| 1 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 200 | LF |
$0.3500 |
$3.30 |
$3.27 |
| 2 | 859(A) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 100 | LF |
$0.1000 |
$1.10 |
$1.09 |
| 3 | 876(C) 8482 |
(PL)TRUCK MOUNTED ATTENUATOR | 150 | SD |
$30.00 |
$90.00 |
$92.73 |
| 4 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 150 | SD |
$5.00 |
$11.00 |
$10.91 |
| 5 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 13,650 | SD |
$0.0500 |
$0.3000 |
$0.2700 |
| 6 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 4,500 | SD |
$0.7500 |
$0.8000 |
$0.8200 |
| 7 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 7,500 | SD |
$1.25 |
$0.8000 |
$0.8200 |
| 8 | 880(C) 8842 |
BARRICADES(TYPE III) | 4,500 | SD |
$0.1000 |
$0.3000 |
$0.2700 |
| 9 | 880(C) 8848 |
WING BARRICADES | 1,200 | SD |
$0.7500 |
$2.20 |
$2.18 |
| 10 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 13,500 | SD |
$0.0500 |
$0.1100 |
$0.1100 |
| 11 | 880(E) 8872 |
WARNING LIGHTS(TYPE C) | 64,500 | SD |
$0.0500 |
$0.0100 |
$0.0100 |
| 12 | 880(F) 8878 |
DRUMS | 4,500 | SD |
$0.0500 |
$0.5500 |
$0.5500 |
| 13 | 880(G) 8890 |
CHANNELIZER CONES | 60,000 | SD |
$0.0100 |
$0.2200 |
$0.2200 |
| 14 | 880(L) 8911 |
TRAFFIC SURVEILLANCE, POLICE | 180 | HOUR |
$55.00 |
$35.00 |
$64.80 |
| 15 | 882(B) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 600 | SD |
$15.00 |
$22.00 |
$21.82 |
| 16 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 2,435 | CY |
$7.15 |
$10.00 |
$92.94 |
| 17 | 202(C) 0184 |
UNCLASSIFIED BORROW | 7,694 | CY |
$7.25 |
$12.00 |
$31.96 |
| 18 | 223 2801 |
TEMPORARY SILT FENCE | 1,150 | LF |
$2.00 |
$2.00 |
$3.95 |
| 19 | 224 2803 |
TEMPORARY SEDIMENT FILTER | 19 | EA |
$150.00 |
$150.00 |
$196.58 |
| 20 | 227 0100 |
TEMPORARY SILT DIKE | 1,190 | LF |
$7.50 |
$7.00 |
$6.41 |
| 21 | 230(A) 2806 |
SOLID SLAB SODDING | 274,563 | SY |
$1.75 |
$1.25 |
$1.22 |
| 22 | 411(S4) 5960 |
(SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 4,332 | TON |
$75.00 |
$75.00 |
$80.47 |
| 23 | 509(A) 0319 |
CLASS AA CONCRETE | 443 | CY |
$315.00 |
$110.00 |
$272.75 |
| 24 | 509(D) 0325 |
CLASS C CONCRETE | 510 | CY |
$295.00 |
$250.00 |
$307.82 |
| 25 | 612(E) 0645 |
INLETS ADJUST TO GRADE | 17 | EA |
$1,500.00 |
$3,000.00 |
$1,566.11 |
| 26 | 619(B) 5881 |
REMOVAL OF CONCRETE DITCH LINER | 9,073 | LF |
$2.75 |
$5.00 |
$5.18 |
| 27 | 619(C) 0924 |
SAWING PAVEMENT | 500 | LF |
$2.50 |
$2.00 |
$3.34 |
| 28 | 628 5110 |
(PL)CABLE END ANCHOR UNIT | 48 | EA |
$1,250.00 |
$2,200.00 |
$1,200.08 |
| 29 | 628 5125 |
HIGH-TENSION CABLE BARRIER(TL-4) | 31,643 | LF |
$10.50 |
$11.00 |
$10.91 |
| 30 | 628 5175 |
CABLE BARRIER TENSION METER | 1 | EA |
$2,500.00 |
$2,500.00 |
$2,181.96 |
| 31 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 22,526 | CY |
$8.00 |
$3.00 |
$24.10 |
| 32 | 202(C) 0184 |
UNCLASSIFIED BORROW | 25,649 | CY |
$8.00 |
$3.00 |
$32.46 |
