RM 150 - SE of Darden Hill to RM 1826
1197-01-027 · let Aug 6, 2026 · Hays, Austin · Safety Improvement Projects
$3,441,590Low bid: STX CIVIL+9.9% vs estimate $3,130,181
$5,752Left on the table0.2% gap to the second bid
7BiddersSpread 34% low to high
86Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | STX CIVIL | $3,441,590 | 9.9% | $5,752 | 1+$65,102 | 4-$1,088,860 | |
| 2 | HUNTER INDUSTRIES, LTD. | $3,447,342 | +0.2% | 10.1% | $115,132 | 4+$241,368 | 3-$950,828 |
| 3 | D&S CONCRETE CONTRACTORS LLC | $3,562,474 | +3.5% | 13.8% | $198,459 | 3+$156,727 | 9-$1,277,751 |
| 4 | TEXAS MATERIALS GROUP, INC. | $3,760,934 | +9.3% | 20.2% | $150,391 | 3+$267,496 | 3-$496,422 |
| 5 | D & D CONTRACTORS, INC. | $3,911,325 | +13.6% | 25.0% | $496,085 | 1+$26,028 | 5-$1,173,151 |
| 6 | AARON CONCRETE CONTRACTORS, LLC | $4,407,410 | +28.1% | 40.8% | $187,630 | ||
| 7 | JOE BLAND CONSTRUCTION LLC | $4,595,040 | +33.5% | 46.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
STX CIVIL vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 9,098 CY | $9.31 | $25.30 | $11.68 | $145,477 |
| 347-7002 TOM-C PG76-22 SAC-B | 2,096 TON | $188.26 | $131.76 | $130.62 | -$118,424 |
| 341-7001 D-GR HMA TY-B PG64-22 | 2,590 TON | $126.80 | $97.21 | $97.82 | -$76,638 |
| 400-7006 CUT & RESTORING PAV | 319 SY | $102.90 | $322.31 | $171.81 | $69,992 |
| 500-7001 MOBILIZATION | 1 LS | $176,324.31 | $239,056.15 | $523,850.32 | $62,732 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 28,174 SY | $3.74 | $1.91 | $1.43 | -$51,558 |
| 508-7001 CONSTRUCTING DETOURS | 2,045 SY | $67.25 | $42.28 | $83.58 | -$51,064 |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 3,679 CY | $80.09 | $66.97 | $63.96 | -$48,268 |
| 464-7005 RC PIPE (CL III)(24 IN) | 70 LF | $117.39 | $643.04 | $108.34 | $36,796 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 3,573 CY | $15.35 | $25.30 | $16.96 | $35,551 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $2,184.60 | $3,780.05 | $11,585.04 | $35,100 |
| 464-7009 RC PIPE (CL III)(36 IN) | 110 LF | $204.77 | $474.67 | $183.45 | $29,689 |
| 341-7056 D-GR HMA TY-D PG76-22 | 1,317 TON | $128.62 | $106.47 | $123.11 | -$29,172 |
| 464-7043 RC PIPE (ARCH)(CL III)(DES 4) | 132 LF | $335.36 | $514.58 | $356.96 | $23,657 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 7 EA | $311.52 | $3,670.32 | $3,190.07 | $23,512 |
| 100-7002 PREPARING ROW | 97 STA | $770.09 | $976.80 | $6,072.92 | $20,051 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $7,497.52 | $17,052.03 | $9,253.78 | $19,109 |
| 467-7434 SET (TY II) (DES 3) (RCP) (6: 1) (P) | 10 EA | $4,087.87 | $2,310.36 | $4,091.82 | -$17,775 |
| 169-7006 SOIL RET BLKT(SL_STEEP_CLAY_LONG) | 28,174 SY | $1.37 | $0.8900 | $1.40 | -$13,524 |
| 530-7006 DRIVEWAYS (CONC) | 765 SY | $130.51 | $113.42 | $109.20 | -$13,074 |
Positive: the low bidder was cheaper on that item. These 20 items account for $82,168 of the $5,752 gap.
