Intersection & Operational Imprv
CCSJ 0252-01-084 · lets Dec 1, 2026 · Burnet, Austin · US 281 · Intersection Improvement
$6,953,263Engineer's estimate
Items at market: $2,327,584 (-66.5%)
$6,076,116Most likely low bid$5,423,640 to $6,612,968 (middle half)
5.6Expected bidders10 plan holders, 10 regular bidders
42/100Weak fitMarket only. Set your company for a personal score
Where the low bid should land
$6,076,116
Estimate $6,953,263
$4,944,048 (1 in 10 go lower)$7,182,346 (1 in 10 go higher)
From 60 comparable let jobs (district, estimates of $2,781,305 to $17,383,158, last 3 years). 82% of them went under the estimate; the typical low bid was -12.6% vs estimate.
Bid / no-bid score
- Competition14 / 25Jobs like this draw about 5.6 bidders.
- Margin5 / 20Low bids land at 87% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 0016-03-125Hays · 6 bidders | $2,797,454-12.2% |
| Sep 2026 | 0573-02-008Caldwell · 8 bidders | $5,111,478-5.9% |
| Sep 2026 | 6496-52-001Blanco · 4 bidders | $2,803,000+0.8% |
| Aug 2026 | 1197-01-027Hays · 7 bidders | $3,441,590+9.9% |
| Aug 2026 | 0114-02-112Travis · 6 bidders | $8,579,439+8.2% |
| Jul 2026 | 0914-04-377Travis · 6 bidders | $7,779,122-52.3% |
| Jul 2026 | 0015-09-208Williamson · 5 bidders | $2,920,576-5.2% |
| Jun 2026 | 0337-01-053Williamson · 6 bidders | $7,574,102+3.3% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Austin | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| HUNTER INDUSTRIES, LTD. SharpestBidders | 240 | 66 | 12 of 69 | -1.0% | -9.3% | $6,886,658 |
| TEXAS MATERIALS GROUP, INC.Bidders | 710 | 181 | 12 of 74 | 3.6% | -3.6% | $7,206,403 |
| DAN WILLIAMS COMPANYBidders | 108 | 31 | 11 of 35 | 4.1% | -6.8% | $7,238,535 |
| STX CIVILBidders | 225 | 32 | 3 of 12 | 5.4% | -3.5% | $7,326,455 |
| DIGG COMMERCIAL, LLCBidders | 187 | 42 | 4 of 23 | 6.8% | -5.7% | $7,424,294 |
| E-Z BEL CONSTRUCTION, LLCBidders | 186 | 39 | 8 of 35 | 7.1% | -2.4% | $7,445,083 |
| STRUCTURAL INTEGRITY GROUP LLCBidders | 204 | 22 | 3 of 16 | 8.2% | -24.1% | $7,524,926 |
| AARON CONCRETE CONTRACTORS, LLCBidders | 39 | 3 | 3 of 37 | 11.7% | -24.5% | $7,769,128 |
| JOE BLAND CONSTRUCTION LLCBidders | 34 | 2 | 2 of 18 | 14.7% | -8.5% | $7,976,839 |
| Lumin8 Transportation Technologies, LLCBidders | 18 | 1 | 1 of 6 | 26.7% | -7.5% | $8,813,158 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
144 of 153 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 22.5% |
| 530-7007 DRIVEWAYS (CONC) (HES)79 low bids · prices swing 12x | 1,103 SY | $122.10 | $32.00 – $395.00 | $134,675 | 5.8% |
| 105-7014 RMV (14"-18") TRT/UNTRT BASE & ASPH PAV12 low bids · prices swing 9x | 12,473 SY | $9.39 | $3.75 – $35.00 | $117,091 | 5.0% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 10 MO | $11,585.04 | $0.0010 – $273,686.48 | $115,850 | 5.0% |
| 100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x | 17.34 STA | $6,072.92 | $0.0100 – $861,170.00 | $105,304 | 4.5% |
| 508-7001 CONSTRUCTING DETOURS174 low bids · prices swing 79x | 1,221 SY | $83.58 | $3.80 – $300.00 | $102,057 | 4.4% |
| 360-7004 CONC PVMT (CRCP) (10")29 low bids · prices swing 6x | 979 SY | $87.39 | $60.00 – $381.63 | $85,550 | 3.7% |
| 531-7002 CONC SIDEWALKS (5")87 low bids · prices swing 87x | 1,128 SY | $68.80 | $11.51 – $1,000.00 | $77,609 | 3.3% |
| 462-7085 CONC BOX CULV (9 FT X 8 FT)(EXTEND)2 low bids | 58 LF | $1,335.71 | $1,300.00 – $1,400.00 | $77,471 | 3.3% |
| 466-7181 WINGWALL (PW - 1) (HW=11 FT)21 low bids · prices swing 7x | 1 EA | $55,052.17 | $22,000.00 – $154,000.00 | $55,052 | 2.4% |
| 464-7003 RC PIPE (CL III)(18 IN)318 low bids · prices swing 13x | 662 LF | $83.08 | $36.17 – $475.00 | $55,000 | 2.4% |
| 529-7009 CONC CURB & GUTTER (TY II)233 low bids · prices swing 50x | 1,249 LF | $32.57 | $5.22 – $261.28 | $40,678 | 1.7% |
| 686-7059 INS TRF SIG PL AM(S)1 ARM(55')LUM55 low bids | 1 EA | $37,709.54 | $25,000.00 – $55,754.26 | $37,710 | 1.6% |
| 686-7055 INS TRF SIG PL AM(S)1 ARM(50')LUM41 low bids | 1 EA | $36,603.13 | $24,918.48 – $58,000.00 | $36,603 | 1.6% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 162 DAY | $217.57 | $0.0010 – $16,487.00 | $35,247 | 1.5% |