IH 35SB FROM INNER LP TO WESTINGHOUSE RD
0015-09-208 · let Jul 1, 2026 · Williamson, Austin · Safety Improvement Projects
$2,920,576Low bid: DAN WILLIAMS COMPANY-5.2% vs estimate $3,081,166
$105,758Left on the table3.6% gap to the second bid
5BiddersSpread 53% low to high
74Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DAN WILLIAMS COMPANY | $2,920,576 | -5.2% | $105,758 | 2+$38,662 | 4-$750,429 | |
| 2 | HUNTER INDUSTRIES, LTD. | $3,026,334 | +3.6% | -1.8% | $413,942 | 1+$24,960 | 2-$703,225 |
| 3 | JORDAN FOSTER CONSTRUCTION, LLC | $3,440,276 | +17.8% | 11.7% | $428,825 | 1+$20,292 | 2-$302,969 |
| 4 | TEXAS MATERIALS GROUP, INC. | $3,869,101 | +32.5% | 25.6% | $613,797 | 3+$200,338 | 3-$593,784 |
| 5 | AARON CONCRETE CONTRACTORS, LLC | $4,482,897 | +53.5% | 45.5% | 5+$842,172 | 3-$838,783 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DAN WILLIAMS COMPANY vs HUNTER INDUSTRIES, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 4,337 CY | $48.00 | $66.73 | $63.96 | $81,232 |
| 650-7031 INS OH SN SUP(30 FT CANT)(CIRC TUBE) | 2 EA | $125,000.00 | $109,106.59 | $108,443.29 | -$31,787 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 8,440 LF | $7.50 | $10.50 | $12.08 | $25,320 |
| 505-7003 TMA (MOBILE OPERATION) | 68 DAY | $1.00 | $312.98 | $229.60 | $21,215 |
| 500-7001 MOBILIZATION | 1 LS | $285,000.00 | $264,265.17 | $523,850.32 | -$20,735 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 8,440 LF | $22.00 | $24.00 | $52.29 | $16,880 |
| 505-7001 TMA (STATIONARY) | 174 DAY | $80.00 | $156.49 | $217.57 | $13,309 |
| 341-7065 D-GR HMA TY-D PG 76-22 (EXEMPT) | 1,228 TON | $115.00 | $104.38 | $111.42 | -$13,041 |
| 342-7001 PFC-C PG76-22 SAC-A | 1,837 TON | $168.00 | $161.62 | $170.34 | -$11,720 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $8,000.00 | $9,318.79 | $11,585.04 | $9,232 |
| 100-7002 PREPARING ROW | 82.44 STA | $550.00 | $438.91 | $6,072.92 | -$9,158 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $8,500.00 | $4,173.02 | $9,253.78 | -$8,654 |
| 466-7194 WINGWALL (PW - 2) (HW=10 FT) | 1 EA | $41,500.00 | $50,000.00 | $54,085.10 | $8,500 |
| 169-7002 SOIL RET BLKT(SL_MOD_CLAY_LONG) | 23,197 SY | $0.9000 | $1.26 | $1.49 | $8,351 |
| 168-7001 VEGETATIVE WATERING | 390 TGL | $10.00 | $26.24 | $8.43 | $6,334 |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 8,220 LF | $3.75 | $3.15 | $3.92 | -$4,932 |
| 658-7012 INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB | 427 EA | $11.00 | $22.00 | $9.89 | $4,697 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 9,265 SY | $1.75 | $2.20 | $2.24 | $4,169 |
| 3006-7001 UNDERSEAL COURSE | 4,083 GAL | $3.75 | $4.54 | $3.65 | $3,226 |
| 310-7013 PRIME COAT(MC-30 OR AE-P) | 2,230 GAL | $3.65 | $4.76 | $4.73 | $2,475 |
Positive: the low bidder was cheaper on that item. These 20 items account for $104,912 of the $105,758 gap.
DAN WILLIAMS COMPANY: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7008 DRILL SHAFT (48 IN) | 58 LF | $800.00 | $400.14 | 2.00x | $23,192 |
| 647-7002 RELOCATE LRSA | 3 EA | $7,500.00 | $2,343.24 | 3.20x | $15,470 |
| 100-7002 PREPARING ROW | 82.44 STA | $550.00 | $6,072.92 | 0.09x | -$455,310 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 8,440 LF | $22.00 | $52.29 | 0.42x | -$255,637 |
| 505-7001 TMA (STATIONARY) | 174 DAY | $80.00 | $217.57 | 0.37x | -$23,937 |
| 505-7003 TMA (MOBILE OPERATION) | 68 DAY | $1.00 | $229.60 | 0.00x | -$15,545 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 2JORDAN FOSTER CONSTRUCTION, LLC: unbalanced items
Placed 3TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 8,440 LF | $28.90 | $12.08 | 2.39x | $141,932 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 9,265 SY | $6.00 | $2.24 | 2.68x | $34,866 |
| 416-7008 DRILL SHAFT (48 IN) | 58 LF | $806.00 | $400.14 | 2.01x | $23,540 |
| 100-7002 PREPARING ROW | 82.44 STA | $169.00 | $6,072.92 | 0.03x | -$486,719 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,400.00 | $11,585.04 | 0.12x | -$71,295 |
| 505-7001 TMA (STATIONARY) | 174 DAY | $12.00 | $217.57 | 0.06x | -$35,769 |
AARON CONCRETE CONTRACTORS, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 8,440 LF | $100.00 | $52.29 | 1.91x | $402,683 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 6,217 CY | $47.00 | $13.19 | 3.56x | $210,185 |
| 110-7001 EXCAV (ROADWAY) | 8,216 CY | $31.00 | $11.68 | 2.65x | $158,715 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 23,197 SY | $3.00 | $1.43 | 2.10x | $36,436 |
| 416-7008 DRILL SHAFT (48 IN) | 58 LF | $989.00 | $400.14 | 2.47x | $34,154 |
| 100-7002 PREPARING ROW | 82.44 STA | $160.00 | $6,072.92 | 0.03x | -$487,461 |
| 500-7001 MOBILIZATION | 1 LS | $241,493.00 | $523,850.32 | 0.46x | -$282,357 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $1,733.00 | $11,585.04 | 0.15x | -$68,964 |