STX CIVIL: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 28,174 SY | $3.74 | $1.43 | 2.62x | $65,102 |
| 100-7002 PREPARING ROW | 97 STA | $770.09 | $6,072.92 | 0.13x | -$514,375 |
| 500-7001 MOBILIZATION | 1 LS | $176,324.31 | $523,850.32 | 0.34x | -$347,526 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $2,184.60 | $11,585.04 | 0.19x | -$206,810 |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 7 EA | $311.52 | $3,190.07 | 0.10x | -$20,150 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 9,098 CY | $25.30 | $11.68 | 2.17x | $123,895 |
| 400-7006 CUT & RESTORING PAV | 319 SY | $322.31 | $171.81 | 1.88x | $48,010 |
| 464-7005 RC PIPE (CL III)(24 IN) | 70 LF | $643.04 | $108.34 | 5.94x | $37,429 |
| 464-7009 RC PIPE (CL III)(36 IN) | 110 LF | $474.67 | $183.45 | 2.59x | $32,035 |
| 100-7002 PREPARING ROW | 97 STA | $976.80 | $6,072.92 | 0.16x | -$494,324 |
| 500-7001 MOBILIZATION | 1 LS | $239,056.15 | $523,850.32 | 0.46x | -$284,794 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $3,780.05 | $11,585.04 | 0.33x | -$171,710 |
D&S CONCRETE CONTRACTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 9,098 CY | $23.00 | $11.68 | 1.97x | $102,969 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 1,475 SY | $40.00 | $19.70 | 2.03x | $29,939 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 18 EA | $2,500.00 | $1,176.76 | 2.12x | $23,818 |
| 100-7002 PREPARING ROW | 97 STA | $500.00 | $6,072.92 | 0.08x | -$540,573 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $4,000.00 | $11,585.04 | 0.35x | -$166,871 |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 3,679 CY | $29.00 | $63.96 | 0.45x | -$128,633 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 28,174 SY | $0.5000 | $1.43 | 0.35x | -$26,182 |
| 496-7007 REMOV STR (PIPE) | 1,298 LF | $5.00 | $23.96 | 0.21x | -$24,614 |
| 466-7176 WINGWALL (PW - 1) (HW=6 FT) | 1 EA | $5,000.00 | $29,518.27 | 0.17x | -$24,518 |
| 530-7018 TURNOUTS (ACP) | 507 SY | $36.00 | $82.59 | 0.44x | -$23,623 |
| 466-7175 WINGWALL (PW - 1) (HW=5 FT) | 1 EA | $4,500.00 | $23,385.57 | 0.19x | -$18,886 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 9,098 CY | $32.00 | $11.68 | 2.74x | $184,851 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 28,174 SY | $3.30 | $1.43 | 2.31x | $52,705 |
| 104-7011 REMOV CONC (DRIVEWAYS) | 1,475 SY | $40.00 | $19.70 | 2.03x | $29,939 |
| 100-7002 PREPARING ROW | 97 STA | $1,400.00 | $6,072.92 | 0.23x | -$453,273 |
| 467-7434 SET (TY II) (DES 3) (RCP) (6: 1) (P) | 10 EA | $1,849.00 | $4,091.82 | 0.45x | -$22,428 |
| 496-7007 REMOV STR (PIPE) | 1,298 LF | $8.00 | $23.96 | 0.33x | -$20,720 |
D & D CONTRACTORS, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 467-7448 SET (TY II) (DES 5) (RCP) (4: 1) (C) | 2 EA | $23,018.66 | $10,004.87 | 2.30x | $26,028 |
| 100-7002 PREPARING ROW | 97 STA | $772.57 | $6,072.92 | 0.13x | -$514,134 |
| 500-7001 MOBILIZATION | 1 LS | $106,704.15 | $523,850.32 | 0.20x | -$417,146 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 22 MO | $3,606.50 | $11,585.04 | 0.31x | -$175,528 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 3,573 CY | $6.36 | $16.96 | 0.37x | -$37,886 |
| 467-7434 SET (TY II) (DES 3) (RCP) (6: 1) (P) | 10 EA | $1,246.11 | $4,091.82 | 0.30x | -$28,457 |