SH 71 SAFETY IMPROVEMENT 2607
0266-04-053 · let Jul 2, 2026 · Colorado, Yoakum · Safety Improvement Projects
$4,778,226Low bid: 3LW CIVIL LLC-8.2% vs estimate $5,202,387
$404,051Left on the table8.5% gap to the second bid
9BiddersSpread 75% low to high
352Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | 3LW CIVIL LLC | $4,778,226 | -8.2% | $404,051 | 4+$160,402 | 7-$701,034 | |
| 2 | E-Z BEL CONSTRUCTION, LLC | $5,182,277 | +8.5% | -0.4% | $306,315 | 7+$470,470 | 10-$701,705 |
| 3 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $5,488,592 | +14.9% | 5.5% | $146,655 | 2+$147,738 | 3-$386,431 |
| 4 | STX CIVIL | $5,635,247 | +17.9% | 8.3% | $778,677 | 3+$220,480 | 6-$707,571 |
| 5 | Rucoba & Maya Construction, LLC | $6,413,924 | +34.2% | 23.3% | $217,045 | 8+$542,710 | 3-$390,038 |
| 6 | JOE BLAND CONSTRUCTION LLC | $6,630,969 | +38.8% | 27.5% | $1,483,974 | ||
| 7 | HUNTER INDUSTRIES, LTD. | $8,114,943 | +69.8% | 56.0% | $170,349 | ||
| 8 | ENVIRONMENTAL ALLIES, INC. | $8,285,292 | +73.4% | 59.3% | $68,696 | ||
| 9 | MB WESTERN CONSTRUCTION CO. | $8,353,988 | +74.8% | 60.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
3LW CIVIL LLC vs E-Z BEL CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 385 DAY | $169.03 | $540.00 | $217.57 | $142,823 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $56.25 | $35,000.00 | $9,253.78 | $139,775 |
| 451-7024 RETROFIT RAIL (TY SSTR) | 684 LF | $133.57 | $275.00 | $175.01 | $96,738 |
| 468-7002 THERMOPLASTIC PIPE (PP) (24") | 80 LF | $11.35 | $800.00 | $108.87 | $63,092 |
| 466-7182 WINGWALL (PW - 1) (HW=12 FT) | 2 EA | $33,563.57 | $65,000.00 | $70,863.10 | $62,873 |
| 400-7010 CEM STABIL BKFL | 366 CY | $131.79 | $300.00 | $138.14 | $61,565 |
| 468-7001 THERMOPLASTIC PIPE (PP) (18") | 80 LF | $98.79 | $800.00 | $86.05 | $56,097 |
| 480-7001 CLEAN EXIST CULVERTS | 3 EA | $20,571.70 | $3,500.00 | $1,712.97 | -$51,215 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 155 EA | $1,355.67 | $1,050.00 | $1,176.76 | -$47,379 |
| 500-7001 MOBILIZATION | 1 LS | $463,646.12 | $510,000.00 | $523,850.32 | $46,354 |
| 685-7001 INSTALL RDSD FLASH BEACON ASSEMBLY | 14 EA | $4,364.16 | $7,000.00 | $5,349.14 | $36,902 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 8 EA | $8,003.45 | $12,585.00 | $8,780.51 | $36,652 |
| 132-7017 EMBANK (VEH)(OC)(TY C) | 833 CY | $67.32 | $28.00 | $37.09 | -$32,754 |
| 400-7008 CUT & RESTORE ASPH PAVING | 216 SY | $128.09 | $250.00 | $140.13 | $26,333 |
| 618-7030 CONDT (PVC) (SCH 40) (2") | 9,135 LF | $4.42 | $7.25 | $13.17 | $25,852 |
| 462-7093 CONC BOX CULV (10 FT X 10 FT)(EXTEND) | 88 LF | $501.73 | $750.00 | $1,731.88 | $21,848 |
| 466-7146 WINGWALL (FW - 0) (HW=4 FT) | 7 EA | $7,187.64 | $4,100.00 | $11,477.14 | -$21,613 |
| 466-7145 WINGWALL (FW - 0) (HW=3 FT) | 6 EA | $6,542.48 | $3,000.00 | $9,135.97 | -$21,255 |
| 462-7057 CONC BOX CULV (3 FT X 3 FT)(EXTEND) | 80 LF | $614.85 | $350.00 | $799.74 | -$21,188 |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 133 TON | $331.25 | $175.00 | $116.75 | -$20,781 |
Positive: the low bidder was cheaper on that item. These 20 items account for $600,718 of the $404,051 gap.
