 | $0.6515 | 3.07x | $29,937 |
| 464-7003 RC PIPE (CL III)(18 IN) | 153 LF | $196.70 | $83.08 | 2.37x | $17,384 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 10 EA | $2,715.00 | $1,176.76 | 2.31x | $15,382 |
| 500-7001 MOBILIZATION | 1 LS | $134,500.00 | $523,850.32 | 0.26x | -$389,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $2,992.00 | $11,585.04 | 0.26x | -$77,337 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $24,393.00 | $11,585.04 | 2.11x | $115,272 |
| 462-7007 CONC BOX CULV (5 FT X 3 FT) | 240 LF | $769.00 | $428.08 | 1.80x | $81,821 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 1,167 SY | $67.00 | $34.56 | 1.94x | $37,862 |
| 316-7229 AGGR (TY-PE, GR-3)(SAC-B) | 473 CY | $179.00 | $100.41 | 1.78x | $37,172 |
| 505-7003 TMA (MOBILE OPERATION) | 20 DAY | $986.00 | $229.60 | 4.29x | $15,128 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 9,859 CY | $6.15 | $18.71 | 0.33x | -$123,859 |
| 275-7006 CEMENT TRT (EXIST MATL & NEW BASE)(6") | 47,863 SY | $0.5500 | $2.25 | 0.24x | -$81,133 |