Bid tab 100005

Let Jan 28, 2010 · Division 5 · Custer Sign up free

‹ Jan 2010 results

BRIDGE AND APPROACHES COUNTY ROAD (EW-88): OVER EAST BARNITZ CREEK 7.1 MILES NORTH AND 6.5 MILES EAST OF BUTLER . PROJECT LENGTH = 0.189 MILES

Let date
Thursday, January 28, 2010
Contract
100005
J/P numbers
23057(04)
District
Division 5
County
Custer
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EW-88): OVER EAST BARNITZ CREEK 7.1 MILES NORTH AND 6.5 MILES EAST OF BUTLER . PROJECT LENGTH = 0.189 MILES
Project number
BRF-120C(116)CO

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$424,385
1 SEWELL BROS., INC. Low bidder $315,718 -25.6%
2 D. M. DOZERS, INC. $330,596 -22.1% +4.7%
3 K & R BUILDERS, INC. $333,421 -21.4% +5.6%
4 Cimarron Construction Company, LLC $377,958 -10.9% +19.7%
5 EARTH BUILDERS, L.P. $460,018 +8.4% +45.7%
6 Reece Construction Co, Inc. $505,902 +19.2% +60.2%

Bid tab: unit prices 26 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SEWELL BROS., I…#2 D. M. DOZERS, I…#3 K & R BUILDERS,…#4 Cimarron Constr…#5 EARTH BUILDERS,…#6 Reece Construct…
1202(G) 0185 EARTHWORK1LSUM $25,000.00 $13,000.00 $28,500.00 $18,000.00 $36,500.00 $30,000.00 $54,008.16
2223 2801 TEMPORARY SILT FENCE680LF $2.00 $1.50 $2.00 $1.50 $1.35 $2.00 $1.35
3230(A) 2806 SOLID SLAB SODDING7,000SY $2.00 $1.15 $1.50 $1.20 $1.20 $2.00 $1.10
4233(A) 2817 VEGETATIVE MULCHING1.7AC $650.00 $250.00 $300.00 $100.00 $150.00 $350.00 $150.00
5303 5912 AGGREGATE BASE887TON $28.00 $24.00 $23.00 $24.00 $22.25 $30.00 $34.80
6509(D) 0325 CLASS C CONCRETE146.2CY $250.00 $250.00 $200.00 $268.00 $270.00 $340.00 $327.00
7613(CC) 7188 TYPE C4 CULVERT END TREATMENT2EA $1,200.00 $700.00 $750.00 $1,325.00 $1,475.00 $1,800.00 $1,480.00
8613(D) 4530 42" X 29" CORR. GALV. STEEL PIPE ARCH60LF $35.00 $43.00 $32.00 $35.00 $38.00 $75.00 $53.75
9501(B) 1307 SUBSTRUCTURE EXCAVATION COMMON84CY $15.00 $6.00 $8.00 $5.50 $8.00 $10.00 $23.00
10501(D) 6353 UNCLASSIFIED BACKFILL82CY $15.00 $6.00 $10.00 $9.00 $11.00 $15.00 $23.00
11503(A) 1313 PRESTRESSED CONCRETE BEAMS (TYPE IV)316.67LF $185.00 $157.00 $160.00 $166.00 $157.00 $180.00 $223.00
12504(E) 1380 CONCRETE RAIL (TR1)225LF $50.00 $40.00 $45.00 $54.25 $55.00 $65.00 $73.00
13506(A) 1322 STRUCTURAL STEEL1,810LB $1.50 $3.00 $3.00 $3.00 $2.40 $3.50 $4.00
14509(A) 1326 CLASS AA CONCRETE62.5CY $525.00 $400.00 $500.00 $430.00 $503.00 $450.00 $615.00
15509(B) 1328 CLASS A CONCRETE53.8CY $550.00 $400.00 $450.00 $437.50 $503.00 $430.00 $637.00
16511(A) 1332 REINFORCING STEEL21,569LB $0.9000 $0.6500 $0.6800 $0.7200 $0.6500 $0.8000 $0.6000
17514(A) 6010 PILES, FURNISHED (HP 10X42)1,224LF $30.00 $18.00 $20.00 $21.00 $31.55 $25.00 $32.00
18514(B) 6292 PILES, DRIVEN (HP 10X42)1,224LF $15.00 $10.00 $6.00 $6.75 $14.15 $25.00 $6.00
19601(A-1)1353 TYPE I-A PLAIN RIPRAP1,000TON $38.00 $34.00 $32.00 $32.85 $34.00 $43.00 $48.56
20601(A-2)1355 TYPE I-A FILTER BLANKET300TON $32.00 $26.00 $28.00 $26.00 $27.00 $35.00 $38.63
21619(D) 1397 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $10,000.00 $3,500.00 $6,000.00 $2,550.00 $4,800.00 $10,000.00 $12,300.00
22623(F) 6033 GUARD RAIL ANCHOR UNIT (TYPE II)4EA $2,500.00 $1,900.00 $1,800.00 $1,875.00 $1,820.00 $2,100.00 $1,850.00
23880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $5,000.00 $2,750.00 $2,500.00 $2,800.00 $2,525.00 $4,000.00 $2,600.00
24642 0098 STAKING1LSUM $5,000.00 $3,300.00 $4,400.00 $3,450.00 $3,275.00 $6,500.00 $3,150.00
25220 2800 (SP)SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $7,500.00 $2,500.00 $2,000.00 $1,850.00 $4,000.00 $2,500.00 $2,000.00
26641 1399 MOBILIZATION1LSUM $20,000.00 $10,000.00 $4,500.00 $10,500.00 $7,000.00 $35,000.00 $40,300.00