3LW CIVIL LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 480-7001 CLEAN EXIST CULVERTS | 3 EA | $20,571.70 | $1,712.97 | 12.01x | $56,576 |
| 341-7001 D-GR HMA TY-B PG64-22 | 530 TON | $192.38 | $97.82 | 1.97x | $50,114 |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 133 TON | $331.25 | $116.75 | 2.84x | $28,529 |
| 132-7017 EMBANK (VEH)(OC)(TY C) | 833 CY | $67.32 | $37.09 | 1.82x | $25,183 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 18 MO | $2,263.96 | $11,585.04 | 0.20x | -$167,779 |
| 403-7001 TEMPORARY SPL SHORING | 7,865 SF | $6.78 | $25.56 | 0.27x | -$147,709 |
| 462-7093 CONC BOX CULV (10 FT X 10 FT)(EXTEND) | 88 LF | $501.73 | $1,731.88 | 0.29x | -$108,253 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 2,460 LF | $17.35 | $52.29 | 0.33x | -$85,949 |
| 618-7030 CONDT (PVC) (SCH 40) (2") | 9,135 LF | $4.42 | $13.17 | 0.34x | -$79,953 |
| 466-7182 WINGWALL (PW - 1) (HW=12 FT) | 2 EA | $33,563.57 | $70,863.10 | 0.47x | -$74,599 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $56.25 | $9,253.78 | 0.01x | -$36,790 |
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 385 DAY | $540.00 | $217.57 | 2.48x | $124,135 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $35,000.00 | $9,253.78 | 3.78x | $102,985 |
| 400-7010 CEM STABIL BKFL | 366 CY | $300.00 | $138.14 | 2.17x | $59,239 |
| 468-7001 THERMOPLASTIC PIPE (PP) (18") | 80 LF | $800.00 | $86.05 | 9.30x | $57,116 |
| 468-7002 THERMOPLASTIC PIPE (PP) (24") | 80 LF | $800.00 | $108.87 | 7.35x | $55,290 |
| 341-7001 D-GR HMA TY-B PG64-22 | 530 TON | $175.00 | $97.82 | 1.79x | $40,903 |
| 505-7003 TMA (MOBILE OPERATION) | 54 DAY | $800.00 | $229.60 | 3.48x | $30,802 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 18 MO | $2,500.00 | $11,585.04 | 0.22x | -$163,531 |
| 403-7001 TEMPORARY SPL SHORING | 7,865 SF | $5.00 | $25.56 | 0.20x | -$161,709 |
| 462-7093 CONC BOX CULV (10 FT X 10 FT)(EXTEND) | 88 LF | $750.00 | $1,731.88 | 0.43x | -$86,405 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 2,460 LF | $23.00 | $52.29 | 0.44x | -$72,050 |
| 466-7146 WINGWALL (FW - 0) (HW=4 FT) | 7 EA | $4,100.00 | $11,477.14 | 0.36x | -$51,640 |
| 467-7132 SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1)(C) | 6 EA | $5,800.00 | $12,323.87 | 0.47x | -$39,143 |
| 466-7145 WINGWALL (FW - 0) (HW=3 FT) | 6 EA | $3,000.00 | $9,135.97 | 0.33x | -$36,816 |
| 462-7057 CONC BOX CULV (3 FT X 3 FT)(EXTEND) | 80 LF | $350.00 | $799.74 | 0.44x | -$35,979 |
| 467-7332 SET (TY II) (24 IN) (TP) (6: 1) (P) | 18 EA | $1,100.00 | $2,657.95 | 0.41x | -$28,043 |
| 462-7067 CONC BOX CULV (6 FT X 4 FT)(EXTEND) | 44 LF | $480.00 | $1,079.72 | 0.44x | -$26,388 |
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $30,000.00 | $9,253.78 | 3.24x | $82,985 |
| 341-7001 D-GR HMA TY-B PG64-22 | 530 TON | $220.00 | $97.82 | 2.25x | $64,753 |
| 100-7002 PREPARING ROW | 37 STA | $1,000.00 | $6,072.92 | 0.16x | -$187,698 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 18 MO | $2,250.00 | $11,585.04 | 0.19x | -$168,031 |
| 467-7324 SET (TY II) (24 IN) (CMP) (6: 1) (P) | 27 EA | $1,000.00 | $2,137.13 | 0.47x | -$30,703 |
STX CIVIL: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 155 EA | $2,140.75 | $1,176.76 | 1.82x | $149,418 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 2,460 LF | $28.27 | $12.08 | 2.34x | $39,819 |
| 545-7002 CRASH CUSH ATTEN (MOVE & RESET) | 14 EA | $3,702.65 | $1,471.00 | 2.52x | $31,243 |
| 403-7001 TEMPORARY SPL SHORING | 7,865 SF | $1.00 | $25.56 | 0.04x | -$193,169 |
| 100-7002 PREPARING ROW | 37 STA | $1,569.32 | $6,072.92 | 0.26x | -$166,633 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 18 MO | $2,578.85 | $11,585.04 | 0.22x | -$162,111 |
| 462-7066 CONC BOX CULV (6 FT X 3 FT)(EXTEND) | 114 LF | $116.94 | $845.41 | 0.14x | -$83,045 |
| 420-7146 CL C CONC (WINGWALLS) | 59 CY | $847.70 | $2,100.77 | 0.40x | -$73,931 |
| 462-7067 CONC BOX CULV (6 FT X 4 FT)(EXTEND) | 44 LF | $427.89 | $1,079.72 | 0.40x | -$28,681 |
Rucoba & Maya Construction, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 155 EA | $2,200.00 | $1,176.76 | 1.87x | $158,602 |
| 618-7030 CONDT (PVC) (SCH 40) (2") | 9,135 LF | $24.49 | $13.17 | 1.86x | $103,386 |
| 341-7001 D-GR HMA TY-B PG64-22 | 530 TON | $215.00 | $97.82 | 2.20x | $62,103 |
| 505-7003 TMA (MOBILE OPERATION) | 54 DAY | $1,200.00 | $229.60 | 5.23x | $52,402 |
| 533-7005 FILL MILLED ASPH RUMBLE STRIPS (SHLDR) | 5,860 LF | $11.80 | $3.00 | 3.93x | $51,540 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $20,000.00 | $9,253.78 | 2.16x | $42,985 |
| 464-7062 RC PIPE (ELLIP)(CL III)(DES 5) | 104 LF | $690.00 | $329.84 | 2.09x | $37,457 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 2,460 LF | $26.00 | $12.08 | 2.15x | $34,235 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 18 MO | $1,350.00 | $11,585.04 | 0.12x | -$184,231 |
| 100-7002 PREPARING ROW | 37 STA | $1,790.00 | $6,072.92 | 0.29x | -$158,468 |
| 462-7057 CONC BOX CULV (3 FT X 3 FT)(EXTEND) | 80 LF | $208.00 | $799.74 | 0.26x | -$47,339 |