$3,510.31Avg low bid / EA
$3,793.18Avg of all bids
$1,973.47Avg engineer's estimate
15Jobs · 49 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 2 | 7 | $4,191.86 | $4,676.39 |
| 2020 | 7 | 21 | $3,382.58 | $3,911.97 |
| 2019 | 4 | 16 | $3,901.77 | $3,622.92 |
| 2018 | 2 | 5 | $1,840.00 | $2,454.59 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 20, 2021 | 210142 | Nhpp-022n(225)pm | 1 EA | $8,343.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 20, 2021 | 210136 | HughesDivision 3 | 6 EA | $3,500.00 | C-GAWF CONSTRUCTION, INC. |
| Nov 19, 2020 | 200355 | RogersDivision 8 | 2 EA | $6,050.00 | EMERY SAPP & SONS, INC. |
| Aug 20, 2020 | 200225 | GradyDivision 7 | 4 EA | $2,675.00 | SEWELL BROS., INC. |
| Apr 16, 2020 | 200028 | Cirb-264d(069)rb | 8 EA | $3,239.50 | THE CUMMINS CONSTRUCTION CO., INC. |
| Mar 19, 2020 | 200133 | HaskellDivision 1 | 2 EA | $3,709.08 | C3 Construction, Inc. |
| Jan 16, 2020 | 200001 | AlfalfaDivision 6 | 2 EA | $1,725.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Jan 16, 2020 | 200020 | NobleDivision 4 | 2 EA | $3,775.00 | Evans & Associates Construction Co., Inc. |
| Jan 16, 2020 | 200092 | TulsaDivision 8 | 1 EA | $3,900.00 | APAC-CENTRAL, INC. |
| Oct 17, 2019 | 190335 | TulsaDivision 8 | 4 EA | $3,979.60 | Tri Star Construction Arkansas, LLC |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 4 EA | $3,513.96 | DUIT CONSTRUCTION COMPANY, INC. |
| May 16, 2019 | 180277 | BlaineDivision 5 | 6 EA | $4,309.00 | HASKELL LEMON CONSTRUCTION CO. |
| Jan 17, 2019 | 190001 | AtokaDivision 2 | 2 EA | $3,300.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Nov 15, 2018 | 180354 | Cirb-225c(074)rb | 2 EA | $2,935.00 | OVERLAND CORPORATION |
| Jun 14, 2018 | 180225 | Stp-231c(033)ci | 4 EA | $1,800.00 | T. McDonald Construction, Inc. |
| Jan 18, 2018 | 180030 | RogersDivision 8 | 1 EA | $2,000.00 | BECCO CONTRACTORS, INC. |