| 33 | 205 4229 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$93,500.00 |
$95,000.00 |
$361,209.71 |
| 34 | 223 2801 |
TEMPORARY SILT FENCE | 2,000 | LF |
$2.50 |
$2.00 |
$3.45 |
| 35 | 227 0100 |
TEMPORARY SILT DIKE | 1,463 | LF |
$8.00 |
$7.00 |
$6.41 |
| 36 | 230(A) 2806 |
SOLID SLAB SODDING | 57,459 | SY |
$1.50 |
$1.25 |
$1.22 |
| 37 | 232(B) 2814 |
SEEDING METHOD B | 11.97 | AC |
$550.00 |
$450.00 |
$459.03 |
| 38 | 233(A) 2817 |
VEGETATIVE MULCHING | 11.97 | AC |
$500.00 |
$450.00 |
$459.03 |
| 39 | 241 2832 |
MOWING | 54.4 | AC |
$60.00 |
$50.00 |
$52.92 |
| 40 | 303 0192 |
AGGREGATE BASE | 3,780 | CY |
$40.00 |
$45.00 |
$47.58 |
| 41 | 325 5271 |
SEPARATOR FABRIC | 41,312 | SY |
$1.40 |
$1.00 |
$1.90 |
| 42 | 327(D) 4230 |
(SP)LIME | 596 | TON |
$170.00 |
$150.00 |
$172.23 |
| 43 | 327(H) 4270 |
(SP)LIME STABILIZED SUBGRADE | 41,312 | SY |
$2.00 |
$2.00 |
$5.34 |
| 44 | 403(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 1,650 | TON |
$23.00 |
$20.00 |
$23.84 |
| 45 | 407 0250 |
TACK COAT | 5,131 | GAL |
$3.00 |
$2.00 |
$2.28 |
| 46 | 408 5774 |
PRIME COAT | 10,833 | GAL |
$4.50 |
$3.00 |
$4.53 |
| 47 | 411(S3) 5945 |
(SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | 16,246 | TON |
$50.00 |
$61.00 |
$63.06 |
| 48 | 411(S4) 5960 |
(SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 5,814 | TON |
$60.00 |
$71.00 |
$75.45 |
| 49 | 413(A) 4861 |
RUMBLE STRIP-METHOD AC-CON | 220,170 | LF |
$0.1500 |
$0.0700 |
$0.1900 |
| 50 | 509(D) 0325 |
CLASS C CONCRETE | 180 | CY |
$300.00 |
$250.00 |
$307.82 |
| 51 | 611(E) 6002 |
INLET (SMD-TYPE 2) | 26 | EA |
$2,000.00 |
$2,200.00 |
$1,593.11 |
| 52 | 611(F) 5196 |
ADDITIONAL DEPTH IN INLET | 7.12 | VF |
$400.00 |
$300.00 |
$162.01 |
| 53 | 613(CC) 7196 |
TYPE A6 CULVERT END TREATMENT | 2 | EA |
$1,000.00 |
$1,000.00 |
$2,149.35 |
| 54 | 613(CC) 7197 |
TYPE B6 CULVERT END TREATMENT | 1 | EA |
$1,000.00 |
$1,200.00 |
$2,257.36 |
| 55 | 613(D) 0689 |
18" CORR. GALV. STEEL PIPE | 3,316 | LF |
$25.00 |
$38.00 |
$40.83 |
| 56 | 613(D) 4527 |
21" X 15" CORR. GALV. STEEL PIPE ARCH | 488 | LF |
$30.00 |
$40.00 |
$51.23 |
| 57 | 613(D) 4528 |
28" X 20" CORR. GALV. STEEL PIPE ARCH | 333 | LF |
$30.00 |
$50.00 |
$51.92 |
| 58 | 613(MM) 7500 |
TYPE A4 SLOPED CONCRETE END SECTION | 3 | EA |
$1,500.00 |
$2,200.00 |
$2,214.15 |
| 59 | 613(MM) 7520 |
TYPE A6 SLOPED CONCRETE END SECTION | 1 | EA |
$2,000.00 |
$2,900.00 |
$2,214.15 |
| 60 | 613(P) 1091 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 2,105 | LF |
$10.00 |
$9.00 |
$1.54 |
| 61 | 613(Q) 1096 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 702 | LF |
$7.00 |
$9.00 |
$1.54 |
| 62 | 613(S) 1180 |
TRENCH EXCAVATION | 562 | CY |
$10.00 |
$10.00 |
$31.55 |
| 63 | 613(T) 1181 |
STANDARD BEDDING MATERIAL | 281 | CY |
$35.00 |
$45.00 |
$22.13 |
| 64 | 613(U) 4498 |
18" JACKED CONDUIT | 315 | LF |
$500.00 |
$435.00 |
$379.21 |
| 65 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$10,000.00 |
