CapEx-C Power to Pump
0914-04-377 · let Jul 2, 2026 · Travis, Austin · Transportation Non-Roadway
$7,779,122Low bid: TEXAS ROAD LLC-52.3% vs estimate $16,306,479
$7,841,466Left on the table100.8% gap to the second bid
6BiddersSpread 206% low to high
114Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS ROAD LLC | $7,779,122 | -52.3% | $7,841,466 | 1+$123,597 | 1-$46,216 | |
| 2 | E-Z BEL CONSTRUCTION, LLC | $15,620,588 | +100.8% | -4.2% | $270,446 | 5+$6,894,843 | 0 |
| 3 | JAY-REESE CONTRACTORS, INC. | $15,891,035 | +104.3% | -2.5% | $3,670,006 | 8+$7,897,710 | 1-$562,567 |
| 4 | JOE BLAND CONSTRUCTION LLC | $19,561,041 | +151.5% | 20.0% | $2,585,318 | 2+$9,817,974 | 1-$372,167 |
| 5 | ZACHRY CONSTRUCTION CORPORATION | $22,146,359 | +184.7% | 35.8% | $1,680,705 | 8+$13,710,494 | 0 |
| 6 | WEBBER, LLC | $23,827,063 | +206.3% | 46.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TEXAS ROAD LLC vs E-Z BEL CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 6159-7001 DUCT BANK (CONC ENCASE) (TRENCH) | 9,485 LF | $248.00 | $678.00 | $248.00 | $4,078,550 |
| 6159-7002 DUCT BANK (STL ENCASE) (BORE) | 1,413 LF | $1,200.00 | $2,350.00 | $1,200.00 | $1,624,950 |
| 500-7001 MOBILIZATION | 1 LS | $700,000.00 | $1,500,000.00 | $523,850.32 | $800,000 |
| 6159-7003 MANHOLE (6’X12’) (ALL DEPTHS) | 35 EA | $30,000.00 | $50,000.00 | $30,000.00 | $700,000 |
| 100-7002 PREPARING ROW | 112 STA | $3,200.00 | $5,500.00 | $6,072.92 | $257,600 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,740 LF | $17.00 | $105.00 | $43.56 | $153,120 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 23,692 SY | $1.00 | $6.00 | $1.43 | $118,460 |
| 347-7002 TOM-C PG76-22 SAC-B | 1,130 TON | $240.00 | $189.00 | $130.62 | -$57,630 |
| 341-7069 D-GR HMA TY-D PG70-22 (EXEMPT) | 1,100 TON | $260.00 | $208.00 | $245.63 | -$57,200 |
| 341-7003 D-GR HMA TY-B PG64-22 (EXEMPT) | 393 TON | $150.00 | $270.00 | $127.48 | $47,160 |
| 341-7040 D-GR HMA TY-C PG76-22 (EXEMPT) | 314 TON | $150.00 | $290.00 | $158.71 | $43,960 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 9,493 LF | $4.50 | $0.0100 | $5.96 | -$42,624 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $13,000.00 | $22,800.00 | $9,253.78 | $39,200 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 1,740 LF | $6.50 | $24.00 | $11.18 | $30,450 |
| 505-7003 TMA (MOBILE OPERATION) | 45 DAY | $80.00 | $750.00 | $229.60 | $30,150 |
| 432-7001 RIPRAP (CONC)(4 IN) | 113 CY | $540.00 | $780.00 | $573.24 | $27,120 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 6,547 SY | $38.00 | $35.00 | $35.01 | -$19,641 |
| 512-7033 PORT CTB (MOVE)(LOW PROF)(TY 1) | 2,060 LF | $10.00 | $19.00 | $8.08 | $18,540 |
| 164-7004 BROADCAST SEED (PERM_URBAN_CLAY) | 23,692 SY | $0.2500 | $1.00 | $0.5051 | $17,769 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $7,300.00 | $6,000.00 | $11,585.04 | -$15,600 |
Positive: the low bidder was cheaper on that item. These 20 items account for $7,794,334 of the $7,841,466 gap.
TEXAS ROAD LLC: unbalanced items
Placed 1E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6159-7001 DUCT BANK (CONC ENCASE) (TRENCH) | 9,485 LF | $678.00 | $248.00 | 2.73x | $4,078,550 |
| 6159-7002 DUCT BANK (STL ENCASE) (BORE) | 1,413 LF | $2,350.00 | $1,200.00 | 1.96x | $1,624,950 |
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $523,850.32 | 2.86x | $976,150 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 23,692 SY | $6.00 | $1.43 | 4.20x | $108,289 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,740 LF | $105.00 | $43.56 | 2.41x | $106,904 |
JAY-REESE CONTRACTORS, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6159-7001 DUCT BANK (CONC ENCASE) (TRENCH) | 9,485 LF | $750.00 | $248.00 | 3.02x | $4,761,470 |
| 6159-7002 DUCT BANK (STL ENCASE) (BORE) | 1,413 LF | $2,150.00 | $1,200.00 | 1.79x | $1,342,350 |
| 500-7001 MOBILIZATION | 1 LS | $1,400,000.00 | $523,850.32 | 2.67x | $876,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $32,750.00 | $11,585.04 | 2.83x | $253,979 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 6,547 SY | $70.00 | $35.01 | 2.00x | $229,047 |
| 402-7001 TRENCH EXCAVATION PROTECTION | 9,493 LF | $30.00 | $5.96 | 5.03x | $228,220 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 23,692 SY | $6.00 | $1.43 | 4.20x | $108,289 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 1,740 LF | $100.00 | $43.56 | 2.30x | $98,204 |
| 100-7002 PREPARING ROW | 112 STA | $1,050.00 | $6,072.92 | 0.17x | -$562,567 |
JOE BLAND CONSTRUCTION LLC: unbalanced items
Placed 4ZACHRY CONSTRUCTION CORPORATION: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 6159-7001 DUCT BANK (CONC ENCASE) (TRENCH) | 9,485 LF | $955.38 | $248.00 | 3.85x | $6,709,499 |
| 6159-7002 DUCT BANK (STL ENCASE) (BORE) | 1,413 LF | $2,962.32 | $1,200.00 | 2.47x | $2,490,158 |
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $523,850.32 | 3.82x | $1,476,150 |
| 100-7002 PREPARING ROW | 112 STA | $17,500.00 | $6,072.92 | 2.88x | $1,279,833 |
| 6159-7003 MANHOLE (6’X12’) (ALL DEPTHS) | 35 EA | $60,870.06 | $30,000.00 | 2.03x | $1,080,452 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 6,547 SY | $87.60 | $35.01 | 2.50x | $344,275 |
| 347-7002 TOM-C PG76-22 SAC-B | 1,130 TON | $280.31 | $130.62 | 2.15x | $169,148 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 12 MO | $25,000.00 | $11,585.04 | 2.16x | $160,979 |