$5,000.00 |
$18,541.57 |
| 66 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 17,538 | SY |
$3.25 |
$2.00 |
$10.77 |
| 67 | 619(C) 0924 |
SAWING PAVEMENT | 23,113 | LF |
$3.00 |
$0.4000 |
$1.62 |
| 68 | 653(C) 5946 |
OUTLET LATERAL HEADWALL | 6 | EA |
$725.00 |
$400.00 |
$834.85 |
| 69 | 859(A) 8006 |
PAVEMENT MARKING REMOVAL(TRAFFIC STRIPE) | 5,000 | LF |
$0.1500 |
$0.3000 |
$0.2700 |
| 70 | 876(C) 8482 |
(PL)TRUCK MOUNTED ATTENUATOR | 360 | SD |
$30.00 |
$90.00 |
$92.73 |
| 71 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 360 | SD |
$3.25 |
$11.00 |
$10.91 |
| 72 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 16,380 | SD |
$0.0500 |
$0.3000 |
$0.2700 |
| 73 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 9,500 | SD |
$0.4000 |
$0.5500 |
$0.5500 |
| 74 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 4,000 | SD |
$0.6000 |
$1.65 |
$1.64 |
| 75 | 880(C) 8842 |
BARRICADES(TYPE III) | 5,400 | SD |
$0.2500 |
$0.5500 |
$0.5500 |
| 76 | 880(C) 8848 |
WING BARRICADES | 720 | SD |
$1.25 |
$2.20 |
$2.18 |
| 77 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 16,200 | SD |
$0.1000 |
$0.1100 |
$0.1100 |
| 78 | 880(E) 8872 |
WARNING LIGHTS(TYPE C) | 5,400 | SD |
$0.0500 |
$0.1100 |
$0.1100 |
| 79 | 880(F) 8878 |
DRUMS | 5,400 | SD |
$0.1000 |
$0.5500 |
$0.5500 |
| 80 | 880(G) 8890 |
CHANNELIZER CONES | 18,000 | SD |
$0.1000 |
$0.2200 |
$0.2200 |
| 81 | 880(L) 8911 |
TRAFFIC SURVEILLANCE, POLICE | 480 | HOUR |
$55.00 |
$35.00 |
$64.80 |
| 82 | 882(B) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 720 | SD |
$13.00 |
$22.00 |
$21.82 |
| 83 | 850(A) 8110 |
SHEET ALUMINUM SIGNS | 745.66 | SF |
$14.00 |
$13.00 |
$13.09 |
| 84 | 851(C) 8330 |
2 1/2" SQUARE TUBE POST | 1,942.5 | LF |
$8.90 |
$8.00 |
$7.64 |
| 85 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 33,855 | LF |
$0.4500 |
$0.5500 |
$0.5500 |
| 86 | 855(B) 8818 |
TRAFFIC STRIPE(PLASTIC)(ARROWS) | 111 | EA |
$77.00 |
$70.00 |
$70.91 |
| 87 | 890(A) 8724 |
(PL)REMOVAL OF EXISTING SIGNS | 114 | EA |
$44.00 |
$30.00 |
$27.27 |
| 88 | 509(A) 0319 |
CLASS AA CONCRETE | 300 | CY |
$350.00 |
$110.00 |
$272.75 |
| 89 | 612(E) 0645 |
INLETS ADJUST TO GRADE | 1 | EA |
$1,500.00 |
$3,000.00 |
$1,566.11 |
| 90 | 628 5110 |
(PL)CABLE END ANCHOR UNIT | 45 | EA |
$1,250.00 |
$2,200.00 |
$1,745.57 |
| 91 | 628 5125 |
HIGH-TENSION CABLE BARRIER(TL-4) | 7,500 | LF |
$11.00 |
$11.00 |
$13.26 |
| 92 | 628 5180 |
INSTALLATION OF CABLE BARRIER SYSTEM | 6,400 | LF |
$3.50 |
$7.00 |
$6.55 |
| 93 | 628 5190 |
REMOVAL OF CABLE BARRIER | 6,400 | LF |
$2.50 |
$1.60 |
$3.27 |
| 94 | 642 0098 |
STAKING | 1 | LSUM |
$25,000.00 |
$20,000.00 |
$33,212.27 |
| 95 | 220 2800 |
(SP)SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$5,000.00 |
$9,302.08 |
| 96 | 640 1426 |
FIELD OFFICE | 1 | EA |
$15,000.00 |
$8,000.00 |
$11,772.81 |
| 97 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$110,000.00 |
$155,000.00 |
$199,613.00 |